Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
1
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.NS1.02780 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 06/08/26 07/06/26 25.0 25.0
0%
33.8
RPL10.INT.NS2.02605 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (Mech Side Aisle) OFE NS2 Control Fault Domain 4 Not Started 06/08/26 06/24/26 16.2 16.2
0%
-11.2
RPL10.INT.NS3.01230 RPL10.Interior.NS3 - Control Fault Domain 1 SQ7.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/08/26 06/12/26 6.2 6.2
0%
121.2
RPL10.INT.NS4.01114 RPL10.Interior.NS4 - MES Skids - BMS Tie-Ins NS4 - MES Skids Not Started 06/08/26 07/10/26 30.0 30.0
0%
237.5
RPL10.INT.NS4.01490 RPL10.Interior.NS4 - OFE - Control Fault Domain 4 SQ10.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS4 Control Fault Domain 4 Not Started 06/08/26 10/06/26 106.2 106.2
0%
68.8
RPL10.INT.NS4.01510 RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/08/26 06/11/26 5.0 5.0
0%
176.2
RPL10.INT.NS4.02660 RPL10.Interior.NS4 - OFE - Control Fault Domain 4 SQ10.1 (LV Side Aisle) OFE NS4 Control Fault Domain 4 Not Started 06/08/26 06/11/26 5.0 5.0
0%
157.5
RPL10.OFCI.7000 OFCI - Delivery ROJ: FE Fiber for CFD NS2.3 (ROJ ) (RVCD ) NS2 Not Started 06/08/26 06/26/26 18.8 18.8
0%
87.5
RPL10.OFCI.7020 OFCI - Delivery ROJ: FE Fiber for CFD NS2.2 (ROJ ) (RVCD ) NS2 Not Started 06/08/26 06/26/26 18.8 18.8
0%
111.2
RPL10.WP2.01060 RPL10.Conn CorpNet & FacNet Live WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 06/08/26 06/08/26 0.0 0.0
0%
56.2
RPL10.WP4.027500 RPL10.Conn NS1.CFD5.48<>21-25 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/08/26 06/11/26 5.0 5.0
0%
136.2
RPL10.WP4.027700 RPL10.Conn NS1.CFD4.48<>21-25 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/08/26 06/11/26 5.0 5.0
0%
136.2
RPL10.WP4.028500 RPL10.Conn NS2.CFD6.48<>21-25 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/08/26 06/11/26 5.0 5.0
0%
147.5
RPL10.WP4.028700 RPL10.Conn NS2.CFD5.48<>21-25 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/08/26 06/11/26 5.0 5.0
0%
147.5
RPL10.WP4.028820 RPL10.Conn NS2.CFD4.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/08/26 06/09/26 2.5 2.5
0%
130.0
RPL10.WP4.NS2.01640 RPL10.Conn NS2.CFD4 Network - WBS Summary Network Not Started 06/08/26 11/10/26 137.5 137.5
0%
60.0
DCC.B10.3557 [NWB] Cabling Start : Front End Production Cabling [NWS 4] Connectivity Not Started 06/09/26 06/09/26 0.0 0.0
0%
866.2
DCC.B10.3559 [NWB] Cabling Start : Back End Production Cabling [NWS 4] Connectivity Not Started 06/09/26 06/09/26 0.0 0.0
0%
866.2
GCD.RPL10.3528 [RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 9-16] TC Ready: Production Cabling - NS1 Not Started 06/09/26 06/09/26 0.0 0.0
0%
36.2
GCD.RPL10.5825 RMU Loop Ready for Energization - NS2 Loop 2 EY Not Started 06/09/26 06/09/26 0.0 0.0
0%
62.5
RPL.10.D.X3730.XG RMUs/MV Skids Set (Loop 1) - RPL10 NS4 Give Milestones (XREFs) Not Started 06/09/26 06/09/26 0.0 0.0
0%
865.0
RPL.10.D.X3735.XG RMUs/MV Skids Set (Loop 2) - RPL10 NS4 Give Milestones (XREFs) Not Started 06/09/26 06/09/26 0.0 0.0
0%
865.0
RPL10.EY.NS2.01340 RPL10.EY.NS2 - Install Lighting Hardscape and Landscape Not Started 06/09/26 06/22/26 12.5 12.5
0%
181.2
RPL10.INT.EF1.01270 RPL10.Interior.EF1 - North CRAH Gallery - Pull EPMS / BMS from panel to devices North CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01280 RPL10.Interior.EF1 - North CRAH Gallery - Fire Life Safety North CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
177.5
