Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL.GF.D.N0155.XG NWB FacNet/CorpNet Live - to SS Buildings (DPR) Give Milestones (XREFs) Not Started 05/26/26 05/26/26 0.0 0.0
0%
878.8
RPL10.CTRC.BB.1000 RPL10.Int.Build Back.Center-Corr - Interior Leave Out (Center Corridor) #6, #8 WBS Summary Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 05/26/26 07/20/26 48.8 48.8
0%
142.5
RPL10.CTRC.BB.1060 RPL10.Int.Build Back.Center-Corr - LO #6,8 - Arch Finishes - Frame, Hang Drywall, Paint, Final Finishes (LOE) Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 05/26/26 06/17/26 21.2 21.2
0%
142.5
RPL10.CTRC.BB.3375 RPL10.Int.Build Back.Center-Corr - LO #6 - Hang IMP Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 05/26/26 05/28/26 3.8 3.8
0%
142.5
RPL10.CTRC.BB.3595 RPL10.Int.Build Back.Center-Corr - LO #7B - Hang Drywall Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) Not Started 05/26/26 05/28/26 3.8 3.8
0%
160.0
RPL10.EY.EF2.01250 RPL10.EY.EF2 - Install RPL-5 Total Road Closure For Fiber Supprt Platform Fiber Support Platform - RPL-5 Not Started 05/26/26 08/04/26 62.5 62.5
0%
231.2
RPL10.EY.EF2.01870 RPL10.EY.EF2 - Install RPL-5 FSP Columns Cap Cure Fiber Support Platform - RPL-5 Not Started 05/26/26 06/01/26 6.2 6.2
0%
215.0
RPL10.EY.ENDC.01180 RPL10.EY.End - Install BMS Tie-ins Tie-ins Not Started 05/26/26 06/15/26 18.8 18.8
0%
177.5
RPL10.EY.ENDC.01190 RPL10.EY.End - Install Irrigation Hardscape and Landscape Not Started 05/26/26 06/15/26 18.8 18.8
0%
446.2
RPL10.EY.NS2.01300 RPL10.EY.NS2 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/26/26 06/01/26 6.2 6.2
0%
181.2
RPL10.EY.NS2.01310 RPL10.EY.NS2 - MV Loop 2 - L2 Checklist Completion Tie-ins Not Started 05/26/26 06/08/26 12.5 12.5
0%
62.5
RPL10.EY.NS2.01320 RPL10.EY.NS2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/26/26 11/12/26 150.0 150.0
0%
333.8
RPL10.INT.CTRC.01400 RPL10.Interior.Center-Corridor - BoW - Toilet Accessories Balance of Walls & OverHead Not Started 05/26/26 05/28/26 3.8 3.8
0%
187.5
RPL10.INT.EF1.01110 RPL10.Interior.EF1 - Priority OH - Controls / EPMS / BMS *EPMS Separate Activty OverHead Not Started 05/26/26 05/29/26 5.0 5.0
0%
136.2
RPL10.INT.EF1.01180 RPL10.Interior.EF1 - North CRAH Gallery - Install Upper Trays North CRAH Gallery Not Started 05/26/26 06/01/26 6.2 6.2
0%
30.0
RPL10.INT.EF1.01200 RPL10.Interior.EF1 - Tie-ins - North CRAH Gallery - WBS Summary North CRAH Gallery Not Started 05/26/26 06/26/26 30.0 30.0
0%
166.2
RPL10.INT.EF1.01250 RPL10.Interior.EF1 - South CRAH Gallery - Install Upper Trays South CRAH Gallery Not Started 05/26/26 06/01/26 6.2 6.2
0%
30.0
RPL10.INT.EF1.01260 RPL10.Interior.EF1 - Tie-ins - South CRAH Gallery - WBS Summary South CRAH Gallery Not Started 05/26/26 07/10/26 41.2 41.2
0%
155.0
RPL10.INT.EF1.01480 RPL10.Interior.EF1 - EF1 West - Install Upper Trays West EF-1 Not Started 05/26/26 06/01/26 6.2 6.2
