Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
1
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL.10.D.X33X0.XR |
Pull and Term mCUP Skids - RPL10 North | Power (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
35.0 |
RPL.10.D.X33X1.XR |
Pull and Term MV Skids - RPL10 NS1 Loop 1 & 2 | Power (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
42.5 |
RPL.10.D.X3900.XG |
Ready for MV Cable Pull mCUP South Loop (Loop#2) | Give Milestones (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
896.2 |
RPL10.CTRC.BB.3275 |
RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 05/04/26 | 05/05/26 | 2.5 | 2.5 |
|
127.5 |
RPL10.EY.EF1.01160 |
RPL10.EY.EF1 - Install RPL-1 FSP Install Steel Span Structure Modules | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 05/18/26 | 13.8 | 13.8 |
|
201.2 |
RPL10.EY.EF1.01170 |
RPL10.EY.EF1 - Install RPL-1 FSP Road Closure For Steel Erection | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
201.2 |
RPL10.EY.EF1.01180 |
RPL10.EY.EF1 - Install RPL-1 Total Road Closure For Fiber Supprt Platform | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 07/14/26 | 62.5 | 62.5 |
|
237.5 |
RPL10.EY.EF2.01240 |
RPL10.EY.EF2 - Install RPL-5 FSP Grounding Wire | Fiber Support Platform - RPL-5 | Not Started | 05/04/26 | 05/05/26 | 2.5 | 2.5 |
|
300.0 |
RPL10.EY.ENDC.01170 |
RPL10.EY.End - Install Lighting | Hardscape and Landscape | Not Started | 05/04/26 | 05/22/26 | 18.8 | 18.8 |
|
446.2 |
RPL10.EY.NS3.01210 |
RPL10.EY.NS3 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/27/26) | Tent and Temp Conditions | Not Started | 05/04/26 | 05/11/26 | 7.5 | 7.5 |
|
80.0 |
RPL10.INT.CTRC.01220 |
RPL10.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall *EPMS Separate Activty | Balance of Walls & OverHead | Not Started | 05/04/26 | 05/07/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.INT.EF1.01490 |
RPL10.Interior.EF1 - Tie-ins - EF1 West - WBS Summary | West EF-1 | Not Started | 05/04/26 | 07/14/26 | 62.5 | 62.5 |
|
168.8 |
RPL10.INT.EF1.01525 |
RPL10.Interior.EF1 - EF1 West - Install Wall Mounted Ladder Racks on Full Height EF Walls | West EF-1 | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
218.8 |
RPL10.INT.NS1.01260 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS1.01270 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS2.01170 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS2.01180 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS2.01190 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Set TWMS, UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
27.5 |
RPL10.INT.NS3.01070 |
RPL10.Interior.NS3 - OFE - MES Skids - Set / Place / Anchor | OFE | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
123.8 |
RPL10.INT.SSB.01760 |
RPL10.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In | Loading Dock and Storage | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.INT.SSB.01820 |
RPL10.Interior.SSB - BoW - Mechanical Tie-In | Balance of Walls and OverHead | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
220.0 |
RPL10.WP2.GSIDF.1180 |
RPL10.Conn GSIDFNE1 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/04/26 | 05/11/26 | 7.5 | 7.5 |
|
148.8 |
RPL10.WP2.GSIDF.1340 |
RPL10.Conn GSIDFN13 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
62.5 |
RPL10.WP2.GSIDF.1480 |
RPL10.Conn GSIDFN23 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
66.2 |
RPL10.WP2.GSIDF.1560 |
RPL10.Conn GSIDFN41 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
188.8 |
RPL10.WP2.GSIDF.1800 |
RPL10.Conn GSIDFN31 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
