Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL.GF.D.N0155.XG |
NWB FacNet/CorpNet Live - to SS Buildings (DPR) | Give Milestones (XREFs) | Not Started | 05/26/26 | 05/26/26 | 0.0 | 0.0 |
|
878.8 |
RPL10.CTRC.BB.1000 |
RPL10.Int.Build Back.Center-Corr - Interior Leave Out (Center Corridor) #6, #8 WBS Summary | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 05/26/26 | 07/20/26 | 48.8 | 48.8 |
|
142.5 |
RPL10.CTRC.BB.1060 |
RPL10.Int.Build Back.Center-Corr - LO #6,8 - Arch Finishes - Frame, Hang Drywall, Paint, Final Finishes (LOE) | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 05/26/26 | 06/17/26 | 21.2 | 21.2 |
|
142.5 |
RPL10.CTRC.BB.3375 |
RPL10.Int.Build Back.Center-Corr - LO #6 - Hang IMP | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 05/26/26 | 05/28/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.CTRC.BB.3595 |
RPL10.Int.Build Back.Center-Corr - LO #7B - Hang Drywall | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 05/26/26 | 05/28/26 | 3.8 | 3.8 |
|
160.0 |
RPL10.EY.EF2.01250 |
RPL10.EY.EF2 - Install RPL-5 Total Road Closure For Fiber Supprt Platform | Fiber Support Platform - RPL-5 | Not Started | 05/26/26 | 08/04/26 | 62.5 | 62.5 |
|
231.2 |
RPL10.EY.EF2.01870 |
RPL10.EY.EF2 - Install RPL-5 FSP Columns Cap Cure | Fiber Support Platform - RPL-5 | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.EY.ENDC.01180 |
RPL10.EY.End - Install BMS Tie-ins | Tie-ins | Not Started | 05/26/26 | 06/15/26 | 18.8 | 18.8 |
|
177.5 |
RPL10.EY.ENDC.01190 |
RPL10.EY.End - Install Irrigation | Hardscape and Landscape | Not Started | 05/26/26 | 06/15/26 | 18.8 | 18.8 |
|
446.2 |
RPL10.EY.NS2.01300 |
RPL10.EY.NS2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.EY.NS2.01310 |
RPL10.EY.NS2 - MV Loop 2 - L2 Checklist Completion | Tie-ins | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
62.5 |
RPL10.EY.NS2.01320 |
RPL10.EY.NS2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/26/26 | 11/12/26 | 150.0 | 150.0 |
|
333.8 |
RPL10.INT.CTRC.01400 |
RPL10.Interior.Center-Corridor - BoW - Toilet Accessories | Balance of Walls & OverHead | Not Started | 05/26/26 | 05/28/26 | 3.8 | 3.8 |
|
187.5 |
RPL10.INT.EF1.01110 |
RPL10.Interior.EF1 - Priority OH - Controls / EPMS / BMS *EPMS Separate Activty | OverHead | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.INT.EF1.01180 |
RPL10.Interior.EF1 - North CRAH Gallery - Install Upper Trays | North CRAH Gallery | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01200 |
RPL10.Interior.EF1 - Tie-ins - North CRAH Gallery - WBS Summary | North CRAH Gallery | Not Started | 05/26/26 | 06/26/26 | 30.0 | 30.0 |
|
166.2 |
RPL10.INT.EF1.01250 |
RPL10.Interior.EF1 - South CRAH Gallery - Install Upper Trays | South CRAH Gallery | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01260 |
RPL10.Interior.EF1 - Tie-ins - South CRAH Gallery - WBS Summary | South CRAH Gallery | Not Started | 05/26/26 | 07/10/26 | 41.2 | 41.2 |
|
155.0 |
RPL10.INT.EF1.01480 |
RPL10.Interior.EF1 - EF1 West - Install Upper Trays | West EF-1 | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.INT.EF1.01650 |
RPL10.Interior.EF1 - North CRAH Gallery - Install Duct work | North CRAH Gallery | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
87.5 |
RPL10.INT.EF1.01690 |
RPL10.Interior.EF1 - South CRAH Gallery - Install Duct work | South CRAH Gallery | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
110.0 |
RPL10.INT.NS2.01290 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
27.5 |
RPL10.INT.NS2.01310 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
31.2 |
RPL10.INT.NS2.01320 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
31.2 |
RPL10.INT.NS2.01330 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
18.8 |
