Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
2
Completed
20
In Progress
4
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.MCUP.LP2.1720 |
RPL10.MCUP.Loop 2 - Tie-in BMS #2 | Tie-Ins BMS | Active | 04/22/26 | 05/26/26 | 11.2 | 11.2 |
|
138.8 |
RPL10.MCUP.LP2.1820 |
RPL10.MCUP.Loop 2 - Tie-in BMS #4 | Tie-Ins BMS | Active | 04/22/26 | 05/28/26 | 8.8 | 8.8 |
|
136.2 |
RPL10.MCUP.LP2.1880 |
RPL10.MCUP.Loop 2 - Tie-in BMS #6 | Tie-Ins BMS | Active | 04/22/26 | 05/28/26 | 8.8 | 8.8 |
|
136.2 |
RPL10.MCUP.LP2.1980 |
RPL10.MCUP.Loop 2 - Tie-in BMS #8 | Tie-Ins BMS | Active | 04/22/26 | 05/28/26 | 11.2 | 11.2 |
|
136.2 |
RPL10.CTRC.BB.2000 |
RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Active | 04/23/26 | 04/27/26 | 2.5 | 1.2 |
|
135.0 |
RPL10.EY.EF1.01660 |
RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Erect Shoring & Decking & F/R/P | Fiber Support Platform - RPL-2 | Active | 04/23/26 | 05/04/26 | 7.5 | 7.5 |
|
207.5 |
RPL10.INT.NS4.02440 |
RPL10.Interior.NS43 - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Complete | 04/23/26 | 04/24/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02460 |
RPL10.Interior.NS43 - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Complete | 04/23/26 | 04/24/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01310 |
RPL10.Interior.SSB - BoW - MEPF Hard Lid Rough-In | Balance of Walls and OverHead | Active | 04/23/26 | 04/27/26 | 6.2 | 1.2 |
|
137.5 |
RPL10.MCUP.LP2.1840 |
RPL10.MCUP.Loop 2 - Tie-in EPMS #6 | Tie-Ins EPMS | Active | 04/23/26 | 05/27/26 | 7.5 | 7.5 |
|
136.2 |
RPL10.MCUP.LP2.1900 |
RPL10.MCUP.Loop 2 - Tie-in Electrical #6 | Tie-Ins Electrical | Active | 04/23/26 | 05/26/26 | 8.8 | 23.8 |
|
136.2 |
RPL10.MCUP.LP2.1940 |
RPL10.MCUP.Loop 2 - Tie-in EPMS #8 | Tie-Ins EPMS | Active | 04/23/26 | 05/27/26 | 8.8 | 8.8 |
|
136.2 |
RPL10.MCUP.LP2.2620 |
RPL10.MCUP.Loop 2 - Condenser WaterTie-in Mechanical #2 | Tie-in Mechanical #2 | Active | 04/23/26 | 05/08/26 | 10.0 | 12.5 |
|
148.8 |
RPL10.MCUP.LP2.2660 |
RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #4 | Tie-in Mechanical #4 | Active | 04/23/26 | 05/22/26 | 7.5 | 25.0 |
|
136.2 |
RPL10.MCUP.LP2.2700 |
RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #6 | Tie-in Mechanical #6 | Active | 04/23/26 | 05/22/26 | 7.5 | 25.0 |
|
136.2 |
RPL10.MCUP.LP2.2740 |
RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #8 | Tie-in Mechanical #8 | Active | 04/23/26 | 05/22/26 | 10.0 | 25.0 |
|
136.2 |
RPL10.EY.EF2.01200 |
RPL10.EY.EF2 - Install RPL-5 FSP Columns F/R/P | Fiber Support Platform - RPL-5 | Active | 04/24/26 | 05/01/26 | 6.2 | 6.2 |
|
198.8 |
RPL10.INT.CTRC.01650 |
RPL10.Interior.Center-Corridor - BoW - Tape, Float and Paint BoW | Balance of Walls & OverHead | Active | 04/24/26 | 04/29/26 | 5.0 | 3.8 |
|
125.0 |
RPL10.INT.NS1.01204 |
RPL10.Interior.NS1 - MES Skids - BMS Tie-Ins | NS1 - MES Skids | Active | 04/24/26 | 06/04/26 | 30.0 | 13.8 |
|
140.0 |
RPL10.INT.NS2.01630 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS2 Control Fault Domain 2 | Active | 04/24/26 | 08/06/26 | 91.2 | 90.0 |
|
-16.2 |
RPL10.INT.NS2.02685 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle) | OFE NS2 Control Fault Domain 2 | Active | 04/24/26 | 04/29/26 | 5.0 | 3.8 |
|
51.2 |
RPL10.MCUP.LP2.2000 |
RPL10.MCUP.Loop 2 - Tie-in Electrical #8 | Tie-Ins Electrical | Active | 04/24/26 | 05/26/26 | 11.2 | 23.8 |
|
136.2 |
RPL10.EY.EF1.01640 |
RPL10.EY.EF1 - Install RPL-1 FSP Columns Cap Cure | Fiber Support Platform - RPL-1 | Not Started | 04/26/26 | 05/02/26 | 8.8 | 8.8 |
|
286.2 |
DCC.B10.3010 |
[NWB] Production Gear Delivered [Network Suite] DR/EBB | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3015 |
[NWB] Production Gear Delivered [Network Suite] MA | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
433.8 |
DCC.B10.3020 |
[NWB] Production Gear Delivered [Network Suite] XSW | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
433.8 |
DCC.B10.3025 |
[NWB] Production Gear Delivered [NWS1] Front End (SSW & FSW) | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3027 |
[NWB] Production Gear Delivered [NWS1] Back End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3035 |