RPL10.INT.EF1.01290 RPL10.Interior.EF1 - North CRAH Gallery - Install copper from GS.IDF to BMS and EPMS panels North CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01340 RPL10.Interior.EF1 - South CRAH Gallery - Pull EPMS / BMS from panel to devices South CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01350 RPL10.Interior.EF1 - South CRAH Gallery - Fire Life Safety South CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
177.5
RPL10.INT.EF1.01360 RPL10.Interior.EF1 - South CRAH Gallery - Install copper from GS.IDF to BMS and EPMS panels South CRAH Gallery Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01520 RPL10.Interior.EF1 - EF1 West - Pull EPMS / BMS from panel to devices West EF-1 Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01530 RPL10.Interior.EF1 - EF1 West - Install copper from GS.IDF to BMS and EPMS panels West EF-1 Not Started 06/09/26 06/15/26 6.2 6.2
0%
110.0
RPL10.INT.EF1.01540 RPL10.Interior.EF1 - EF1 West - Fire Life Safety West EF-1 Not Started 06/09/26 06/17/26 8.8 8.8
0%
175.0
RPL10.INT.EF1.01610 RPL10.Interior.EF1 - North CRAH Gallery - Piping Tie-ins FW (In Gallery #3 CRAH Units) North CRAH Gallery Not Started 06/09/26 06/19/26 11.2 11.2
0%
87.5
RPL10.INT.NS2.01200 RPL10.Conn NS2.CFD6 - Set Passive Racks for WP3B Infrastructure Not Started 06/09/26 06/11/26 3.8 3.8
0%
40.0
RPL10.INT.NS2.01390 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install Copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/26 07/07/26 25.0 25.0
0%
18.8
RPL10.INT.NS2.01410 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/26 07/07/26 25.0 25.0
0%
22.5
RPL10.INT.NS2.01420 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/26 07/07/26 25.0 25.0
0%
16.2
RPL10.INT.NS2.02220 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/26 07/07/26 25.0 25.0
0%
16.2
RPL10.INT.NS2.02845 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/26 07/07/26 25.0 25.0
0%
16.2
RPL10.INT.NS2.02925 RPL10.Conn NS2.CFD6 - Set Passive Racks for PON Infrastructure Not Started 06/09/26 06/11/26 3.8 3.8
0%
161.2
RPL10.INT.NS3.01113 RPL10.Interior.NS3 - MES Skids - CDU Tie-Ins NS3 - MES Skids Not Started 06/09/26 07/13/26 30.0 30.0
0%
240.0
RPL10.INT.NS3.01210 RPL10.Interior.NS3 - OFE - Control Fault Domain 2 SQ8.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS3 Control Fault Domain 2 Not Started 06/09/26 09/30/26 100.0 100.0
0%
3.8
RPL10.INT.NS3.01250 RPL10.Interior.NS3 - Control Fault Domain 1 SQ7.2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/09/26 06/15/26 6.2 6.2
0%
121.2
RPL10.INT.NS3.02560 RPL10.Interior.NS3 - OFE - Control Fault Domain 2 SQ8.2 (LV Side Aisle) OFE NS3 Control Fault Domain 2 Not Started 06/09/26 06/12/26 5.0 5.0
0%
88.8
RPL10.INT.NS4.01530 RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/09/26 06/12/26 5.0 5.0
0%
176.2
RPL10.INT.SSB.03040 RPL10.SKIN.SSB - Install Metal Canopy Glazing, Doors and Ext Devices Not Started 06/09/26 06/10/26 2.5 2.5
0%
155.0
RPL10.MCUP.LP2.2400 RPL10.MCUP.Loop 2 - Install Bollards Hardscape and Landscape Not Started 06/09/26 06/17/26 8.8 8.8
0%
462.5
RPL10.SKN.SSB.01410 RPL10.SKIN.BLDG - Install Lightning Protection Skin Not Started 06/09/26 06/15/26 6.2 6.2
0%
307.5
RPL10.SSB.BB.1960 RPL10.Ext.Build Back.SSB - LO #5 - Final Punch Walk Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 06/09/26 06/10/26 2.5 2.5
0%
437.5
RPL10.WP2.GSIDF.1740 RPL10.Conn GSIDFN43 Install & Test Network (FIM) Network Not Started 06/09/26 06/11/26 3.8 3.8
0%
208.8
RPL10.WP2.GSIDF.1980 RPL10.Conn GSIDFN33 Install & Test Network (FIM) Network Not Started 06/09/26 06/11/26 3.8 3.8