0%
30.0
RPL10.INT.EF1.01650 RPL10.Interior.EF1 - North CRAH Gallery - Install Duct work North CRAH Gallery Not Started 05/26/26 06/01/26 6.2 6.2
0%
87.5
RPL10.INT.EF1.01690 RPL10.Interior.EF1 - South CRAH Gallery - Install Duct work South CRAH Gallery Not Started 05/26/26 06/01/26 6.2 6.2
0%
110.0
RPL10.INT.NS2.01290 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 05/26/26 06/22/26 25.0 25.0
0%
27.5
RPL10.INT.NS2.01310 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/26/26 06/22/26 25.0 25.0
0%
31.2
RPL10.INT.NS2.01320 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/26/26 06/22/26 25.0 25.0
0%
31.2
RPL10.INT.NS2.01330 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 05/26/26 06/22/26 25.0 25.0
0%
18.8
RPL10.INT.NS3.01112 RPL10.Interior.NS3 - MES Skids - Piping Tie-Ins & Inspections NS3 - MES Skids Not Started 05/26/26 06/26/26 30.0 30.0
0%
123.8
RPL10.INT.NS4.01230 RPL10.Interior.NS4 - Control Fault Domain 1 SQ7.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/26/26 06/01/26 6.2 6.2
0%
142.5
RPL10.INT.SSBC.02920 RPL10.Interior.SSB-Corridor - BoW - Install Resinous Flooring in specific rooms Balance of Walls & OverHead Not Started 05/26/26 06/01/26 6.2 6.2
0%
125.0
RPL10.MCUP.LP2.1860 RPL10.MCUP.Loop 2 - Install Mcup Paving *Start 05/15 Hardscape and Landscape Not Started 05/26/26 06/15/26 18.8 18.8
0%
452.5
RPL10.PR.PR.02320 RPL10.PR MDF - Set META gear at GS.MDFs for FacNet GS-MDFs & IDFs Not Started 05/26/26 05/26/26 1.2 1.2
0%
161.2
RPL10.WP2.GSIDF.1720 RPL10.Conn GSIDFN43 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/26/26 06/08/26 12.5 12.5
0%
208.8
RPL10.WP2.GSIDF.1960 RPL10.Conn GSIDFN33 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/26/26 06/08/26 12.5 12.5
0%
208.8
RPL10.WP2.GSIDF.2420 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX06 WBS Summary GSIDFNX06 Not Started 05/26/26 06/11/26 16.2 16.2
0%
467.5
RPL10.WP2.GSIDF.2440 RPL10.Conn GSIDFNX06 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/26/26 06/01/26 6.2 6.2
0%
208.8
RPL10.WP2.GSIDF.2500 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX07 WBS Summary GSIDFNX07 Not Started 05/26/26 06/11/26 16.2 16.2
0%
467.5
RPL10.WP2.GSIDF.2520 RPL10.Conn GSIDFNX07 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/26/26 06/01/26 6.2 6.2
0%
208.8
RPL10.WP4.027460 RPL10.Conn NS1.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/26/26 06/01/26 6.2 6.2
0%
136.2
RPL10.WP4.027660 RPL10.Conn NS1.CFD4.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/26/26 06/01/26 6.2 6.2
0%
136.2
RPL10.WP4.028460 RPL10.Conn NS2.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/26/26 06/01/26 6.2 6.2
0%
147.5
RPL10.WP4.028660 RPL10.Conn NS2.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/26/26 06/01/26 6.2 6.2
0%
147.5
