Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
2
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.NS2.01380 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/11/26 | 05/14/26 | 5.0 | 5.0 |
|
37.5 |
RPL10.INT.NS3.01065 |
RPL10.Interior.NS3 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor | OFE | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
160.0 |
RPL10.INT.NS3.01100 |
RPL10.Interior.NS3 - Tie-ins - WBS Summary | Tie-Ins | Not Started | 05/11/26 | 01/19/27 | 216.2 | 216.2 |
|
126.2 |
RPL10.INT.NS3.01110 |
RPL10.Interior.NS3 - MES Skids Tie-ins (LOE) | NS3 - MES Skids | Not Started | 05/11/26 | 08/04/26 | 75.0 | 75.0 |
|
240.0 |
RPL10.INT.NS3.01111 |
RPL10.Interior.NS3 - MES Skids - Set & Anchor Interconnects | NS3 - MES Skids | Not Started | 05/11/26 | 06/12/26 | 30.0 | 30.0 |
|
123.8 |
RPL10.INT.SSB.01390 |
RPL10.Interior.SSB - BoW - Plumbing Trim Out | Balance of Walls and OverHead | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
211.2 |
RPL10.INT.SSB.01400 |
RPL10.Interior.SSB - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls and OverHead | Not Started | 05/11/26 | 05/19/26 | 8.8 | 8.8 |
|
211.2 |
RPL10.INT.SSB.01470 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Unit Heaters | Loading Dock and Storage | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
200.0 |
RPL10.INT.SSB.01530 |
RPL10.Interior.SSB - Loading Dock and Storage - Install OverHead Doors (Mob 1) | Loading Dock and Storage | Not Started | 05/11/26 | 05/12/26 | 2.5 | 2.5 |
|
185.0 |
RPL10.INT.SSB.01780 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers | Loading Dock and Storage | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.MCUP.LP1.2020 |
RPL10.MCUP.Loop 1 - Tie-in - MV Loop L2 Checklist Completion | Tie-Ins Electrical | Not Started | 05/11/26 | 05/21/26 | 11.2 | 11.2 |
|
16.2 |
RPL10.WP2.01030 |
RPL10.Conn SSB - Early Construction Cx Server Ready - At NS1 (LV) | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
62.5 |
RPL10.WP2.GSIDF.1500 |
RPL10.Conn GSIDFN23 Install & Test Network (FIM) | Network | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
233.8 |
RPL10.WP2.GSIDF.3100 |
RPL10.Conn GSIDFN13 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/11/26 | 05/27/26 | 15.0 | 15.0 |
|
191.2 |
RPL10.WP2.GSIDF.3140 |
RPL10.Conn GSIDFN23 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/11/26 | 05/27/26 | 15.0 | 15.0 |
|
191.2 |
RPL.GF.D.N0250.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL6 | Connectivity (XREFs) | Not Started | 05/12/26 | 05/12/26 | 0.0 | 0.0 |
|
232.5 |
RPL10.CFCI.5260 |
RPL10 - Fabricate / Deliver - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 05/12/26 | 05/26/26 | 12.5 | 12.5 |
|
147.5 |
RPL10.EY.NS1.01290 |
RPL10.EY.NS1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.EY.NS1.01300 |
RPL10.EY.NS1 - MV Loop 1 - L2 Checklist Completion | Tie-ins | Not Started | 05/12/26 | 05/26/26 | 12.5 | 12.5 |
|
22.5 |
RPL10.EY.NS1.01310 |
RPL10.EY.NS1 - MV Loop 2 - L2 Checklist Completion | Tie-ins | Not Started | 05/12/26 | 05/26/26 | 12.5 | 12.5 |
|
65.0 |
RPL10.EY.NS1.01320 |
RPL10.EY.NS1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/12/26 | 10/15/26 | 137.5 | 137.5 |
|
357.5 |
RPL10.EY.NS4.01220 |
RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (15) | OFE | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
107.5 |
RPL10.EY.NS4.01230 |
RPL10.EY.NS4 - OFE - MV - WBS Summary | OFE | Not Started | 05/12/26 | 06/30/26 | 43.8 | 43.8 |
|
101.2 |
RPL10.INT.CTRC.01460 |
RPL10.Interior.Center-Corridor - BoW - Install Lighting | Balance of Walls & OverHead | Not Started | 05/12/26 | 05/20/26 | 8.8 | 8.8 |
|
125.0 |
RPL10.INT.EF1.01410 |
RPL10.Interior.EF1 - EF1 East - Install Lower Trays | East EF-1 | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
47.5 |