RPL10.INT.NS3.01112 |
RPL10.Interior.NS3 - MES Skids - Piping Tie-Ins & Inspections | NS3 - MES Skids | Not Started | 05/26/26 | 06/26/26 | 30.0 | 30.0 |
|
123.8 |
RPL10.INT.NS4.01230 |
RPL10.Interior.NS4 - Control Fault Domain 1 SQ7.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
142.5 |
RPL10.INT.SSBC.02920 |
RPL10.Interior.SSB-Corridor - BoW - Install Resinous Flooring in specific rooms | Balance of Walls & OverHead | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.MCUP.LP2.1860 |
RPL10.MCUP.Loop 2 - Install Mcup Paving *Start 05/15 | Hardscape and Landscape | Not Started | 05/26/26 | 06/15/26 | 18.8 | 18.8 |
|
452.5 |
RPL10.PR.PR.02320 |
RPL10.PR MDF - Set META gear at GS.MDFs for FacNet | GS-MDFs & IDFs | Not Started | 05/26/26 | 05/26/26 | 1.2 | 1.2 |
|
161.2 |
RPL10.WP2.GSIDF.1720 |
RPL10.Conn GSIDFN43 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
208.8 |
RPL10.WP2.GSIDF.1960 |
RPL10.Conn GSIDFN33 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
208.8 |
RPL10.WP2.GSIDF.2420 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX06 WBS Summary | GSIDFNX06 | Not Started | 05/26/26 | 06/11/26 | 16.2 | 16.2 |
|
467.5 |
RPL10.WP2.GSIDF.2440 |
RPL10.Conn GSIDFNX06 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.WP2.GSIDF.2500 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX07 WBS Summary | GSIDFNX07 | Not Started | 05/26/26 | 06/11/26 | 16.2 | 16.2 |
|
467.5 |
RPL10.WP2.GSIDF.2520 |
RPL10.Conn GSIDFNX07 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.WP4.027460 |
RPL10.Conn NS1.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
136.2 |
RPL10.WP4.027660 |
RPL10.Conn NS1.CFD4.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
136.2 |
RPL10.WP4.028460 |
RPL10.Conn NS2.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
147.5 |
RPL10.WP4.028660 |
RPL10.Conn NS2.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
147.5 |
GCD.RPL10.2001 |
Cx Power Available (Temp) | CX Milestones | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
15.0 |
GCD.RPL10.3527 |
[RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 1-8] | TC Ready: Production Cabling - NS1 | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
40.0 |
GCD.RPL10.5765 |
RMU Loop Ready for Energization - NS1 Loop 1 | EY | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
22.5 |
GCD.RPL10.5785 |
RMU Loop Ready for Energization - NS1 Loop 2 | EY | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
65.0 |
RPL.10.D.X3810.XR |
100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 NS1 Available (DPR Want 05.20.25) | Power (XREFs) | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
22.5 |
RPL.10.D.X38X0.XR |
100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 mCUPs (North)Available (DPR Want 05.06.25) | Power (XREFs) | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
15.0 |
RPL10.EY.EF1.01140 |
RPL10.EY.EF1 - Install RPL-1 FSP Grounding Wire | Fiber Support Platform - RPL-1 | Not Started | 05/27/26 | 05/28/26 | 2.5 | 2.5 |
|
267.5 |
RPL10.EY.EF1.01700 |
RPL10.EY.EF1 - Install RPL-1 FSP Final Roof (Standing Seam Panels) Phase 2 | Fiber Support Platform - RPL-1 | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
242.5 |
RPL10.EY.NS1.01340 |
RPL10.EY.NS1 - Install Lighting | Hardscape and Landscape | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
181.2 |
RPL10.INT.CTRC.01070 |
RPL10.Interior.Center-Corridor - BoW - Install Doors (Verify with Trades Before Installation) | Balance of Walls & OverHead | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
191.2 |
RPL10.INT.CTRC.01100 |
RPL10.Interior.Center-Corridor - BoW - Security Trim Out (Both Side of Corridor Wall) | Balance of Walls & OverHead | Not Started | 05/27/26 | 05/28/26 | 2.5 | 2.5 |
|