[NWB] Production Gear Delivered [NWS2] Front End (SSW & FSW) | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3037 |
[NWB] Production Gear Delivered [NWS2] Back End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3045 |
[NWB] Production Gear Delivered [NWS3] Front End (SSW & FSW) | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3047 |
[NWB] Production Gear Delivered [NWS3] Back End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3055 |
[NWB] Production Gear Delivered [NWS4] Front End (SSW & FSW) | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3057 |
[NWB] Production Gear Delivered [NWS4] Back End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3165 |
[NWB] PortMaps Delivered : GS | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3170 |
[NWB] PortMaps Delivered : Elevations & Cabling | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3175 |
[NWB] PortMaps Delivered :Backbone | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3180 |
[NWB] PortMaps Delivered :Front End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3185 |
[NWB] PortMaps Delivered :Back End | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3300 |
[NWB] Cabling Start : OSP Pathways - Primary GS | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3410 |
[NWB] IBB1.1 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3420 |
[NWB] IBB1.2 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3430 |
[NWB] DCN 1 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3440 |
[NWB] CORP 1 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3450 |
[NWB] CORP OOB1 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3460 |
[NWB] Production Dark Fiber Path 1 - Circuit Delivered | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
DCC.B10.3707 |
[NWB] Cabling Start : General Services (GS) | Connectivity | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
ICM.B10.1805 |
[NWB] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE | Construction | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
JCL.C.1260 |
RPL10 - Cost Risk LOE-14 Cabling | Cost LOEs | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
208.8 |
RPL.10.D.X1410.XR |
Ready for Fiber Support Platform Construction - AI 1 (TCCO est Release 09-Feb-26) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
207.5 |
RPL.10.D.X3210.XR |
500kva Temp Power Skids Energized (First 10 MW or Gen) | Power (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
41.2 |
RPL.10.D.X4510.XR |
Storm Available for Roof Drain Tie-ins | Pad Ready (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
182.5 |
RPL.CM.D.C5620.XR |
Naboo Road | Logistics - Onsite Receive XREF Milestones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
RPL.CM.D.N5620.XR |
LA 183 /Wade - Traffic Signal | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
140.0 |
RPL.CM.D.N5630.XR |
LA 183 /Fortenberry - Traffic Signal | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
496.2 |
RPL.CM.D.N5650.XR |
I-20 / LA 583 Right Turn Lane | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
150.0 |
RPL.CM.D.N5655.XR |
US 80 Traffic Signals at LA 583, LA 183 and LA 609 | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
150.0 |
RPL.CM.D.N5695.XR |
LA 854 - (Donahue Rd - LA183) Repaving / Overlay | Logistics - Off-Site Receive XREF Milsetones | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
RPL.GF.D.N0110.XR |
2 of 4 Fiber Pulls Complete (CAV1/4) MMH to GS.EF1/ Prod.EF1F | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
178.8 |
RPL.GF.D.N0120.XR |
4 of 4 Fiber Pulls Complete CAV2/3 to GS.EF2/ Prod.EF2B | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL.GF.D.N0261.XR |
GS.IDF Hut 10-Way Install Complete (03, 04, 08, 09, 10) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
221.2 |
RPL.GF.D.N0262.XR |
GS.IDF Hut 10-Way Install Complete (01, 02, 06, 07) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
36.2 |
RPL.GF.D.N0263.XR |
GS.IDF Hut 10-Way Install Complete (11, 12, 13, 05) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
903.8 |
RPL.GF.D.N0520.XR |
Radio Tower(s) Available for DAS/PS - SSB, NWS1, NWS2, EF1, EF2 RPL10 ( WP3B - Successor) - Commissoning affect? | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
93.8 |
RPL.GF.D.N0530.XR |