RPL10.INT.EF1.01420 |
RPL10.Interior.EF1 - EF1 East - Install Lighting | East EF-1 | Not Started | 05/12/26 | 05/28/26 | 15.0 | 15.0 |
|
125.0 |
RPL10.INT.NS1.01450 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
32.5 |
RPL10.INT.NS1.01750 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
110.0 |
RPL10.INT.NS2.01114 |
RPL10.Interior.NS2 - MES Skids - BMS Tie-Ins ( 2 per day) | NS2 - MES Skids | Not Started | 05/12/26 | 06/15/26 | 30.0 | 30.0 |
|
157.5 |
RPL10.INT.NS2.01510 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
72.5 |
RPL10.INT.NS2.02525 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (HAC) | OFE NS2 Control Fault Domain 5 | Not Started | 05/12/26 | 06/02/26 | 18.8 | 18.8 |
|
-18.8 |
RPL10.INT.NS3.01060 |
RPL10.Interior.NS3 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.30.26) (Rev-05.11.26) | OFE | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
80.0 |
RPL10.INT.NS4.01112 |
RPL10.Interior.NS4 - MES Skids - Piping Tie-Ins & Inspections | NS4 - MES Skids | Not Started | 05/12/26 | 06/15/26 | 30.0 | 30.0 |
|
135.0 |
RPL10.MCUP.LP1.2060 |
RPL10.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-Ins Electrical | Not Started | 05/12/26 | 05/22/26 | 11.2 | 11.2 |
|
16.2 |
RPL10.SSB.BB.1130 |
RPL10.Ext.Build Back.SSB - LO #5 - Hang, Tape and Finish | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
437.5 |
RPL10.WP2.GSIDF.1200 |
RPL10.Conn GSIDFNE1 Install & Test Network (FIM) | Network | Not Started | 05/12/26 | 05/14/26 | 3.8 | 3.8 |
|
148.8 |
RPL10.WP2.GSIDF.2020 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX01 WBS Summary | GSIDFNX01 | Not Started | 05/12/26 | 05/29/26 | 16.2 | 16.2 |
|
478.8 |
RPL10.WP2.GSIDF.2040 |
RPL10.Conn GSIDFNX01 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
220.0 |
RPL10.WP2.GSIDF.2100 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX02 WBS Summary | GSIDFNX02 | Not Started | 05/12/26 | 05/29/26 | 16.2 | 16.2 |
|
478.8 |
RPL10.WP2.GSIDF.2120 |
RPL10.Conn GSIDFNX02 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
22.5 |
RPL10.WP2.GSIDF.3060 |
RPL10.Conn GSIDFNE1 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/12/26 | 06/02/26 | 18.8 | 18.8 |
|
476.2 |
RPL.10.D.X33X7.XR |
Cable Pull to Concrete Pad - RPL10 NS4 Loop 1 & 2 | Power (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
33.8 |
RPL.10.D.X4420.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections (L3/L4) | Water / Gas Available (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
51.2 |
RPL.GF.D.G4620.XG |
Rack & Cabinets Complete - DHB - RPL6 | Give Milestones (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
227.0 |
RPL10.INT.ENDC.01100 |
RPL10.Interior.End-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls & Overhead | Not Started | 05/13/26 | 05/18/26 | 5.0 | 5.0 |
|
247.5 |
RPL10.INT.ENDC.1560 |
RPL10.Interior.End-Corridor - BoW - Hang Drywall BoW | Balance of Walls & Overhead | Not Started | 05/13/26 | 05/22/26 | 10.0 | 10.0 |
|
183.8 |
RPL10.INT.NS1.01430 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/13/26 | 06/10/26 | 25.0 | 25.0 |
|
37.5 |
RPL10.INT.NS1.01870 |
RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/13/26 | 05/18/26 | 5.0 | 5.0 |
|
97.5 |
RPL10.INT.NS2.01520 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/13/26 | 05/18/26 | 5.0 | 5.0 |
|
95.0 |
RPL10.INT.NS2.01820 |
RPL10.Interior.NS2 - Control Fault Domain 1 SQ6.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/13/26 | 05/18/26 | 5.0 | 5.0 |
|
68.8 |
RPL10.INT.NS2.01850 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 1 SQ6.2 - WBS Summary | Tie-Ins NS2 Control Fault Domain 1 | Not Started | 05/13/26 | 09/30/26 | 122.5 | 122.5 |
|
8.8 |
RPL10.INT.NS3.01094 |
RPL10.Interior.NS3 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins | NS3 - LV Skids and TopHat | Not Started | 05/13/26 | 06/03/26 | 18.8 | 18.8 |