187.5 |
RPL10.INT.CTRC.01410 |
RPL10.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & OverHead | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
190.0 |
RPL10.INT.NS1.01570 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/27/26 | 06/23/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS4.01113 |
RPL10.Interior.NS4 - MES Skids - CDU Tie-Ins | NS4 - MES Skids | Not Started | 05/27/26 | 06/29/26 | 30.0 | 30.0 |
|
237.5 |
RPL10.INT.NS4.01210 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 2 SQ8.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS4 Control Fault Domain 2 | Not Started | 05/27/26 | 09/08/26 | 91.2 | 91.2 |
|
46.2 |
RPL10.INT.NS4.01250 |
RPL10.Interior.NS4 - Control Fault Domain 1 SQ7.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
142.5 |
RPL10.INT.NS4.02540 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 2 SQ8.1 (LV Side Aisle) | OFE NS4 Control Fault Domain 2 | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
122.5 |
RPL10.INT.SSB.01350 |
RPL10.Interior.SSB - Loading Dock and Storage - Final Paint | Loading Dock and Storage | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
173.8 |
RPL10.INT.SSB.01490 |
RPL10.Interior.SSB - BoW - Install Remaining Lighting | Balance of Walls and OverHead | Not Started | 05/27/26 | 06/04/26 | 8.8 | 8.8 |
|
147.5 |
RPL10.INT.SSB.01500 |
RPL10.Interior.SSB - BoW - Install Bathroom Fixtures | Balance of Walls and OverHead | Not Started | 05/27/26 | 06/04/26 | 8.8 | 8.8 |
|
147.5 |
RPL10.OFCI.6900 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.2 (ROJ ) (RVCD ) | NS1 | Not Started | 05/27/26 | 06/16/26 | 18.8 | 18.8 |
|
110.0 |
RPL10.PR.PR.02340 |
RPL10.PR MDF - Rack/ Stack/ Patch and Provisioning at GS.MDFs for FacNet | GS-MDFs & IDFs | Not Started | 05/27/26 | 06/30/26 | 31.2 | 31.2 |
|
161.2 |
RPL10.WP2.01020 |
RPL10.Conn SSB - Early Construction Cx Server Ready - At NS1 EY (MV) | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
22.5 |
RPL10.WP2.GSIDF.2080 |
RPL10.Conn GSIDFNX01 Install & Test Network (FIM) | Network | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
220.0 |
RPL10.WP2.GSIDF.2160 |
RPL10.Conn GSIDFNX02 Install & Test Network (FIM) | Network | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
220.0 |
RPL10.WP2.GSIDF.3280 |
RPL10.Conn GSIDFNX01 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
478.8 |
RPL10.WP2.GSIDF.3300 |
RPL10.Conn GSIDFNX02 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
478.8 |
RPL10.WP4.027260 |
RPL10.Conn NS1.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
135.0 |
DCC.B10.3225 |
[NWB] CorpNet/Security/FacNet Ready [NWS 1] | Connectivity | Not Started | 05/28/26 | 05/28/26 | 0.0 | 0.0 |
|
222.5 |
DCC.B10.3235 |
[NWB] CorpNet/Security/FacNet Ready [NWS 2] | Connectivity | Not Started | 05/28/26 | 05/28/26 | 0.0 | 0.0 |
|
222.5 |
JCL.C.1400 |
RPL10 - Cost Risk LOE-19 Connectivity Package 3B - Front End Cabling (ISP) | Cost LOEs | Not Started | 05/28/26 | 03/31/27 | 262.5 | 262.5 |
|
58.8 |
RPL10.EY.EF1.01400 |
RPL10.EY.EF1 - L2 Checklist Completion | Tie-ins | Not Started | 05/28/26 | 06/10/26 | 12.5 | 12.5 |
|
126.2 |
RPL10.INT.ENDC.01260 |
RPL10.Interior.End-Corridor - BoW - Install Cable Tray | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
287.5 |
RPL10.INT.ENDC.01270 |
RPL10.Interior.End-Corridor - BoW - Install Tile | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/05/26 | 8.8 | 8.8 |
|
207.5 |
RPL10.INT.ENDC.1460 |
RPL10.Interior.End-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.INT.ENDC.1600 |
RPL10.Interior.End-Corridor - BoW - Electrical Trim Out (incl Lights) | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/08/26 | 10.0 | 10.0 |
|
221.2 |
RPL10.INT.ENDC.1900 |
