Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
4
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.NS4.01300 |
RPL10.Interior.NS4 - Tie-ins - Control Fault Domain 2 SQ8.1 - WBS Summary | Tie-Ins NS4 Control Fault Domain 2 | Not Started | 05/29/26 | 10/22/26 | 128.8 | 128.8 |
|
58.8 |
RPL.CM.D.C5480.XR |
Leia Lane | Logistics - Onsite Receive XREF Milestones | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
873.8 |
RPL10.Conn.MS.01490 |
Wifi Ready - mCUP Yard | Connectivity Milestones | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
477.5 |
RPL10.INT.EF2.01430 |
RPL10.Interior.EF2 - EF2 East - Pull EPMS / BMS from panel to devices | East EF-2 | Not Started | 06/01/26 | 06/05/26 | 6.2 | 6.2 |
|
128.8 |
RPL10.INT.EF2.01440 |
RPL10.Interior.EF2 - EF2 East - Install copper from GS.IDF to BMS and EPMS panels | East EF-2 | Not Started | 06/01/26 | 06/05/26 | 6.2 | 6.2 |
|
128.8 |
RPL10.INT.EF2.01450 |
RPL10.Interior.EF2 - EF2 East - Fire Life Safety | East EF-2 | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
193.8 |
RPL10.INT.NS1.01205 |
RPL10.Interior.NS1 - MES Skids - EPMS Tie-Ins | NS1 - MES Skids | Not Started | 06/01/26 | 07/02/26 | 30.0 | 30.0 |
|
140.0 |
RPL10.INT.NS1.01590 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/01/26 | 06/26/26 | 25.0 | 25.0 |
|
43.8 |
RPL10.INT.NS1.01620 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center ID | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/01/26 | 06/26/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS3.01093 |
RPL10.Interior.NS3 - LV Skids and TopHat - Top Hat Busway | NS3 - LV Skids and TopHat | Not Started | 06/01/26 | 06/19/26 | 18.8 | 18.8 |
|
171.2 |
RPL10.INT.SSB.01430 |
RPL10.Interior.SSB - Loading Dock and Storage - Electrical Trim Out | Loading Dock and Storage | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.01460 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Lighting and Devices | Loading Dock and Storage | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.01480 |
RPL10.Interior.SSB - Loading Dock and Storage - Security Trim Out | Loading Dock and Storage | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.01540 |
RPL10.Interior.SSB - Loading Dock and Storage - Fire Life Safety Trim Out / Fire Alarm Trim Out | Loading Dock and Storage | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.06040 |
RPL10.Interior.SSB - Loading Dock Area - Electrical Panels | Loading Dock and Storage | Not Started | 06/01/26 | 06/09/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.SSBC.BB.1180 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Final Clean | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
178.8 |
GCD.RPL10.5805 |
RMU Loop Ready for Energization - NS2 Loop 1 | EY | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
27.5 |
JCL.C.1320 |
RPL10 - Cost Risk LOE-17 Site | Cost LOEs | Not Started | 06/02/26 | 02/23/27 | 227.5 | 227.5 |
|
250.0 |
RPL10.Conn.MS.02210 |
FacNet Ready @ NS1-EY IDFs | Connectivity Milestones | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
217.5 |
RPL10.Conn.MS.02290 |
FacNet Ready @ MCUP IDFs | Connectivity Milestones | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
217.5 |
RPL10.EY.EF2.01210 |
RPL10.EY.EF2 - Install RPL-3 FSP Road Closure For Steel Erection | Fiber Support Platform - RPL-3 | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
202.5 |
RPL10.EY.NS2.01330 |
RPL10.EY.NS2 - Install Early EY Paving | Hardscape and Landscape | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.INT.EF1.01220 |
RPL10.Interior.EF1 - North CRAH Gallery - Install Lower Trays | North CRAH Gallery | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01300 |
RPL10.Interior.EF1 - South CRAH Gallery - Install Lower Trays | South CRAH Gallery | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01500 |