GCD.RPL10.2001 Cx Power Available (Temp) CX Milestones Not Started 05/27/26 05/27/26 0.0 0.0
0%
15.0
GCD.RPL10.3527 [RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 1-8] TC Ready: Production Cabling - NS1 Not Started 05/27/26 05/27/26 0.0 0.0
0%
40.0
GCD.RPL10.5765 RMU Loop Ready for Energization - NS1 Loop 1 EY Not Started 05/27/26 05/27/26 0.0 0.0
0%
22.5
GCD.RPL10.5785 RMU Loop Ready for Energization - NS1 Loop 2 EY Not Started 05/27/26 05/27/26 0.0 0.0
0%
65.0
RPL.10.D.X3810.XR 100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 NS1 Available (DPR Want 05.20.25) Power (XREFs) Not Started 05/27/26 05/27/26 0.0 0.0
0%
22.5
RPL.10.D.X38X0.XR 100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 mCUPs (North)Available (DPR Want 05.06.25) Power (XREFs) Not Started 05/27/26 05/27/26 0.0 0.0
0%
15.0
RPL10.EY.EF1.01140 RPL10.EY.EF1 - Install RPL-1 FSP Grounding Wire Fiber Support Platform - RPL-1 Not Started 05/27/26 05/28/26 2.5 2.5
0%
267.5
RPL10.EY.EF1.01700 RPL10.EY.EF1 - Install RPL-1 FSP Final Roof (Standing Seam Panels) Phase 2 Fiber Support Platform - RPL-1 Not Started 05/27/26 06/02/26 6.2 6.2
0%
242.5
RPL10.EY.NS1.01340 RPL10.EY.NS1 - Install Lighting Hardscape and Landscape Not Started 05/27/26 06/09/26 12.5 12.5
0%
181.2
RPL10.INT.CTRC.01070 RPL10.Interior.Center-Corridor - BoW - Install Doors (Verify with Trades Before Installation) Balance of Walls & OverHead Not Started 05/27/26 05/29/26 3.8 3.8
0%
191.2
RPL10.INT.CTRC.01100 RPL10.Interior.Center-Corridor - BoW - Security Trim Out (Both Side of Corridor Wall) Balance of Walls & OverHead Not Started 05/27/26 05/28/26 2.5 2.5
0%
187.5
RPL10.INT.CTRC.01410 RPL10.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & OverHead Not Started 05/27/26 06/01/26 5.0 5.0
0%
190.0
RPL10.INT.NS1.01570 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 05/27/26 06/23/26 25.0 25.0
0%
42.5
RPL10.INT.NS4.01113 RPL10.Interior.NS4 - MES Skids - CDU Tie-Ins NS4 - MES Skids Not Started 05/27/26 06/29/26 30.0 30.0
0%
237.5
RPL10.INT.NS4.01210 RPL10.Interior.NS4 - OFE - Control Fault Domain 2 SQ8.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS4 Control Fault Domain 2 Not Started 05/27/26 09/08/26 91.2 91.2
0%
46.2
RPL10.INT.NS4.01250 RPL10.Interior.NS4 - Control Fault Domain 1 SQ7.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/27/26 06/02/26 6.2 6.2
0%
142.5
RPL10.INT.NS4.02540 RPL10.Interior.NS4 - OFE - Control Fault Domain 2 SQ8.1 (LV Side Aisle) OFE NS4 Control Fault Domain 2 Not Started 05/27/26 06/01/26 5.0 5.0
0%
122.5
RPL10.INT.SSB.01350 RPL10.Interior.SSB - Loading Dock and Storage - Final Paint Loading Dock and Storage Not Started 05/27/26 05/29/26 3.8 3.8
0%
173.8
RPL10.INT.SSB.01490 RPL10.Interior.SSB - BoW - Install Remaining Lighting Balance of Walls and OverHead Not Started 05/27/26 06/04/26 8.8 8.8
0%
147.5