|
160.0 |
RPL.GF.D.N0125.XR |
4 of 4 Fiber Test Complete CAV2/3 to GS.EF2/ Prod.EF2B | Connectivity (XREFs) | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
161.2 |
RPL10.INT.CTRC.01290 |
RPL10.Interior.Center-Corridor - BoW - Remaining Mechanical OFE Tie In | Balance of Walls & OverHead | Not Started | 05/14/26 | 05/18/26 | 3.8 | 3.8 |
|
127.5 |
RPL10.INT.NS1.01890 |
RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
131.2 |
RPL10.INT.NS1.02560 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (Mech Side Aisle) | OFE NS1 Control Fault Domain 4 | Not Started | 05/14/26 | 06/02/26 | 16.2 | 16.2 |
|
2.5 |
RPL10.INT.NS2.01650 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
80.0 |
RPL10.INT.NS3.01090 |
RPL10.Interior.NS3 - LV Skids and TopHat Tie-ins (LOE) | NS3 - LV Skids and TopHat | Not Started | 05/14/26 | 06/19/26 | 32.5 | 32.5 |
|
171.2 |
RPL10.INT.NS3.01091 |
RPL10.Interior.NS3 - LV Skids and TopHat - Set & Anchor Interconnects | NS3 - LV Skids and TopHat | Not Started | 05/14/26 | 06/09/26 | 22.5 | 22.5 |
|
171.2 |
RPL10.INT.SSB.01250 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Security | Loading Dock and Storage | Not Started | 05/14/26 | 05/22/26 | 8.8 | 8.8 |
|
175.0 |
RPL10.INT.SSB.01270 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Controls / EPMS / BMS *Separate EPMS *Whats Scope Check Trade | Loading Dock and Storage | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
175.0 |
RPL10.INT.SSB.01300 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety / Fire Alarm | Loading Dock and Storage | Not Started | 05/14/26 | 05/22/26 | 8.8 | 8.8 |
|
175.0 |
RPL10.INT.SSB.07100 |
RPL10.Interior.SSB - Loading Dock and Storage - Install OverHead Doors (Mob 2) | Loading Dock and Storage | Not Started | 05/14/26 | 05/26/26 | 10.0 | 10.0 |
|
173.8 |
RPL10.INT.SSBC.01400 |
RPL10.Interior.SSB-Corridor - BoW - Install Grounding | Balance of Walls & OverHead | Not Started | 05/14/26 | 05/20/26 | 6.2 | 6.2 |
|
123.8 |
RPL10.INT.SSBC.01410 |
RPL10.Interior.SSB-Corridor - BoW - Battery Connection | Balance of Walls & OverHead | Not Started | 05/14/26 | 05/20/26 | 6.2 | 6.2 |
|
123.8 |
RPL10.OFCI.6880 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.3 (ROJ ) (RVCD ) | NS1 | Not Started | 05/14/26 | 06/04/26 | 18.8 | 18.8 |
|
93.8 |
RPL10.WP2.CMDF1.1010 |
RPL10.Conn CMDF1 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
162.5 |
RPL10.WP2.CMDF2.1020 |
RPL10.Conn CMDF2 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/14/26 | 05/20/26 | 6.2 | 6.2 |
|
161.2 |
RPL10.WP2.GSIDF.1210 |
CorpNet & FacNet Available - EF | Network | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
232.5 |
RPL10.WP2.MDF1.1240 |
RPL10.Conn C.MDF1 <> GS.MDF1 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
165.0 |
RPL10.WP2.MDF2.1240 |
RPL10.Conn C.MDF2 <> GS.MDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/14/26 | 05/19/26 | 5.0 | 5.0 |
|
165.0 |
RPL10.CTRC.BB.1840 |
RPL10.Int.Build Back.Center-Corr - LO #7,7B - Arch Finishes - Frame and Hang Drywall, Paint, Final Finishes (LOE) | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 05/15/26 | 06/25/26 | 36.2 | 36.2 |
|
141.2 |
RPL10.CTRC.BB.1940 |
RPL10.Int.Build Back.Center-Corr - Interior Leave Out (Center Corridor) #7,#7B, #9 WBS Summary | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 05/15/26 | 07/24/26 | 61.2 | 61.2 |
|
141.2 |
RPL10.CTRC.BB.3555 |
RPL10.Int.Build Back.Center-Corr - LO #7B - Frame | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 05/15/26 | 05/19/26 | 3.8 | 3.8 |
|
160.0 |
RPL10.EY.EF2.01890 |
RPL10.EY.EF2 - Install RPL-3 FSP Columns Cap Erect Shoring & Decking & F/R/P (DPR Side) | Fiber Support Platform - RPL-3 | Not Started | 05/15/26 | 05/19/26 | 3.8 | 3.8 |
|
