Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
2
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.SSBC.04120 |
RPL10.Interior.SSB-Corridor - BoW - Install Fire Alarm Panel | Balance of Walls & OverHead | Not Started | 04/27/26 | 04/28/26 | 2.5 | 2.5 |
|
143.8 |
RPL10.MCUP.LP1.2000 |
RPL10.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
483.8 |
RPL10.MCUP.LP2.1760 |
RPL10.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 04/27/26 | 05/07/26 | 11.2 | 11.2 |
|
485.0 |
RPL10.OFCI.4000 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.6 (ROJ ) (RVCD ) | NS1 | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
48.8 |
RPL10.OFCI.6840 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.5 (ROJ ) (RVCD ) | NS1 | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
56.2 |
RPL10.OFCI.6860 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.4 (ROJ ) (RVCD ) | NS1 | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
83.8 |
RPL10.OFCI.6940 |
OFCI - Delivery ROJ: FE Fiber for CFD NS2.6 (ROJ ) (RVCD ) | NS2 | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
62.5 |
RPL10.OFCI.6960 |
OFCI - Delivery ROJ: FE Fiber for CFD NS2.5 (ROJ ) (RVCD ) | NS2 | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
70.0 |
RPL10.SSB.BB.1120 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Exterior Backing, In Wall | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
437.5 |
RPL10.SSBC.BB.3235 |
RPL10.Int.Build Back.SSB-Corr - LO #4 - Frame | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 04/27/26 | 04/29/26 | 3.8 | 3.8 |
|
178.8 |
RPL10.WP2.01000 |
RPL10.Conn SSB - Install GS Cabling Pull/Term/Test (GSMDF Cross Connects) (2x GSMDF) ~120 LF | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 04/27/26 | 06/08/26 | 37.5 | 37.5 |
|
56.2 |
RPL10.WP2.01160 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) EF1 NE1 WBS Summary | GSIDFNE1 | Not Started | 04/27/26 | 06/02/26 | 32.5 | 32.5 |
|
476.2 |
RPL10.WP2.EF1.1020 |
RPL10.Conn GS.EF1 Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
211.2 |
RPL10.WP2.EF1.1160 |
RPL10.Conn GS.EF1 Install Cabling for Path1 from (CAV 1/4) MMH to GS.EF (Pull, Splice & Terminate) | Cabling | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
181.2 |
RPL10.WP2.EF2.1020 |
RPL10.Conn GS.EF2 Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
211.2 |
RPL10.WP2.EF2.1040 |
RPL10.Conn GS.EF2 Install Cabling for Path1 from (CAV 1/4) MMH to GS.EF (Pull, Splice & Terminate) | Cabling | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
181.2 |
RPL10.WP2.GSIDF.1160 |
RPL10.Conn GSIDFNE1 Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
148.8 |
RPL10.WP2.GSIDF.1300 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 N13 WBS Summary | GSIDFN13 | Not Started | 04/27/26 | 05/27/26 | 27.5 | 27.5 |
|
222.5 |
RPL10.WP2.GSIDF.1320 |
RPL10.Conn GSIDFN13 Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
62.5 |
RPL10.WP2.GSIDF.1440 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 N23 WBS Summary | GSIDFN23 | Not Started | 04/27/26 | 05/27/26 | 27.5 | 27.5 |
|
222.5 |
RPL10.WP2.GSIDF.1460 |
RPL10.Conn GSIDFN23 Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
66.2 |
RPL10.WP2.GSIDF.1520 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS4 N41 WBS Summary | GSIDFN41 | Not Started | 04/27/26 | 06/03/26 | 33.8 | 33.8 |
|
300.0 |
RPL10.WP2.GSIDF.1540 |
RPL10.Conn GSIDFN41 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
188.8 |
RPL10.WP2.GSIDF.1760 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS3 N31 WBS Summary | GSIDFN31 | Not Started | 04/27/26 | 06/03/26 | 33.8 | 33.8 |
|
300.0 |
RPL10.WP2.GSIDF.1780 |
RPL10.Conn GSIDFN31 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
201.2 |
RPL10.WP2.GSIDF.2840 |
RPL10.Conn GSIDFNX11 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
