Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
1
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL.10.D.X33X0.XR Pull and Term mCUP Skids - RPL10 North Power (XREFs) Not Started 05/04/26 05/04/26 0.0 0.0
0%
35.0
RPL.10.D.X33X1.XR Pull and Term MV Skids - RPL10 NS1 Loop 1 & 2 Power (XREFs) Not Started 05/04/26 05/04/26 0.0 0.0
0%
42.5
RPL.10.D.X3900.XG Ready for MV Cable Pull mCUP South Loop (Loop#2) Give Milestones (XREFs) Not Started 05/04/26 05/04/26 0.0 0.0
0%
896.2
RPL10.CTRC.BB.3275 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 05/04/26 05/05/26 2.5 2.5
0%
127.5
RPL10.EY.EF1.01160 RPL10.EY.EF1 - Install RPL-1 FSP Install Steel Span Structure Modules Fiber Support Platform - RPL-1 Not Started 05/04/26 05/18/26 13.8 13.8
0%
201.2
RPL10.EY.EF1.01170 RPL10.EY.EF1 - Install RPL-1 FSP Road Closure For Steel Erection Fiber Support Platform - RPL-1 Not Started 05/04/26 05/15/26 12.5 12.5
0%
201.2
RPL10.EY.EF1.01180 RPL10.EY.EF1 - Install RPL-1 Total Road Closure For Fiber Supprt Platform Fiber Support Platform - RPL-1 Not Started 05/04/26 07/14/26 62.5 62.5
0%
237.5
RPL10.EY.EF2.01240 RPL10.EY.EF2 - Install RPL-5 FSP Grounding Wire Fiber Support Platform - RPL-5 Not Started 05/04/26 05/05/26 2.5 2.5
0%
300.0
RPL10.EY.ENDC.01170 RPL10.EY.End - Install Lighting Hardscape and Landscape Not Started 05/04/26 05/22/26 18.8 18.8
0%
446.2
RPL10.EY.NS3.01210 RPL10.EY.NS3 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/27/26) Tent and Temp Conditions Not Started 05/04/26 05/11/26 7.5 7.5
0%
80.0
RPL10.INT.CTRC.01220 RPL10.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall *EPMS Separate Activty Balance of Walls & OverHead Not Started 05/04/26 05/07/26 5.0 5.0
0%
136.2
RPL10.INT.EF1.01490 RPL10.Interior.EF1 - Tie-ins - EF1 West - WBS Summary West EF-1 Not Started 05/04/26 07/14/26 62.5 62.5
0%
168.8
RPL10.INT.EF1.01525 RPL10.Interior.EF1 - EF1 West - Install Wall Mounted Ladder Racks on Full Height EF Walls West EF-1 Not Started 05/04/26 05/08/26 6.2 6.2
0%
218.8
RPL10.INT.NS1.01260 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/04/26 06/01/26 25.0 25.0
0%
40.0
RPL10.INT.NS1.01270 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/04/26 06/01/26 25.0 25.0
0%
40.0
RPL10.INT.NS2.01170 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/04/26 06/01/26 25.0 25.0
0%
40.0
RPL10.INT.NS2.01180 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/04/26 06/01/26 25.0 25.0
0%
40.0
RPL10.INT.NS2.01190 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Set TWMS, UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 05/04/26 06/01/26 25.0 25.0
0%
27.5
RPL10.INT.NS3.01070 RPL10.Interior.NS3 - OFE - MES Skids - Set / Place / Anchor OFE Not Started 05/04/26 06/01/26 25.0 25.0
0%
123.8
RPL10.INT.SSB.01760 RPL10.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In Loading Dock and Storage Not Started 05/04/26 05/08/26 6.2 6.2
0%
181.2
RPL10.INT.SSB.01820 RPL10.Interior.SSB - BoW - Mechanical Tie-In Balance of Walls and OverHead Not Started 05/04/26 05/08/26 6.2 6.2
0%
220.0
RPL10.WP2.GSIDF.1180 RPL10.Conn GSIDFNE1 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/04/26 05/11/26 7.5 7.5
0%
148.8
RPL10.WP2.GSIDF.1340 RPL10.Conn GSIDFN13 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/04/26 05/08/26 6.2 6.2
0%
62.5
RPL10.WP2.GSIDF.1480 RPL10.Conn GSIDFN23 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/04/26 05/08/26 6.2 6.2
0%
66.2
RPL10.WP2.GSIDF.1560 RPL10.Conn GSIDFN41 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/04/26 05/15/26 12.5 12.5
0%
188.8