RPL10.INT.SSB.01500 RPL10.Interior.SSB - BoW - Install Bathroom Fixtures Balance of Walls and OverHead Not Started 05/27/26 06/04/26 8.8 8.8
0%
147.5
RPL10.OFCI.6900 OFCI - Delivery ROJ: FE Fiber for CFD NS1.2 (ROJ ) (RVCD ) NS1 Not Started 05/27/26 06/16/26 18.8 18.8
0%
110.0
RPL10.PR.PR.02340 RPL10.PR MDF - Rack/ Stack/ Patch and Provisioning at GS.MDFs for FacNet GS-MDFs & IDFs Not Started 05/27/26 06/30/26 31.2 31.2
0%
161.2
RPL10.WP2.01020 RPL10.Conn SSB - Early Construction Cx Server Ready - At NS1 EY (MV) WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 05/27/26 05/27/26 0.0 0.0
0%
22.5
RPL10.WP2.GSIDF.2080 RPL10.Conn GSIDFNX01 Install & Test Network (FIM) Network Not Started 05/27/26 05/29/26 3.8 3.8
0%
220.0
RPL10.WP2.GSIDF.2160 RPL10.Conn GSIDFNX02 Install & Test Network (FIM) Network Not Started 05/27/26 05/29/26 3.8 3.8
0%
220.0
RPL10.WP2.GSIDF.3280 RPL10.Conn GSIDFNX01 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/27/26 05/29/26 3.8 3.8
0%
478.8
RPL10.WP2.GSIDF.3300 RPL10.Conn GSIDFNX02 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/27/26 05/29/26 3.8 3.8
0%
478.8
RPL10.WP4.027260 RPL10.Conn NS1.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/27/26 06/02/26 6.2 6.2
0%
135.0
DCC.B10.3225 [NWB] CorpNet/Security/FacNet Ready [NWS 1] Connectivity Not Started 05/28/26 05/28/26 0.0 0.0
0%
222.5
DCC.B10.3235 [NWB] CorpNet/Security/FacNet Ready [NWS 2] Connectivity Not Started 05/28/26 05/28/26 0.0 0.0
0%
222.5
JCL.C.1400 RPL10 - Cost Risk LOE-19 Connectivity Package 3B - Front End Cabling (ISP) Cost LOEs Not Started 05/28/26 03/31/27 262.5 262.5
0%
58.8
RPL10.EY.EF1.01400 RPL10.EY.EF1 - L2 Checklist Completion Tie-ins Not Started 05/28/26 06/10/26 12.5 12.5
0%
126.2
RPL10.INT.ENDC.01260 RPL10.Interior.End-Corridor - BoW - Install Cable Tray Balance of Walls & Overhead Not Started 05/28/26 06/03/26 6.2 6.2
0%
287.5
RPL10.INT.ENDC.01270 RPL10.Interior.End-Corridor - BoW - Install Tile Balance of Walls & Overhead Not Started 05/28/26 06/05/26 8.8 8.8
0%
207.5
RPL10.INT.ENDC.1460 RPL10.Interior.End-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 05/28/26 06/03/26 6.2 6.2
0%
215.0
RPL10.INT.ENDC.1600 RPL10.Interior.End-Corridor - BoW - Electrical Trim Out (incl Lights) Balance of Walls & Overhead Not Started 05/28/26 06/08/26 10.0 10.0
0%
221.2
RPL10.INT.ENDC.1900 RPL10.Interior.End-Corridor - BoW - F/R/P Pads Balance of Walls & Overhead Not Started 05/28/26 06/03/26 6.2 6.2
0%
183.8
RPL10.INT.ENDC.6200 RPL10.Interior.End-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) Balance of Walls & Overhead Not Started 05/28/26 06/02/26 5.0 5.0
0%
218.8
RPL10.INT.ENDC.6460 RPL10.Interior.End-Corridor - BoW - Install Fire Alarm Panel Balance of Walls & Overhead Not Started 05/28/26 05/29/26 2.5 2.5
0%
281.2
RPL10.INT.NS1.01290 RPL10.Conn NS1.CFD6 - Set Passive Racks for WP3B Infrastructure Not Started 05/28/26 06/01/26 3.8 3.8
0%
36.2