22.5 |
RPL10.WP2.GSIDF.2920 |
RPL10.Conn GSIDFNX12 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
22.5 |
RPL10.WP2.GSIDF.2980 |
RPL10.Conn GSIDFNX13 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 04/27/26 | 05/04/26 | 7.5 | 7.5 |
|
33.8 |
RPL10.WP2.MDF1.1000 |
RPL10.Conn GSMDF1 Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 04/29/26 | 3.8 | 3.8 |
|
32.5 |
RPL10.WP2.MDF2.1000 |
RPL10.Conn GSMDF2 Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 04/27/26 | 04/29/26 | 3.8 | 3.8 |
|
32.5 |
RPL.GF.D.N0600.XG |
GS.IDF Hut Install Complete (01, 02, 06, 07) | Give Milestones (XREFs) | Not Started | 04/28/26 | 04/28/26 | 0.0 | 0.0 |
|
901.2 |
RPL10.CFCI.5070 |
RPL10 - Submittal Rvw/App'l - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 04/28/26 | 05/11/26 | 12.5 | 12.5 |
|
147.5 |
RPL10.CFCI.5290 |
RPL10 - Fabricate / Deliver - Carpet Tile | (CFCI) Div. 09 - Carpet | Not Started | 04/28/26 | 05/26/26 | 25.0 | 25.0 |
|
191.2 |
RPL10.CTRC.BB.2020 |
RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Hang Drywall (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 04/28/26 | 04/29/26 | 2.5 | 2.5 |
|
135.0 |
RPL10.EY.ENDC.01145 |
RPL10.EY.End - Install Mechanical Tie-ins | Tie-ins | Not Started | 04/28/26 | 05/11/26 | 12.5 | 12.5 |
|
286.2 |
RPL10.EY.NS1.01280 |
RPL10.EY.NS1 - Install BMS Tie-ins | Tie-ins | Not Started | 04/28/26 | 05/11/26 | 12.5 | 12.5 |
|
22.5 |
RPL10.EY.NS4.01210 |
RPL10.EY.NS4 - Tent Temp Conditioning Startup and Available (Including Acclimation) (04/10/26) | Tent and Temp Conditions | Not Started | 04/28/26 | 05/05/26 | 7.5 | 7.5 |
|
110.0 |
RPL10.INT.CTRC.01270 |
RPL10.Interior.Center-Corridor - OFE - Install UPS in Corridor (2x UPS) NS1/NS2 | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/11/26 | 12.5 | 12.5 |
|
133.8 |
RPL10.INT.CTRC.01300 |
RPL10.Interior.Center-Corridor - BoW - Frame Hard Lid | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.INT.CTRC.01590 |
RPL10.Interior.Center-Corridor - BoW - Install Electrical - NS3/NS4 UPS Gallery | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.INT.CTRC.01610 |
RPL10.Interior.Center-Corridor - BoW - Install Electrical - Lighning Inverter Rooms (N1/N2) | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.INT.CTRC.01850 |
RPL10.Interior.Center-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/01/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.INT.CTRC.07780 |
RPL10.Interior.Center-Corridor - BoW - Install Cable Tray (Remaining) | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
60.0 |
RPL10.INT.EF2.01090 |
RPL10.Interior.EF2 - Priority OH - Security | OverHead | Not Started | 04/28/26 | 04/29/26 | 2.5 | 2.5 |
|
168.8 |
RPL10.INT.NS1.01355 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/28/26 | 05/26/26 | 25.0 | 25.0 |
|
32.5 |
RPL10.INT.NS1.01360 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/28/26 | 05/26/26 | 25.0 | 25.0 |
|
55.0 |
RPL10.INT.NS1.01370 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/28/26 | 05/26/26 | 25.0 | 25.0 |
|
32.5 |
RPL10.INT.NS1.02220 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/28/26 | 05/26/26 | 25.0 | 25.0 |
|
32.5 |
RPL10.INT.NS4.01100 |
RPL10.Interior.NS4 - Tie-ins - WBS Summary | Tie-Ins | Not Started | 04/28/26 | 12/29/26 | 211.2 | 211.2 |
|
130.0 |
RPL10.INT.NS4.01110 |
RPL10.Interior.NS4 - MES Skids Tie-ins (LOE) | NS4 - MES Skids | Not Started | 04/28/26 | 07/22/26 | 75.0 | 75.0 |
|
237.5 |
RPL10.INT.NS4.01111 |
RPL10.Interior.NS4 - MES Skids - Set & Anchor Interconnects | NS4 - MES Skids | Not Started | 04/28/26 | 06/01/26 | 30.0 | 30.0 |
|
135.0 |
RPL10.INT.SSB.01280 |
RPL10.Interior.SSB - BoW - Duct Drops / Trim out | Balance of Walls and OverHead | Not Started | 04/28/26 | 05/06/26 | 8.8 | 8.8 |
|
173.8 |