RPL10.Interior.EF1 - EF1 West - Install Lower Trays | West EF-1 | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01510 |
RPL10.Interior.EF1 - EF1 West - Install Lighting | West EF-1 | Not Started | 06/02/26 | 06/17/26 | 15.0 | 15.0 |
|
107.5 |
RPL10.INT.EF1.01670 |
RPL10.Interior.EF1 - North CRAH Gallery - Install Duct Drops & GRD's | North CRAH Gallery | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
87.5 |
RPL10.INT.EF1.01710 |
RPL10.Interior.EF1 - South CRAH Gallery - Install Duct Drops & GRD's | South CRAH Gallery | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
110.0 |
RPL10.INT.NS1.02600 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (HAC) | OFE NS1 Control Fault Domain 3 | Not Started | 06/02/26 | 06/22/26 | 18.8 | 18.8 |
|
-5.0 |
RPL10.INT.NS2.01360 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/02/26 | 06/29/26 | 25.0 | 25.0 |
|
18.8 |
RPL10.INT.NS3.01120 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 1 SQ7.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS3 Control Fault Domain 1 | Not Started | 06/02/26 | 09/16/26 | 93.8 | 93.8 |
|
0.0 |
RPL10.INT.NS3.02500 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 1 SQ7.2 (LV Side Aisle) | OFE NS3 Control Fault Domain 1 | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
75.0 |
RPL10.INT.NS4.01350 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 3 SQ9.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS4 Control Fault Domain 3 | Not Started | 06/02/26 | 09/22/26 | 98.8 | 98.8 |
|
48.8 |
RPL10.INT.NS4.01370 |
RPL10.Interior.NS4 - Control Fault Domain 2 SQ8.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
146.2 |
RPL10.INT.NS4.02600 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 3 SQ9.1 (LV Side Aisle) | OFE NS4 Control Fault Domain 3 | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
128.8 |
RPL10.MCUP.LP1.2100 |
RPL10.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
465.0 |
RPL10.SKN.SSB.01390 |
RPL10.SKIN.BLDG - Install Coping | Skin | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
307.5 |
RPL10.WP2.GSIDF.2460 |
RPL10.Conn GSIDFNX06 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.WP2.GSIDF.2540 |
RPL10.Conn GSIDFNX07 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.WP4.027480 |
RPL10.Conn NS1.CFD5.48<>16-20 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.WP4.027680 |
RPL10.Conn NS1.CFD4.48<>16-20 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.WP4.028480 |
RPL10.Conn NS2.CFD6.48<>16-20 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
147.5 |
RPL10.WP4.028680 |
RPL10.Conn NS2.CFD5.48<>16-20 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
147.5 |
FR03.1240 |
FR03: PSI - NS1 - PCX H01 & H02 - Install | FR03: House Power Skid Missing Panel Delay | Not Started | 06/03/26 | 06/05/26 | 3.8 | 3.8 |
|
15.0 |
FR03.1360 |
FR03: PSI - NS2 - PCX H01 & H02 - Install | FR03: House Power Skid Missing Panel Delay | Not Started | 06/03/26 | 06/05/26 | 3.8 | 3.8 |
|
15.0 |
ICM.B10.1212 |
[NWB] Start Fill & Flush of Chilled Water System | Commissioning | Not Started | 06/03/26 | 06/03/26 | 0.0 | 0.0 |
|
67.5 |
RPL.10.D.X4210.XR |
FW Water Available for mCUP Flush/Fill - Utility connections | Water / Gas Available (XREFs) | Not Started | 06/03/26 | 06/03/26 | 0.0 | 0.0 |
|
26.2 |
RPL.10.D.X4410.XR |
Discharge Available for Fill/Flush Cx - Utility connections | Water / Gas Available (XREFs) | Not Started | 06/03/26 | 06/03/26 | 0.0 | 0.0 |
|
26.2 |
RPL10.CTRC.BB.3415 |
RPL10.Int.Build Back.Center-Corr - LO #6 - Install Remaining Cable Tray on Hilti Steel | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/03/26 | 06/05/26 | 3.8 | 3.8 |
|
152.5 |
RPL10.CTRC.BB.3455 |
RPL10.Int.Build Back.Center-Corr - LO #8 - MEPF - In Wall | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/03/26 | 06/05/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.CX.MCUP.01150 |
RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (Phase 1) | Fill and Flush | Not Started | 06/03/26 | 06/12/26 | 10.0 | 10.0 |
|
26.2 |
RPL10.EY.EF1.01320 |
RPL10.EY.EF1 - Install RPL-2 FSP Floor Grating | Fiber Support Platform - RPL-2 | Not Started | 06/03/26 | 06/16/26 | 12.5 | 12.5 |
|
242.5 |
RPL10.EY.EF1.01370 |
RPL10.EY.EF1 - Install RPL-2 FSP Final Roof (Standing Seam Panels) Phase 1 | Fiber Support Platform - RPL-2 | Not Started | 06/03/26 | 06/09/26 | 6.2 | 6.2 |
|
242.5 |
RPL10.EY.EF1.01380 |
RPL10.EY.EF1 - Install RPL-1 FSP Interior Hilti Support & Cable Trays | Fiber Support Platform - RPL-1 | Not Started | 06/03/26 | 06/18/26 | 15.0 | 15.0 |
|
248.8 |
RPL10.INT.NS2.02585 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (HAC) | OFE NS2 Control Fault Domain 4 | Not Started | 06/03/26 | 06/23/26 | 18.8 | 18.8 |
|
-18.8 |
RPL10.INT.NS4.01390 |
RPL10.Interior.NS4 - Control Fault Domain 2 SQ8.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/03/26 | 06/08/26 | 5.0 | 5.0 |
|
146.2 |
RPL10.SSB.BB.1920 |
RPL10.Ext.Build Back.SSB - LO #5 - Final Clean | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 06/03/26 | 06/08/26 | 5.0 | 5.0 |
|
437.5 |
RPL10.WP4.027280 |
RPL10.Conn NS1.CFD6.48<>16-20 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/03/26 | 06/08/26 | 5.0 | 5.0 |
|
135.0 |
DCC.B10.3145 |
[NWB] GS Gear Delivered [NWS 3] | Connectivity | Not Started | 06/04/26 | 06/04/26 | 0.0 | 0.0 |
|
870.0 |
DCC.B10.3245 |
[NWB] CorpNet/Security/FacNet Ready [NWS 3] | Connectivity | Not Started | 06/04/26 | 06/04/26 | 0.0 | 0.0 |
|
331.2 |
DCC.B10.3255 |
[NWB] CorpNet/Security/FacNet Ready [NWS 4] | Connectivity | Not Started | 06/04/26 | 06/04/26 | 0.0 | 0.0 |
|
331.2 |
RPL10.INT.ENDC.1760 |
RPL10.Interior.End-Corridor - BoW - Install Flooring Tiles/Resinous Flooring in specific rooms | Balance of Walls & Overhead | Not Started | 06/04/26 | 06/15/26 | 10.0 | 10.0 |
|
183.8 |
RPL10.INT.NS3.01130 |
RPL10.Interior.NS3 - Control Fault Domain 1 SQ7.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/04/26 | 06/10/26 | 6.2 | 6.2 |
|
90.0 |
RPL10.INT.NS3.01160 |
RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 1 SQ7.2 - WBS Summary | Tie-Ins NS3 Control Fault Domain 1 | Not Started | 06/04/26 | 11/10/26 | 140.0 | 140.0 |
|
45.0 |
RPL10.INT.NS4.01410 |
RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/04/26 | 06/09/26 | 5.0 | 5.0 |
|
145.0 |
RPL10.INT.NS4.01440 |
RPL10.Interior.NS4 - Tie-ins - Control Fault Domain 3 SQ9.1 (including IDF) - WBS Summary | Tie-Ins NS4 Control Fault Domain 3 | Not Started | 06/04/26 | 11/10/26 | 140.0 | 140.0 |
|
57.5 |
RPL.10.D.X33X2.XR |
Pull and Term MV Skids - RPL10 NS2 Loop 1 & 2 | Power (XREFs) | Not Started | 06/05/26 | 06/05/26 | 0.0 | 0.0 |
|
23.8 |
RPL.10.D.X33X6.XR |
Cable Pull to Concrete Pad - RPL10 NS3 Loop 1 & 2 | Power (XREFs) | Not Started | 06/05/26 | 06/05/26 | 0.0 | 0.0 |
|
23.8 |
RPL10.INT.NS1.02620 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (Mech Side Aisle) | OFE NS1 Control Fault Domain 3 | Not Started | 06/05/26 | 06/23/26 | 16.2 | 16.2 |
|
0.0 |
RPL10.INT.SSB.01550 |
RPL10.Interior.SSB - BoW - Install TVs and Conf Sound | Balance of Walls and OverHead | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
191.2 |
RPL10.INT.SSB.01560 |
RPL10.Interior.SSB - BoW - Install Asset Tags & QC | Balance of Walls and OverHead | Not Started | 06/05/26 | 06/15/26 | 8.8 | 8.8 |
|
147.5 |
RPL10.INT.SSBC.01420 |
RPL10.Interior.SSB-Corridor - BoW - Final Clean | Balance of Walls & OverHead | Not Started | 06/05/26 | 06/10/26 | 5.0 | 5.0 |
|
123.8 |
RPL10.SSBC.BB.1160 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Final Punch Walk | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
178.8 |
RPL10.WP4.027820 |