201.2 |
RPL10.EY.EF1.01680 |
RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Cure | Fiber Support Platform - RPL-2 | Not Started | 05/05/26 | 05/11/26 | 8.8 | 8.8 |
|
296.2 |
RPL10.INT.CTRC.01170 |
RPL10.Interior.Center-Corridor - BoW - Install Doors Frame | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
131.2 |
RPL10.INT.CTRC.01280 |
RPL10.Interior.Center-Corridor - BoW - Install Duct and Drops | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.INT.CTRC.01320 |
RPL10.Interior.Center-Corridor - BoW - MEPF Frame Hard Lid Rough In/Close of Inspection | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
131.2 |
RPL10.INT.EF1.01380 |
RPL10.Interior.EF1 - EF1 East - Install Upper Trays | East EF-1 | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
47.5 |
RPL10.INT.NS1.01390 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
55.0 |
RPL10.INT.NS1.01400 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
55.0 |
RPL10.INT.NS1.01410 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
32.5 |
RPL10.INT.NS3.02020 |
RPL10.Interior.NS3 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) | OFE | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
93.8 |
RPL10.INT.NS4.01060 |
RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.22.26) (Rev-05.04.26) | OFE | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
103.8 |
RPL10.INT.NS4.01065 |
RPL10.Interior.NS4 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor | OFE | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
152.5 |
RPL10.INT.SSBC.01590 |
RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Tie-Ins (needs to micro plan) | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
132.5 |
RPL10.INT.SSBC.03020 |
RPL10.Interior.SSB-Corridor - BoW - Plumbing Trim Out | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/13/26 | 8.8 | 8.8 |
|
138.8 |
RPL10.INT.SSBC.03040 |
RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/18/26 | 12.5 | 12.5 |
|
138.8 |
RPL10.INT.SSBC.03060 |
RPL10.Interior.SSB-Corridor - BoW - Asset Tagging | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
132.5 |
RPL10.SSB.BB.1125 |
RPL10.Ext.Build Back.SSB - LO #5 - Hang Exterior Drywall | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
437.5 |
RPL10.SSBC.BB.3275 |
RPL10.Int.Build Back.SSB-Corr - LO #4 - Hang Drywall | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/05/26 | 05/07/26 | 3.8 | 3.8 |
|
178.8 |
RPL10.WP2.GSIDF.3000 |
RPL10.Conn GSIDFNX13 Install & Test Network (FIM) | Network | Not Started | 05/05/26 | 05/07/26 | 3.8 | 3.8 |
|
238.8 |
RPL10.WP2.GSIDF.3520 |
RPL10.Conn GSIDFNX13 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/05/26 | 05/18/26 | 12.5 | 12.5 |
|
488.8 |
RPL10.CTRC.BB.3315 |
RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Hang Drywall (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 05/06/26 | 05/07/26 | 2.5 | 2.5 |
|
127.5 |
RPL10.EY.EF2.01410 |
RPL10.EY.EF2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
450.0 |
RPL10.EY.EF2.01420 |
RPL10.EY.EF2 - Early L2 Checklist Completion | Tie-ins | Not Started | 05/06/26 | 05/19/26 | 12.5 | 12.5 |
|
156.2 |
RPL10.EY.EF2.01430 |
RPL10.EY.EF2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/06/26 | 09/01/26 | 103.8 | 103.8 |
|
396.2 |
RPL10.INT.ENDC.01090 |
RPL10.Interior.End-Corridor - BoW - Install Security Lowside OH and In-Wall | Balance of Walls & Overhead | Not Started | 05/06/26 | 05/06/26 | 0.0 | 0.0 |
|
183.8 |
RPL10.INT.ENDC.1340 |
RPL10.Interior.End-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
247.5 |
RPL10.INT.ENDC.1440 |