RPL10.INT.NS1.02840 RPL10.Conn NS1.CFD6 - Set Passive Racks for PON Infrastructure Not Started 05/28/26 06/01/26 3.8 3.8
0%
157.5
RPL10.WP2.01120 RPL10.Conn GSMDF Ready for ENS Buildout - GSMDF 1&2 Supporting Services Building Not Started 05/28/26 05/28/26 0.0 0.0
0%
193.8
RPL10.WP4.08800 RPL10.Conn NS1.CFD6 Pull/Install Ext. Trunk (384F) [JXSW<>MA] [MA<>JXSW] Not Started 05/28/26 06/04/26 7.5 7.5
0%
187.5
RPL10.WP4.NS1.01760 RPL10.Conn NS1.CFD6 Infrastructure - WBS Summary Infrastructure Not Started 05/28/26 06/10/26 12.5 12.5
0%
70.0
RPL10.WP4.NS1.01780 RPL10.Conn NS1.CFD6 Infrastructure Infrastructure Not Started 05/28/26 06/10/26 12.5 12.5
0%
70.0
DCC.B10.3155 [NWB] GS Gear Delivered [NWS 4] Connectivity Not Started 05/29/26 05/29/26 0.0 0.0
0%
875.0
GCD.RPL10.2051 MCUP Ready for Energization - (MCUPs Loop 1) mCup Not Started 05/29/26 05/29/26 0.0 0.0
0%
50.0
RPL.GF.D.N0100.XG GS.EF1 Infrastructure Ready RPL10 Give Milestones (XREFs) Not Started 05/29/26 05/29/26 0.0 0.0
0%
873.8
RPL10.CTRC.BB.3395 RPL10.Int.Build Back.Center-Corr - LO #6 - Install Remaining Hilti Steel Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 05/29/26 06/02/26 3.8 3.8
0%
152.5
RPL10.CTRC.BB.3435 RPL10.Int.Build Back.Center-Corr - LO #8 - Frame Build Back Interior Leave Out Wall #6 #8 (Center Corr) Not Started 05/29/26 06/02/26 3.8 3.8
0%
142.5
RPL10.CTRC.BB.3615 RPL10.Int.Build Back.Center-Corr - LO #7B - Paint Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) Not Started 05/29/26 06/04/26 6.2 6.2
0%
160.0
RPL10.CX.1180 RPL10.CX.BLDG - L3, L4, IST - WBS Summary Commissioning Not Started 05/29/26 07/12/27 350.0 350.0
0%
512.5
RPL10.CX.MCUP.01000 RPL10.CX.mCup Loop 1 - L3, L4, IST - WBS Summary mCup Loop 1 (mCup #1,#3,#5,#7) Not Started 05/29/26 08/13/26 67.5 67.5
0%
412.5
RPL10.CX.MCUP.01010 RPL10.CX.mCup Loop 1 - L3/L4 - MV Skids mCup Loop 1 (mCup #1,#3,#5,#7) Not Started 05/29/26 06/05/26 7.5 7.5
0%
12.5
RPL10.CX.MCUP.01350 RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) Fill and Flush Not Started 05/29/26 06/04/26 6.2 6.2
0%
33.8
RPL10.INT.CTRC.01440 RPL10.Interior.Center-Corridor - BoW - Plumbing Trim Out (Both Side of Corridor Wall) Balance of Walls & OverHead Not Started 05/29/26 06/03/26 5.0 5.0
0%
187.5
RPL10.INT.CTRC.01500 RPL10.Interior.Center-Corridor - BoW - Mechanical L2 Checklist Completion Balance of Walls & OverHead Not Started 05/29/26 06/11/26 12.5 12.5
0%
125.0
RPL10.INT.EF1.01470 RPL10.Interior.EF1 - EF1 East - Set Passive Panels / Racks East EF-1 Not Started 05/29/26 06/04/26 6.2 6.2
0%
186.2
RPL10.INT.EF2.01280 RPL10.Interior.EF2 - South CRAH Gallery - Leak Detection / Heat Trace South CRAH Gallery Not Started 05/29/26 06/04/26 6.2 6.2
0%
130.0
RPL10.INT.NS4.01270 RPL10.Interior.NS4 - Control Fault Domain 2 SQ8.1 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/29/26 06/03/26 5.0 5.0
0%
125.0