RPL10.INT.SSB.02540 |
RPL10.Interior.SSB - BoW - ACT - Ceiling Grid & Wires | Balance of Walls and OverHead | Not Started | 04/28/26 | 05/06/26 | 8.8 | 8.8 |
|
71.2 |
RPL10.INT.SSBC.01252 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (10.S2.07) | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/06/26 | 8.8 | 8.8 |
|
123.8 |
RPL10.INT.SSBC.02700 |
RPL10.Interior.SSB-Corridor - BoW - Install Split Systems/Humidifiers | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
132.5 |
RPL10.INT.SSBC.02960 |
RPL10.Interior.SSB-Corridor - BoW - Electrical Trim Out | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/06/26 | 8.8 | 8.8 |
|
96.2 |
RPL10.INT.SSBC.02980 |
RPL10.Interior.SSB-Corridor - BoW - Install Lights | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/04/26 | 6.2 | 6.2 |
|
132.5 |
RPL10.INT.SSBC.03460 |
RPL10.Interior.Center-Corridor - BoW - Bed Tape Paint (OFE Room Closing) | Balance of Walls & OverHead | Not Started | 04/28/26 | 05/06/26 | 8.8 | 8.8 |
|
127.5 |
RPL10.EY.EF1.01210 |
RPL10.EY.EF1 - Install Mechanical Tie-ins (include penetration detail) | Tie-ins | Not Started | 04/29/26 | 05/08/26 | 10.0 | 10.0 |
|
141.2 |
RPL10.EY.EF1.01220 |
RPL10.EY.EF1 - Tie-ins - WBS Summary | Tie-ins | Not Started | 04/29/26 | 06/10/26 | 37.5 | 37.5 |
|
126.2 |
RPL10.EY.EF1.01330 |
RPL10.EY.EF1 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 04/29/26 | 05/19/26 | 18.8 | 18.8 |
|
126.2 |
RPL10.EY.EF2.01380 |
RPL10.EY.EF2 - Install BMS Tie-ins | Tie-ins | Not Started | 04/29/26 | 05/05/26 | 6.2 | 6.2 |
|
156.2 |
RPL10.EY.EF2.01620 |
RPL10.EY.EF2 - Install Remaining Mechanical Tie-ins | Tie-ins | Not Started | 04/29/26 | 05/08/26 | 10.0 | 10.0 |
|
191.2 |
RPL10.EY.EF2.01630 |
RPL10.EY.EF2 - Install Remaining Electrical Tie-ins | Tie-ins | Not Started | 04/29/26 | 05/05/26 | 6.2 | 6.2 |
|
195.0 |
RPL10.EY.NS3.01180 |
RPL10.EY.NS3 - Install Tent Electrical Tie-ins | Tent and Temp Conditions | Not Started | 04/29/26 | 05/01/26 | 3.8 | 3.8 |
|
80.0 |
RPL10.INT.NS1.01300 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/29/26 | 05/27/26 | 25.0 | 25.0 |
|
36.2 |
RPL10.INT.NS4.02020 |
RPL10.Interior.NS4 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) | OFE | Not Started | 04/29/26 | 05/04/26 | 5.0 | 5.0 |
|
93.8 |
JCL.C.1420 |
RPL10 - Cost Risk LOE-19 Connectivity Package 4A - Front End Network | Cost LOEs | Not Started | 04/30/26 | 04/16/27 | 301.2 | 301.2 |
|
0.0 |
RPL.GF.D.N0520.XG |
Ready for Mortenson to Test CAV1 to GS.EF1 | Give Milestones (XREFs) | Not Started | 04/30/26 | 04/30/26 | 0.0 | 0.0 |
|
898.8 |
RPL.GF.D.N0530.XG |
Ready for Mortenson to Test CAV4 to EF1F | Give Milestones (XREFs) | Not Started | 04/30/26 | 04/30/26 | 0.0 | 0.0 |
|
898.8 |
RPL10.CTRC.BB.2040 |
RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Tape, Float and Paint (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
135.0 |
RPL10.EY.EF2.01190 |
RPL10.EY.EF2 - Install RPL-3 FSP Grounding Wire | Fiber Support Platform - RPL-3 | Not Started | 04/30/26 | 05/01/26 | 2.5 | 2.5 |
|
302.5 |
RPL10.EY.EF2.01810 |
RPL10.EY.EF2 - Install RPL-3 FSP Columns Cap Erect Shoring & Decking & F/R/P (Center & Turner Side) | Fiber Support Platform - RPL-3 | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
195.0 |
RPL10.INT.CTRC.01390 |
RPL10.Interior.Center-Corridor - BoW - Set Equipment / Interior | Balance of Walls & OverHead | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
125.0 |
RPL10.INT.CTRC.01430 |
RPL10.Interior.Center-Corridor - BoW - Electrical Trim Out (Both Side of Corridor Wall) | Balance of Walls & OverHead | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
207.5 |
RPL10.INT.CTRC.01790 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) | Balance of Walls & OverHead | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