RPL10.Interior.End-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
250.0 |
RPL10.INT.ENDC.1540 |
RPL10.Interior.End-Corridor - BoW - QC BoW Backing/In-Wall | Balance of Walls & Overhead | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
183.8 |
RPL10.INT.NS1.01340 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/06/26 | 06/03/26 | 25.0 | 25.0 |
|
37.5 |
RPL10.INT.NS1.01470 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/06/26 | 05/11/26 | 5.0 | 5.0 |
|
47.5 |
RPL10.INT.NS2.01210 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
31.2 |
RPL10.WP2.01010 |
RPL10.Conn SSB - Construction Cx Server Ready - At GSMDF | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/06/26 | 05/06/26 | 0.0 | 0.0 |
|
32.5 |
RPL10.WP4.08420 |
RPL10.Conn 10GSMDF2 Pull/Install Fanout (MMC<>UPC) [PON] | Pre ORv3 Rack | Not Started | 05/06/26 | 05/11/26 | 5.0 | 5.0 |
|
175.0 |
RPL.GF.D.G4620.XG |
Rack & Cabinets Complete - DHB - RPL6 | Give Milestones (XREFs) | Not Started | 05/07/26 | 05/07/26 | 0.0 | 0.0 |
|
455.0 |
RPL10.EY.EF2.01830 |
RPL10.EY.EF2 - Install RPL-5 FSP Columns Cap Erect Shoring & Decking & F/R/P (Center & Turner Side) | Fiber Support Platform - RPL-5 | Not Started | 05/07/26 | 05/14/26 | 7.5 | 7.5 |
|
195.0 |
RPL10.INT.CTRC.01260 |
RPL10.Interior.Center-Corridor - BoW - Remaining Electrical OFE Tie In | Balance of Walls & OverHead | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
127.5 |
RPL10.INT.CTRC.01420 |
RPL10.Interior.Center-Corridor - BoW - Install Battery | Balance of Walls & OverHead | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
125.0 |
RPL10.INT.NS1.01600 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
82.5 |
RPL10.INT.NS2.01680 |
RPL10.Interior.NS2 - Control Fault Domain 2 SQ5.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
63.8 |
RPL10.INT.NS2.01710 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 2 SQ5.2 - WBS Summary | Tie-Ins NS2 Control Fault Domain 2 | Not Started | 05/07/26 | 09/09/26 | 108.8 | 108.8 |
|
37.5 |
RPL10.INT.NS4.01090 |
RPL10.Interior.NS4 - LV Skids and TopHat Tie-ins (LOE) | NS4 - LV Skids and TopHat | Not Started | 05/07/26 | 06/12/26 | 32.5 | 32.5 |
|
165.0 |
RPL10.INT.NS4.01091 |
RPL10.Interior.NS4 - LV Skids and TopHat - Set & Anchor Interconnects | NS4 - LV Skids and TopHat | Not Started | 05/07/26 | 06/02/26 | 22.5 | 22.5 |
|
165.0 |
RPL10.INT.NS4.01094 |
RPL10.Interior.NS4 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins | NS4 - LV Skids and TopHat | Not Started | 05/07/26 | 05/28/26 | 18.8 | 18.8 |
|
152.5 |
RPL10.INT.SSB.01360 |
RPL10.Interior.SSB - BoW - Electrical Trim Out | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
173.8 |
RPL10.INT.SSB.01380 |
RPL10.Interior.SSB - BoW - Security Trim Out | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.01420 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Lock (Mob 1) | Loading Dock and Storage | Not Started | 05/07/26 | 05/08/26 | 2.5 | 2.5 |
|
177.5 |
RPL10.INT.SSB.02560 |
RPL10.Interior.SSB - BoW - ACT - Device Tiles | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
172.5 |
RPL10.INT.SSB.02580 |
RPL10.Interior.SSB - BoW - ACT - MEP Devices | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
172.5 |
RPL10.INT.SSB.04380 |
RPL10.Interior.SSB - BoW - Install Lights in ACT Ceiling | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/11/26 | 3.0 | 3.0 |
|
200.8 |
RPL10.INT.SSB.07080 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock (Mob 2) | Loading Dock and Storage | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
173.8 |
RPL10.INT.SSBC.01360 |