RPL10.Interior.End-Corridor - BoW - F/R/P Pads | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
183.8 |
RPL10.INT.ENDC.6200 |
RPL10.Interior.End-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) | Balance of Walls & Overhead | Not Started | 05/28/26 | 06/02/26 | 5.0 | 5.0 |
|
218.8 |
RPL10.INT.ENDC.6460 |
RPL10.Interior.End-Corridor - BoW - Install Fire Alarm Panel | Balance of Walls & Overhead | Not Started | 05/28/26 | 05/29/26 | 2.5 | 2.5 |
|
281.2 |
RPL10.INT.NS1.01290 |
RPL10.Conn NS1.CFD6 - Set Passive Racks for WP3B | Infrastructure | Not Started | 05/28/26 | 06/01/26 | 3.8 | 3.8 |
|
36.2 |
RPL10.INT.NS1.02840 |
RPL10.Conn NS1.CFD6 - Set Passive Racks for PON | Infrastructure | Not Started | 05/28/26 | 06/01/26 | 3.8 | 3.8 |
|
157.5 |
RPL10.WP2.01120 |
RPL10.Conn GSMDF Ready for ENS Buildout - GSMDF 1&2 | Supporting Services Building | Not Started | 05/28/26 | 05/28/26 | 0.0 | 0.0 |
|
193.8 |
RPL10.WP4.08800 |
RPL10.Conn NS1.CFD6 Pull/Install Ext. Trunk (384F) [JXSW<>MA] | [MA<>JXSW] | Not Started | 05/28/26 | 06/04/26 | 7.5 | 7.5 |
|
187.5 |
RPL10.WP4.NS1.01760 |
RPL10.Conn NS1.CFD6 Infrastructure - WBS Summary | Infrastructure | Not Started | 05/28/26 | 06/10/26 | 12.5 | 12.5 |
|
70.0 |
RPL10.WP4.NS1.01780 |
RPL10.Conn NS1.CFD6 Infrastructure | Infrastructure | Not Started | 05/28/26 | 06/10/26 | 12.5 | 12.5 |
|
70.0 |
DCC.B10.3155 |
[NWB] GS Gear Delivered [NWS 4] | Connectivity | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
875.0 |
GCD.RPL10.2051 |
MCUP Ready for Energization - (MCUPs Loop 1) | mCup | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
50.0 |
RPL.GF.D.N0100.XG |
GS.EF1 Infrastructure Ready RPL10 | Give Milestones (XREFs) | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
873.8 |
RPL10.CTRC.BB.3395 |
RPL10.Int.Build Back.Center-Corr - LO #6 - Install Remaining Hilti Steel | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 05/29/26 | 06/02/26 | 3.8 | 3.8 |
|
152.5 |
RPL10.CTRC.BB.3435 |
RPL10.Int.Build Back.Center-Corr - LO #8 - Frame | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 05/29/26 | 06/02/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.CTRC.BB.3615 |
RPL10.Int.Build Back.Center-Corr - LO #7B - Paint | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
160.0 |
RPL10.CX.1180 |
RPL10.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 05/29/26 | 07/12/27 | 350.0 | 350.0 |
|
512.5 |
RPL10.CX.MCUP.01000 |
RPL10.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCup Loop 1 (mCup #1,#3,#5,#7) | Not Started | 05/29/26 | 08/13/26 | 67.5 | 67.5 |
|
412.5 |
RPL10.CX.MCUP.01010 |
RPL10.CX.mCup Loop 1 - L3/L4 - MV Skids | mCup Loop 1 (mCup #1,#3,#5,#7) | Not Started | 05/29/26 | 06/05/26 | 7.5 | 7.5 |
|
12.5 |
RPL10.CX.MCUP.01350 |
RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) | Fill and Flush | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
33.8 |
RPL10.INT.CTRC.01440 |
RPL10.Interior.Center-Corridor - BoW - Plumbing Trim Out (Both Side of Corridor Wall) | Balance of Walls & OverHead | Not Started | 05/29/26 | 06/03/26 | 5.0 | 5.0 |
|
187.5 |
RPL10.INT.CTRC.01500 |
RPL10.Interior.Center-Corridor - BoW - Mechanical L2 Checklist Completion | Balance of Walls & OverHead | Not Started | 05/29/26 | 06/11/26 | 12.5 | 12.5 |
|
125.0 |
RPL10.INT.EF1.01470 |
RPL10.Interior.EF1 - EF1 East - Set Passive Panels / Racks | East EF-1 | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
186.2 |
RPL10.INT.EF2.01280 |
RPL10.Interior.EF2 - South CRAH Gallery - Leak Detection / Heat Trace | South CRAH Gallery | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
130.0 |
RPL10.INT.NS4.01270 |
RPL10.Interior.NS4 - Control Fault Domain 2 SQ8.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/29/26 | 06/03/26 | 5.0 | 5.0 |
|
125.0 |