135.0 |
RPL10.INT.CTRC.07740 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Panel | Balance of Walls & OverHead | Not Started | 04/30/26 | 05/01/26 | 2.5 | 2.5 |
|
210.0 |
RPL10.INT.NS2.01113 |
RPL10.Interior.NS2 - MES Skids - CDU Tie-Ins ( 2 per day) | NS2 - MES Skids | Not Started | 04/30/26 | 06/03/26 | 30.0 | 30.0 |
|
157.5 |
RPL10.INT.NS2.01790 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 1 SQ6.2 (LV Side Aisle, HAC, Mech Side Aisle) | OFE NS2 Control Fault Domain 1 | Not Started | 04/30/26 | 08/27/26 | 105.0 | 105.0 |
|
-18.8 |
RPL10.INT.NS2.02745 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 1 SQ6.2 (LV Side Aisle) | OFE NS2 Control Fault Domain 1 | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
65.0 |
RPL10.SSBC.BB.3255 |
RPL10.Int.Build Back.SSB-Corr - LO #4 - MEPF - In Wall | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 04/30/26 | 05/04/26 | 3.8 | 3.8 |
|
178.8 |
RPL10.WP2.MDF1.1180 |
RPL10.Conn GSMDF1<>GSMDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
85.0 |
RPL10.WP2.MDF1.1200 |
RPL10.Conn GSMDF1 - Install, Copper & WAPs | Cabling | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
500.0 |
RPL10.WP2.MDF1.1220 |
RPL10.Conn GSMDF1 - Includes Rack/ Stack/ Patch | Network | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
32.5 |
RPL10.WP2.MDF1.1260 |
RPL10.Conn GS.EF1 <> GS.MDF1 - Pull, Splice, Terminate & Test | Cabling | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
32.5 |
RPL10.WP2.MDF2.1180 |
RPL10.Conn GSMDF2 - Install, Copper & WAPs | Cabling | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
500.0 |
RPL10.WP2.MDF2.1220 |
RPL10.Conn GSMDF2 - Includes Rack/ Stack/ Patch | Network | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
32.5 |
RPL10.WP2.MDF2.1260 |
RPL10.Conn GS.EF2 <> GS.MDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
32.5 |
RPL10.WP4.08400 |
RPL10.Conn 10GSMDF1 Pull/Install Fanout (MMC<>UPC) [PON] | Pre ORv3 Rack | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
175.0 |
RPL.10.D.X1440.XR |
Ready for Fiber Support Platform Construction - AI 2 (TCCO est Release 01-May-26) | Connectivity (XREFs) | Not Started | 05/01/26 | 05/01/26 | 0.0 | 0.0 |
|
216.2 |
RPL10.INT.CTRC.01870 |
RPL10.Interior.Center-Corridor - BoW - Install Split Systems/Humidifiers | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
143.8 |
RPL10.INT.EF1.01150 |
RPL10.Interior.EF1 - CFCI - Set North CRAH Units | OFE | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
113.8 |
RPL10.INT.NS2.01540 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
58.8 |
RPL10.INT.NS2.01570 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 3 SQ4.2 - WBS Summary | Tie-Ins NS2 Control Fault Domain 3 | Not Started | 05/01/26 | 08/18/26 | 95.0 | 95.0 |
|
41.2 |
RPL10.INT.SSBC.02780 |
RPL10.Interior.SSB-Corridor - BoW - Duct Drops Trim out | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
136.2 |
RPL10.INT.SSBC.03000 |
RPL10.Interior.SSB-Corridor - BoW - Security Trim Out (Both Side of Corridor Wall) | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/11/26 | 8.8 | 8.8 |
|
138.8 |
RPL10.SSB.BB.1240 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Security Lowside OH | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
447.5 |
RPL10.SSB.BB.1300 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Electrical Lowside OH | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
447.5 |
RPL10.SSB.BB.1320 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Controls / EPMS / BMS Lowside OH | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
447.5 |
RPL10.SSB.BB.1360 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Frame, Doors, Hardware | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/01/26 | 05/04/26 | 2.5 | 2.5 |
|
437.5 |