RPL10.Interior.SSB-Corridor - BoW - Set Equipment / Interior | Balance of Walls & OverHead | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
130.0 |
RPL10.INT.SSBC.01390 |
RPL10.Interior.SSB-Corridor - BoW - Install Battery | Balance of Walls & OverHead | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
123.8 |
RPL10.WP2.01050 |
RPL10.Conn SSB - Install GS Cabling - Misc Scope (ME to Confirm) | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
71.2 |
RPL10.WP2.CMDF1.1000 |
RPL10.Conn CMDF1 Install Infrastructure Racks, Tier1 | Infrastructure | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
162.5 |
RPL10.WP2.CMDF2.1000 |
RPL10.Conn CMDF2 Install Infrastructure Racks, Tier1 | Infrastructure | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
161.2 |
RPL10.CTRC.BB.3335 |
RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Tape, Float and Paint (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
127.5 |
RPL10.INT.EF1.01170 |
RPL10.Interior.EF1 - CFCI - Set South CRAH Units | OFE | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
118.8 |
RPL10.INT.EF2.01150 |
RPL10.Interior.EF2 - CFCI - Set North CRAH Units | OFE | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
130.0 |
RPL10.INT.NS1.01610 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/08/26 | 05/13/26 | 5.0 | 5.0 |
|
86.2 |
RPL10.INT.NS2.01370 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/08/26 | 05/13/26 | 5.0 | 5.0 |
|
37.5 |
RPL10.SSBC.BB.3295 |
RPL10.Int.Build Back.SSB-Corr - LO #4 - Tape, Float and Paint | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
178.8 |
GCD.RPL10.1827 |
Delivery of RMU - (First Delivery) - RPL10 - NS43 | Construction Milestones | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
107.5 |
PL10.WP2.GSIDF.1920 |
RPL10.Conn GSIDFN13 Install & Test Network (FIM) | Network | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
233.8 |
RPL.GF.D.N0280.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI1 | Connectivity (XREFs) | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
183.8 |
RPL10.EY.EF1.01250 |
RPL10.EY.EF1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
452.5 |
RPL10.EY.EF1.01260 |
RPL10.EY.EF1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/11/26 | 08/25/26 | 93.8 | 93.8 |
|
402.5 |
RPL10.EY.EF1.01350 |
RPL10.EY.EF1 - Install RPL-2 FSP Roofing Z Purlin (Logistic #7 Install) | Fiber Support Platform - RPL-2 | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
250.0 |
RPL10.EY.NS2.01280 |
RPL10.EY.NS2 - Install BMS Tie-ins | Tie-ins | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
27.5 |
RPL10.INT.EF2.01400 |
RPL10.Interior.EF2 - Tie-ins - EF2 East - WBS Summary | East EF-2 | Not Started | 05/11/26 | 08/05/26 | 76.2 | 76.2 |
|
155.0 |
RPL10.INT.EF2.01435 |
RPL10.Interior.EF2 - EF2 East - Install Wall Mounted Ladder Racks on Full Height EF Walls | East EF-2 | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
218.8 |
RPL10.INT.ENDC.01160 |
RPL10.Interior.End-Corridor - OFE - NS4 (1x GS.IDF) N43 (04.24.26) | OFE | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.INT.ENDC.01190 |
RPL10.Interior.End-Corridor - OFE - NS3 (1x GS.IDF) N33 (04.24.26) | OFE | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
208.8 |
RPL10.INT.NS1.01740 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/11/26 | 05/14/26 | 5.0 | 5.0 |
|
90.0 |
RPL10.INT.NS1.02540 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (HAC) | OFE NS1 Control Fault Domain 4 | Not Started | 05/11/26 | 06/01/26 | 18.8 | 18.8 |
|
-5.0 |
RPL10.INT.NS2.01240 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/11/26 | 06/08/26 | 25.0 | 25.0 |
|
27.5 |