0%
208.8
RPL10.WP2.GSIDF.2340 RPL10.Conn IDF Huts - (GSMDF to GSIDF) SSB NX05 WBS Summary GSIDFNX05 Not Started 06/09/26 06/25/26 16.2 16.2
0%
455.0
RPL10.WP2.GSIDF.2360 RPL10.Conn GSIDFNX05 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 06/09/26 06/15/26 6.2 6.2
0%
196.2
RPL10.WP2.GSIDF.2480 RPL10.Conn GSIDFNX06 Install & Test Network (FIM) Network Not Started 06/09/26 06/11/26 3.8 3.8
0%
208.8
RPL10.WP2.GSIDF.2550 RPL10.Conn GSIDFNX07 Install & Test Network (FIM) Network Not Started 06/09/26 06/11/26 3.8 3.8
0%
208.8
RPL10.WP2.GSIDF.3200 RPL10.Conn GSIDFN43 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 06/09/26 06/24/26 15.0 15.0
0%
456.2
RPL10.WP2.GSIDF.3260 RPL10.Conn GSIDFN33 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 06/09/26 06/24/26 15.0 15.0
0%
456.2
RPL10.WP2.GSIDF.3380 RPL10.Conn GSIDFNX06 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 06/09/26 06/11/26 3.8 3.8
0%
467.5
RPL10.WP2.GSIDF.3400 RPL10.Conn GSIDFNX07 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 06/09/26 06/11/26 3.8 3.8
0%
467.5
RPL10.WP3A.EF.03000 RPL10.Conn EF1B Infrastructure - WBS Summary Infrastructure & Cabling Not Started 06/09/26 07/21/26 37.5 37.5
0%
183.8
RPL10.WP3A.EF.03020 RPL10.Conn EF1B Infrasturcture 1 (Racks & Vertical Cable Manager,Ladder Racks) Infrastructure & Cabling Not Started 06/09/26 07/07/26 25.0 25.0
0%
121.2
RPL10.WP3A.EF.04000 RPL10.Conn EF1B OSP Pathway - WBS Summary Infrastructure & Cabling Not Started 06/09/26 07/21/26 37.5 37.5
0%
183.8
RPL10.WP4.027300 RPL10.Conn NS1.CFD6.48<>21-25 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/09/26 06/12/26 5.0 5.0
0%
135.0
RPL10.WP4.027840 RPL10.Conn NS1.CFD3.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/09/26 06/11/26 3.8 3.8
0%
120.0
RPL10.WP4.08840 RPL10.Conn NS2.CFD6 Pull/Install Ext. Trunk (384F) [JXSW<>MA] [MA<>JXSW] Not Started 06/09/26 06/16/26 7.5 7.5
0%
188.8
RPL10.WP4.NS2.01040 RPL10.Conn NS2.CFD6 Infrastructure - WBS Summary Infrastructure Not Started 06/09/26 06/22/26 12.5 12.5
0%
71.2
RPL10.WP4.NS2.01060 RPL10.Conn NS2.CFD6 Infrastructure Infrastructure Not Started 06/09/26 06/22/26 12.5 12.5
0%
71.2
RPL10.EY.EF1.01230 RPL10.EY.EF1 - Install RPL-2 FSP Grounding Wire Fiber Support Platform - RPL-2 Not Started 06/10/26 06/11/26 2.5 2.5
0%
255.0
RPL10.EY.EF1.01420 RPL10.EY.EF1 - Install RPL-2 FSP Interior Hilti Support & Cable Trays Fiber Support Platform - RPL-2 Not Started 06/10/26 06/25/26 15.0 15.0
0%
242.5
RPL10.EY.EF1.01720 RPL10.EY.EF1 - Install RPL-2 FSP Final Roof (Standing Seam Panels) Phase 2 Fiber Support Platform - RPL-2 Not Started 06/10/26 06/16/26 6.2 6.2
0%
242.5
RPL10.EY.NS4.01240 RPL10.EY.NS4 - Install GS.IDF Hut (1x GS.IDF) NX03 (05.29.26) OFE Not Started 06/10/26 06/16/26 6.2 6.2
0%
107.5
RPL10.EY.NS4.01250 RPL10.EY.NS4 - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 06/10/26 06/23/26 12.5 12.5
0%
107.5
RPL10.EY.NS4.01260 RPL10.EY.NS4 - Tie-ins - WBS Summary Tie-ins Not Started 06/10/26 07/29/26 43.8 43.8
0%
165.0
RPL10.INT.EF2.01460 RPL10.Interior.EF2 - EF2 East - Set Passive Panels / Racks East EF-2 Not Started 06/10/26 06/16/26 6.2 6.2
0%
187.5
RPL10.INT.NS1.01420 RPL10.Conn NS1.CFD5 - Set Passive Racks for WP3B Infrastructure Not Started 06/10/26 06/12/26 3.8 3.8
0%
32.5
RPL10.INT.NS1.02860 RPL10.Conn NS1.CFD5 - Set Passive Racks for PON Infrastructure Not Started 06/10/26 06/12/26 3.8 3.8
0%
148.8
RPL10.INT.NS4.01550 RPL10.Interior.NS4 - Control Fault Domain 4 SQ10.1 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/10/26 06/15/26 5.0 5.0