RPL10.Conn NS1.CFD3.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
120.0 |
RPL10.WP4.NS1.02140 |
RPL10.Conn NS1.CFD3 Network - WBS Summary | Network | Not Started | 06/05/26 | 11/17/26 | 143.8 | 143.8 |
|
43.8 |
FR03.1260 |
FR03: PSI - NS1 - PCX H01 & H02 - FTI Complete Terminations for H01 & H02 | FR03: House Power Skid Missing Panel Delay | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
15.0 |
FR03.1380 |
FR03: PSI - NS2 - PCX H01 & H02 - FTI Complete Terminations for H01 & H02 | FR03: House Power Skid Missing Panel Delay | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
15.0 |
GCD.RPL10.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
142.5 |
GCD.RPL10.4065 |
[RPL10] TC Ready: Production Cabling Pathways Complete [NS2 Rows 1-8] | TC Ready: Production Cabling - NS2 | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
43.8 |
ICM.B10.2530 |
[NWB] L3/L4 Start EY - NS1 | Commissioning | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
170.0 |
RPL.10.D.X3910.XG |
GS.MDF / GS Cabling Completed for Campus FacNet Live Distribution (Aux Bldgs) | Give Milestones (XREFs) | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
866.2 |
RPL.10.D.X3920.XG |
GS.MDF / GS Cabling Completed for Campus FacNet Live Distribution (AI Bldgs) | Give Milestones (XREFs) | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
866.2 |
RPL.GF.D.N0260.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL7 | Connectivity (XREFs) | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
217.5 |
RPL10.CTRC.BB.3355 |
RPL10.Int.Build Back.Center-Corr - LO #7 - Hang IMP | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 06/08/26 | 06/10/26 | 3.8 | 3.8 |
|
147.5 |
RPL10.CTRC.BB.3475 |
RPL10.Int.Build Back.Center-Corr - LO #8 - Hang Drywall | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/08/26 | 06/10/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.CTRC.BB.3635 |
RPL10.Int.Build Back.Center-Corr - LO #9 - Frame | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 06/08/26 | 06/10/26 | 3.8 | 3.8 |
|
141.2 |
RPL10.CX.MCUP.01040 |
RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - FWM | mCup Loop 1 (mCup #1,#3,#5,#7) | Not Started | 06/08/26 | 06/19/26 | 12.5 | 12.5 |
|
30.0 |
RPL10.CX.NS1.01000 |
RPL10.CX.NS1 - L3, L4, IST - WBS Summary | NS1 | Not Started | 06/08/26 | 02/12/27 | 215.0 | 215.0 |
|
640.0 |
RPL10.CX.NS1.01010 |
RPL10.CX.NS1 - L3/L4 - WBS Summary (Electrical) | NS1 ELECTRICAL | Not Started | 06/08/26 | 10/28/26 | 126.2 | 126.2 |
|
36.2 |
RPL10.CX.NS1.01020 |
RPL10.CX.NS1 - L3/L4 - MV Skids (8) Loop 2 | NS1 ELECTRICAL | Not Started | 06/08/26 | 06/17/26 | 10.0 | 10.0 |
|
12.5 |
RPL10.Conn.MS.02230 |
FacNet Ready @ NS2-EY IDFs | Connectivity Milestones | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
212.5 |
RPL10.INT.EF2.01110 |
RPL10.Interior.EF2 - Priority OH - Controls / EPMS / BMS | OverHead | Not Started | 06/08/26 | 06/11/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.INT.EF2.01180 |
RPL10.Interior.EF2 - North CRAH Gallery - Install Upper Trays | North CRAH Gallery | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.EF2.01220 |
RPL10.Interior.EF2 - South CRAH Gallery - Install Upper Trays | South CRAH Gallery | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.EF2.01480 |
RPL10.Interior.EF2 - EF2 West - Install Upper Trays | West EF-2 | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.ENDC.01320 |
RPL10.Interior.End-Corridor - BoW - Install Toilet Accessories | Balance of Walls & Overhead | Not Started | 06/08/26 | 06/16/26 | 8.8 | 8.8 |
|
207.5 |
RPL10.INT.NS1.01640 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS1.01650 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
33.8 |
RPL10.INT.NS1.01710 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS1.02260 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
33.8 |