195.0 |
RPL10.INT.CTRC.01350 |
RPL10.Interior.Center-Corridor - BoW - Final Paint | Balance of Walls & OverHead | Not Started | 05/15/26 | 05/19/26 | 3.8 | 3.8 |
|
127.5 |
RPL10.INT.EF2.01170 |
RPL10.Interior.EF2 - CFCI - Set South CRAH Units | OFE | Not Started | 05/15/26 | 05/21/26 | 6.2 | 6.2 |
|
130.0 |
RPL10.INT.EF2.01200 |
RPL10.Interior.EF2 - Tie-ins - North CRAH Gallery - WBS Summary | North CRAH Gallery | Not Started | 05/15/26 | 06/26/26 | 37.5 | 37.5 |
|
177.5 |
RPL10.INT.EF2.01370 |
RPL10.Interior.EF2 - EF2 East - Install Upper Trays | East EF-2 | Not Started | 05/15/26 | 05/21/26 | 6.2 | 6.2 |
|
37.5 |
RPL10.INT.EF2.01390 |
RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 West | OFE | Not Started | 05/15/26 | 06/05/26 | 18.8 | 18.8 |
|
18.8 |
RPL10.INT.EF2.01730 |
RPL10.Interior.EF2 - North CRAH Gallery - Piping Tie-ins FW (In Gallery #3 CRAH Units) | North CRAH Gallery | Not Started | 05/15/26 | 05/28/26 | 11.2 | 11.2 |
|
136.2 |
RPL10.INT.NS1.01500 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/15/26 | 06/12/26 | 25.0 | 25.0 |
|
48.8 |
RPL10.INT.NS1.01510 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/15/26 | 06/12/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS1.02010 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/15/26 | 05/20/26 | 5.0 | 5.0 |
|
105.0 |
RPL10.INT.NS1.02240 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/15/26 | 06/12/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS1.02760 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/15/26 | 06/12/26 | 25.0 | 25.0 |
|
42.5 |
RPL10.INT.NS2.01660 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/15/26 | 05/20/26 | 5.0 | 5.0 |
|
118.8 |
RPL10.INT.NS2.02545 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (Mech Side Aisle) | OFE NS2 Control Fault Domain 5 | Not Started | 05/15/26 | 06/03/26 | 16.2 | 16.2 |
|
-8.8 |
RPL10.INT.NS4.01092 |
RPL10.Interior.NS4 - LV Skids and TopHat - Maintenance and Reserve Busways | NS4 - LV Skids and TopHat | Not Started | 05/15/26 | 06/05/26 | 18.8 | 18.8 |
|
165.0 |
RPL10.MCUP.LP1.2080 |
RPL10.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion | Tie-Ins Mechanical | Not Started | 05/15/26 | 05/28/26 | 11.2 | 11.2 |
|
12.5 |
RPL10.OFCI.6980 |
OFCI - Delivery ROJ: FE Fiber for CFD NS2.4 (ROJ ) (RVCD ) | NS2 | Not Started | 05/15/26 | 06/05/26 | 18.8 | 18.8 |
|
78.8 |
RPL10.SSBC.BB.1000 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - MEPF Trim Out | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/15/26 | 05/29/26 | 12.5 | 12.5 |
|
178.8 |
RPL10.SSBC.BB.1480 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - MEPF - OH, Lowside, Lights | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/15/26 | 05/29/26 | 12.5 | 12.5 |
|
178.8 |
JCL.C.1280 |
RPL10 - Cost Risk LOE-15 Security Systems | Cost LOEs | Not Started | 05/18/26 | 01/05/27 | 198.8 | 198.8 |
|
85.0 |
RPL10.EY.EF1.01290 |
RPL10.EY.EF1 - Install RPL-2 FSP Road Closure For Steel Erection | Fiber Support Platform - RPL-2 | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
202.5 |
RPL10.EY.EF1.01340 |
RPL10.EY.EF1 - Install RPL-1 FSP Final Roof (Standing Seam Panels) Phase 1 | Fiber Support Platform - RPL-1 | Not Started | 05/18/26 | 05/26/26 | 7.5 | 7.5 |
|
242.5 |
RPL10.EY.NS2.01290 |
RPL10.EY.NS2 - MV Loop 1 - L2 Checklist Completion | Tie-ins | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
27.5 |
RPL10.EY.SSB.01240 |
RPL10.EY.SSB - Install BMS Tie-ins | Tie-ins | Not Started | 05/18/26 | 06/08/26 | 18.8 | 18.8 |
|
120.0 |
RPL10.EY.SSB.01260 |
RPL10.EY.SSB - L2 Checklist Completion | Tie-ins | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
17.5 |
RPL10.INT.EF2.01490 |
RPL10.Interior.EF2 - Tie-ins - EF2 West - WBS Summary | West EF-2 | Not Started | 05/18/26 | 08/19/26 | 82.5 | 82.5 |
|
148.8 |