RPL10.WP2.GSIDF.1800 RPL10.Conn GSIDFN31 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/04/26 05/15/26 12.5 12.5
0%
201.2
RPL10.EY.EF1.01680 RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Cure Fiber Support Platform - RPL-2 Not Started 05/05/26 05/11/26 8.8 8.8
0%
296.2
RPL10.INT.CTRC.01170 RPL10.Interior.Center-Corridor - BoW - Install Doors Frame Balance of Walls & OverHead Not Started 05/05/26 05/11/26 6.2 6.2
0%
131.2
RPL10.INT.CTRC.01280 RPL10.Interior.Center-Corridor - BoW - Install Duct and Drops Balance of Walls & OverHead Not Started 05/05/26 05/11/26 6.2 6.2
0%
125.0
RPL10.INT.CTRC.01320 RPL10.Interior.Center-Corridor - BoW - MEPF Frame Hard Lid Rough In/Close of Inspection Balance of Walls & OverHead Not Started 05/05/26 05/11/26 6.2 6.2
0%
131.2
RPL10.INT.EF1.01380 RPL10.Interior.EF1 - EF1 East - Install Upper Trays East EF-1 Not Started 05/05/26 05/11/26 6.2 6.2
0%
47.5
RPL10.INT.NS1.01390 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/05/26 06/02/26 25.0 25.0
0%
55.0
RPL10.INT.NS1.01400 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/05/26 06/02/26 25.0 25.0
0%
55.0
RPL10.INT.NS1.01410 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 05/05/26 06/02/26 25.0 25.0
0%
32.5
RPL10.INT.NS3.02020 RPL10.Interior.NS3 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) OFE Not Started 05/05/26 05/08/26 5.0 5.0
0%
93.8
RPL10.INT.NS4.01060 RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.22.26) (Rev-05.04.26) OFE Not Started 05/05/26 06/02/26 25.0 25.0
0%
103.8
RPL10.INT.NS4.01065 RPL10.Interior.NS4 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Not Started 05/05/26 05/11/26 6.2 6.2
0%
152.5
RPL10.INT.SSBC.01590 RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Tie-Ins (needs to micro plan) Balance of Walls & OverHead Not Started 05/05/26 05/11/26 6.2 6.2
0%
132.5
RPL10.INT.SSBC.03020 RPL10.Interior.SSB-Corridor - BoW - Plumbing Trim Out Balance of Walls & OverHead Not Started 05/05/26 05/13/26 8.8 8.8
0%
138.8
RPL10.INT.SSBC.03040 RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & OverHead Not Started 05/05/26 05/18/26 12.5 12.5
0%
138.8
RPL10.INT.SSBC.03060 RPL10.Interior.SSB-Corridor - BoW - Asset Tagging Balance of Walls & OverHead Not Started 05/05/26 05/11/26 6.2 6.2
0%
132.5
RPL10.SSB.BB.1125 RPL10.Ext.Build Back.SSB - LO #5 - Hang Exterior Drywall Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 05/05/26 05/11/26 6.2 6.2
0%
437.5
RPL10.SSBC.BB.3275 RPL10.Int.Build Back.SSB-Corr - LO #4 - Hang Drywall Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Not Started 05/05/26 05/07/26 3.8 3.8
0%
178.8
RPL10.WP2.GSIDF.3000 RPL10.Conn GSIDFNX13 Install & Test Network (FIM) Network Not Started 05/05/26 05/07/26 3.8 3.8
0%
238.8
RPL10.WP2.GSIDF.3520 RPL10.Conn GSIDFNX13 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/05/26 05/18/26 12.5 12.5
0%
488.8
RPL10.CTRC.BB.3315 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Hang Drywall (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 05/06/26 05/07/26 2.5 2.5
0%
127.5
RPL10.EY.EF2.01410 RPL10.EY.EF2 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/06/26 05/12/26 6.2 6.2
0%
450.0
RPL10.EY.EF2.01420 RPL10.EY.EF2 - Early L2 Checklist Completion Tie-ins Not Started 05/06/26 05/19/26 12.5 12.5
0%
156.2
RPL10.EY.EF2.01430 RPL10.EY.EF2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/06/26 09/01/26 103.8 103.8
0%
396.2
RPL10.INT.ENDC.01090 RPL10.Interior.End-Corridor - BoW - Install Security Lowside OH and In-Wall Balance of Walls & Overhead Not Started 05/06/26 05/06/26 0.0 0.0