0%
162.5
RPL10.INT.NS4.01580 RPL10.Interior.NS4 - Tie-ins - Control Fault Domain 4 SQ10.1 - WBS Summary Tie-Ins NS4 Control Fault Domain 4 Not Started 06/10/26 11/13/26 137.5 137.5
0%
78.8
RPL10.INT.SSB.01570 RPL10.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion Loading Dock and Storage Not Started 06/10/26 06/23/26 12.5 12.5
0%
173.8
RPL10.INT.SSB.02960 RPL10.Interior.SSB - Loading Dock and Storage - Install Flooring / Carpet Tile Loading Dock and Storage Not Started 06/10/26 06/16/26 6.2 6.2
0%
178.8
RPL10.OFCI.6920 OFCI - Delivery ROJ: FE Fiber for CFD NS1.1 (ROJ ) (RVCD ) NS1 Not Started 06/10/26 06/30/26 18.8 18.8
0%
97.5
RPL10.WP4.01220 RPL10.Conn NS1.CFD5.09 Pull Duplex Jumper (LC<>LC) [MA<>JXSW] Pull Duplex Jumper [MA<>JXSW] Not Started 06/10/26 06/12/26 3.8 3.8
0%
146.2
RPL10.WP4.028840 RPL10.Conn NS2.CFD4.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 06/10/26 06/12/26 3.8 3.8
0%
130.0
RPL10.WP4.NS1.02440 RPL10.Conn NS1.CFD5 Infrastructure - WBS Summary Infrastructure Not Started 06/10/26 06/15/26 5.0 5.0
0%
51.2
RPL10.WP4.NS1.02460 RPL10.Conn NS1.CFD5 Infrastructure Infrastructure Not Started 06/10/26 06/15/26 5.0 5.0
0%
51.2
RPL.GF.D.N0105.XG GS.EF2 Infrastructure Ready RPL10 Give Milestones (XREFs) Not Started 06/11/26 06/11/26 0.0 0.0
0%
862.5
RPL.GF.D.N0290.XR Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI2 Connectivity (XREFs) Not Started 06/11/26 06/11/26 0.0 0.0
0%
156.2
RPL10.CTRC.BB.3495 RPL10.Int.Build Back.Center-Corr - LO #8 - Tape, Float and Paint Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 06/11/26 06/17/26 6.2 6.2
0%
142.5
RPL10.CTRC.BB.3515 RPL10.Int.Build Back.Center-Corr - LO #7 - Install Remaining Hilti Steel Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) Not Started 06/11/26 06/15/26 3.8 3.8
0%
147.5
RPL10.CTRC.BB.3655 RPL10.Int.Build Back.Center-Corr - LO #9 - MEPF - In Wall Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) Not Started 06/11/26 06/15/26 3.8 3.8
0%
141.2
RPL10.INT.NS3.01270 RPL10.Interior.NS3 - Control Fault Domain 2 SQ8.2 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/11/26 06/16/26 5.0 5.0
0%
91.2
RPL10.INT.NS3.01300 RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 2 SQ8.2 - WBS Summary Tie-Ins NS3 Control Fault Domain 2 Not Started 06/11/26 11/16/26 137.5 137.5
0%
51.2
RPL10.INT.SSBC.01430 RPL10.Interior.SSB-Corridor - BoW - Final Punch Walk Balance of Walls & OverHead Not Started 06/11/26 06/12/26 2.5 2.5
0%
123.8
RPL10.WP4.NS1.01040 RPL10.Conn NS1.CFD6 Infrastructure - WBS Summary Infrastructure Not Started 06/11/26 06/16/26 5.0 5.0
0%
70.0
RPL10.WP4.NS1.01060 RPL10.Conn NS1.CFD6 Infrastructure Infrastructure Not Started 06/11/26 06/16/26 5.0 5.0
0%
70.0
RPL10.CX.CTRC.01000 RPL10.CX.Center COR - L3, L4, IST - WBS Summary Center Corridor Not Started 06/12/26 08/21/26 62.5 62.5
0%
125.0
RPL10.CX.CTRC.01010 RPL10.CX.Center COR - L3 Center Corridor Not Started 06/12/26 07/24/26 37.5 37.5
0%
125.0
RPL10.INT.CTRC.01470 RPL10.Interior.Center-Corridor - BoW - Final Clean Balance of Walls & OverHead Not Started 06/12/26 06/17/26 5.0 5.0
0%
180.0
RPL10.INT.CTRC.01510 RPL10.Interior.Center-Corridor - BoW - Remaining L2 Checklist Completion Balance of Walls & OverHead Not Started 06/12/26 06/18/26 6.2 6.2
0%
162.5
RPL10.INT.NS4.01630 RPL10.Interior.NS4 - OFE - Control Fault Domain 5 SQ11.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS4 Control Fault Domain 5 Not Started 06/12/26 10/20/26 113.8 113.8
0%
66.2