0%
183.8
RPL10.INT.ENDC.1340 RPL10.Interior.End-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 05/06/26 05/12/26 6.2 6.2
0%
247.5
RPL10.INT.ENDC.1440 RPL10.Interior.End-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 05/06/26 05/12/26 6.2 6.2
0%
250.0
RPL10.INT.ENDC.1540 RPL10.Interior.End-Corridor - BoW - QC BoW Backing/In-Wall Balance of Walls & Overhead Not Started 05/06/26 05/12/26 6.2 6.2
0%
183.8
RPL10.INT.NS1.01340 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 05/06/26 06/03/26 25.0 25.0
0%
37.5
RPL10.INT.NS1.01470 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/06/26 05/11/26 5.0 5.0
0%
47.5
RPL10.INT.NS2.01210 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/06/26 05/12/26 6.2 6.2
0%
31.2
RPL10.WP2.01010 RPL10.Conn SSB - Construction Cx Server Ready - At GSMDF WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 05/06/26 05/06/26 0.0 0.0
0%
32.5
RPL10.WP4.08420 RPL10.Conn 10GSMDF2 Pull/Install Fanout (MMC<>UPC) [PON] Pre ORv3 Rack Not Started 05/06/26 05/11/26 5.0 5.0
0%
175.0
RPL.GF.D.G4620.XG Rack & Cabinets Complete - DHB - RPL6 Give Milestones (XREFs) Not Started 05/07/26 05/07/26 0.0 0.0
0%
455.0
RPL10.EY.EF2.01830 RPL10.EY.EF2 - Install RPL-5 FSP Columns Cap Erect Shoring & Decking & F/R/P (Center & Turner Side) Fiber Support Platform - RPL-5 Not Started 05/07/26 05/14/26 7.5 7.5
0%
195.0
RPL10.INT.CTRC.01260 RPL10.Interior.Center-Corridor - BoW - Remaining Electrical OFE Tie In Balance of Walls & OverHead Not Started 05/07/26 05/13/26 6.2 6.2
0%
127.5
RPL10.INT.CTRC.01420 RPL10.Interior.Center-Corridor - BoW - Install Battery Balance of Walls & OverHead Not Started 05/07/26 05/20/26 12.5 12.5
0%
125.0
RPL10.INT.NS1.01600 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/07/26 05/12/26 5.0 5.0
0%
82.5
RPL10.INT.NS2.01680 RPL10.Interior.NS2 - Control Fault Domain 2 SQ5.2 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/07/26 05/12/26 5.0 5.0
0%
63.8
RPL10.INT.NS2.01710 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 2 SQ5.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 2 Not Started 05/07/26 09/09/26 108.8 108.8
0%
37.5
RPL10.INT.NS4.01090 RPL10.Interior.NS4 - LV Skids and TopHat Tie-ins (LOE) NS4 - LV Skids and TopHat Not Started 05/07/26 06/12/26 32.5 32.5
0%
165.0
RPL10.INT.NS4.01091 RPL10.Interior.NS4 - LV Skids and TopHat - Set & Anchor Interconnects NS4 - LV Skids and TopHat Not Started 05/07/26 06/02/26 22.5 22.5
0%
165.0
RPL10.INT.NS4.01094 RPL10.Interior.NS4 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins NS4 - LV Skids and TopHat Not Started 05/07/26 05/28/26 18.8 18.8
0%
152.5
RPL10.INT.SSB.01360 RPL10.Interior.SSB - BoW - Electrical Trim Out Balance of Walls and OverHead Not Started 05/07/26 05/13/26 6.2 6.2
0%
173.8
RPL10.INT.SSB.01380 RPL10.Interior.SSB - BoW - Security Trim Out Balance of Walls and OverHead Not Started 05/07/26 05/15/26 8.8 8.8
0%
173.8
RPL10.INT.SSB.01420 RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Lock (Mob 1) Loading Dock and Storage Not Started 05/07/26 05/08/26 2.5 2.5
0%
177.5
RPL10.INT.SSB.02560 RPL10.Interior.SSB - BoW - ACT - Device Tiles Balance of Walls and OverHead Not Started 05/07/26 05/15/26 8.8 8.8
0%
172.5
RPL10.INT.SSB.02580 RPL10.Interior.SSB - BoW - ACT - MEP Devices Balance of Walls and OverHead Not Started 05/07/26 05/15/26 8.8 8.8
0%
172.5
RPL10.INT.SSB.04380 RPL10.Interior.SSB - BoW - Install Lights in ACT Ceiling Balance of Walls and OverHead Not Started 05/07/26 05/11/26 3.0 3.0
0%
200.8
RPL10.INT.SSB.07080 RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock (Mob 2) Loading Dock and Storage Not Started 05/07/26 05/13/26 6.2 6.2
0%
173.8
RPL10.INT.SSBC.01360 RPL10.Interior.SSB-Corridor - BoW - Set Equipment / Interior Balance of Walls & OverHead Not Started 05/07/26 05/13/26 6.2 6.2
0%
130.0
RPL10.INT.SSBC.01390 RPL10.Interior.SSB-Corridor - BoW - Install Battery Balance of Walls & OverHead Not Started 05/07/26 05/20/26 12.5 12.5
0%
123.8
RPL10.WP2.01050 RPL10.Conn SSB - Install GS Cabling - Misc Scope (ME to Confirm) WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 05/07/26 05/20/26 12.5 12.5
0%
71.2
RPL10.WP2.CMDF1.1000 RPL10.Conn CMDF1 Install Infrastructure Racks, Tier1 Infrastructure Not Started 05/07/26 05/13/26 6.2 6.2
0%
162.5
RPL10.WP2.CMDF2.1000 RPL10.Conn CMDF2 Install Infrastructure Racks, Tier1 Infrastructure Not Started 05/07/26 05/13/26 6.2 6.2
0%
161.2
RPL10.CTRC.BB.3335 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Tape, Float and Paint (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 05/08/26 05/14/26 6.2 6.2
0%
127.5
RPL10.INT.EF1.01170 RPL10.Interior.EF1 - CFCI - Set South CRAH Units OFE Not Started 05/08/26 05/14/26 6.2 6.2
0%
118.8
RPL10.INT.EF2.01150 RPL10.Interior.EF2 - CFCI - Set North CRAH Units OFE Not Started 05/08/26 05/14/26 6.2 6.2
0%
130.0
RPL10.INT.NS1.01610 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/08/26 05/13/26 5.0 5.0
0%
86.2
RPL10.INT.NS2.01370 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/08/26 05/13/26 5.0 5.0
0%
37.5
RPL10.SSBC.BB.3295 RPL10.Int.Build Back.SSB-Corr - LO #4 - Tape, Float and Paint Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Not Started 05/08/26 05/14/26 6.2 6.2
0%
178.8
GCD.RPL10.1827 Delivery of RMU - (First Delivery) - RPL10 - NS43 Construction Milestones Not Started 05/11/26 05/11/26 0.0 0.0
0%
107.5
PL10.WP2.GSIDF.1920 RPL10.Conn GSIDFN13 Install & Test Network (FIM) Network Not Started 05/11/26 05/13/26 3.8 3.8
0%
233.8
RPL.GF.D.N0280.XR Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI1 Connectivity (XREFs) Not Started 05/11/26 05/11/26 0.0 0.0
0%
183.8
RPL10.EY.EF1.01250 RPL10.EY.EF1 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/11/26 05/15/26 6.2 6.2
0%
452.5
RPL10.EY.EF1.01260 RPL10.EY.EF1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/11/26 08/25/26 93.8 93.8
0%
402.5
RPL10.EY.EF1.01350 RPL10.EY.EF1 - Install RPL-2 FSP Roofing Z Purlin (Logistic #7 Install) Fiber Support Platform - RPL-2 Not Started 05/11/26 05/22/26 12.5 12.5
0%
250.0
RPL10.EY.NS2.01280 RPL10.EY.NS2 - Install BMS Tie-ins Tie-ins Not Started 05/11/26 05/22/26 12.5 12.5
0%
27.5
RPL10.INT.EF2.01400 RPL10.Interior.EF2 - Tie-ins - EF2 East - WBS Summary East EF-2 Not Started 05/11/26 08/05/26 76.2 76.2
0%
155.0
RPL10.INT.EF2.01435 RPL10.Interior.EF2 - EF2 East - Install Wall Mounted Ladder Racks on Full Height EF Walls East EF-2 Not Started 05/11/26 05/15/26 6.2 6.2
0%
218.8
RPL10.INT.ENDC.01160 RPL10.Interior.End-Corridor - OFE - NS4 (1x GS.IDF) N43 (04.24.26) OFE Not Started 05/11/26 05/15/26 6.2 6.2
0%
208.8
RPL10.INT.ENDC.01190 RPL10.Interior.End-Corridor - OFE - NS3 (1x GS.IDF) N33 (04.24.26) OFE Not Started 05/11/26 05/15/26 6.2 6.2
0%
208.8
RPL10.INT.NS1.01740 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/11/26 05/14/26 5.0 5.0
0%
90.0
RPL10.INT.NS1.02540 RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (HAC) OFE NS1 Control Fault Domain 4 Not Started 05/11/26 06/01/26 18.8 18.8
0%
-5.0
RPL10.INT.NS2.01240 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 05/11/26 06/08/26 25.0 25.0
0%
27.5