Radio Tower(s) Available for DAS/PS - NWS3, NWS4 (WP3B-Successor) - Commissoning affect? | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
93.8 |
RPL.GF.D.N0540.XR |
GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to iBOS (META's Ware House logistics) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL.GF.D.N0550.XR |
GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to Admin Building | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL.GF.D.N0560.XR |
GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH1 (Guard House) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL.GF.D.N0570.XR |
GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH2 (Guard House) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL.GF.D.N0580.XR |
GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH3 (Guard House) | Connectivity (XREFs) | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
211.2 |
RPL10.CFCI.5690 |
RPL10 - Fabricate / Deliver - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 04/27/26 | 08/04/26 | 87.5 | 87.5 |
|
126.2 |
RPL10.EY.EF1.01310 |
RPL10.EY.EF1 - Install RPL-1 FSP Roofing Z Purlin (Logistic #7 Install) | Fiber Support Platform - RPL-1 | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
248.8 |
RPL10.EY.EF1.01560 |
RPL10.EY.EF1 - Install CU (12) | OFE | Not Started | 04/27/26 | 04/28/26 | 2.5 | 2.5 |
|
126.2 |
RPL10.EY.EF2.01770 |
RPL10.EY.EF2 - Install Remaining CU (12) | OFE | Not Started | 04/27/26 | 04/28/26 | 2.5 | 2.5 |
|
191.2 |
RPL10.EY.ENDC.01120 |
RPL10.EY.End - Install Perm Paving | Hardscape and Landscape | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
446.2 |
RPL10.EY.ENDC.01130 |
RPL10.EY.End - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
177.5 |
RPL10.EY.ENDC.01160 |
RPL10.EY.End - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 04/27/26 | 07/07/26 | 62.5 | 62.5 |
|
446.2 |
RPL10.EY.NS2.01250 |
RPL10.EY.NS2 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
27.5 |
RPL10.EY.NS2.01260 |
RPL10.EY.NS2 - Tie-ins - WBS Summary | Tie-ins | Not Started | 04/27/26 | 06/08/26 | 37.5 | 37.5 |
|
62.5 |
RPL10.EY.NS3.01140 |
RPL10.EY.NS3 - Install Tent Electrical Panels | Tent and Temp Conditions | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
80.0 |
RPL10.EY.NS3.01150 |
RPL10.EY.NS3 - Install Tent Heating and Cooling Equipment | Tent and Temp Conditions | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
86.2 |
RPL10.EY.NS3.01160 |
RPL10.EY.NS3 - Install Tent Overhead Doors | Tent and Temp Conditions | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
86.2 |
RPL10.EY.NS3.01190 |
RPL10.EY.NS3 - Install Tent Mechanical Tie-ins | Tent and Temp Conditions | Not Started | 04/27/26 | 05/04/26 | 7.5 | 7.5 |
|
86.2 |
RPL10.INT.EF1.01390 |
RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 West | OFE | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
30.0 |
RPL10.INT.EF1.01400 |
RPL10.Interior.EF1 - Tie-ins - EF1 East - WBS Summary | East EF-1 | Not Started | 04/27/26 | 06/23/26 | 51.2 | 51.2 |
|
180.0 |
RPL10.INT.EF1.01435 |
RPL10.Interior.EF1 - EF1 East - Install Wall Mounted Ladder Racks on Full Height EF Walls | East EF-1 | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
218.8 |
RPL10.INT.ENDC.01110 |
RPL10.Interior.End-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 04/27/26 | 05/05/26 | 8.8 | 8.8 |
|
183.8 |
RPL10.INT.ENDC.01130 |
RPL10.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Fit out | Not Started | 04/27/26 | 04/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01230 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS1.02500 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (Mech Side Aisle) | OFE NS1 Control Fault Domain 5 | Not Started | 04/27/26 | 05/13/26 | 16.2 | 16.2 |
|
2.5 |
RPL10.INT.NS2.01094 |
RPL10.Interior.NS2 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins | NS2 - LV Skids and TopHat | Not Started | 04/27/26 | 05/15/26 | 18.8 | 18.8 |
|
33.8 |
RPL10.INT.NS2.01140 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS2.01150 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
27.5 |
RPL10.INT.NS2.01400 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 04/27/26 | 04/30/26 | 5.0 | 5.0 |
|
53.8 |
RPL10.INT.NS2.01430 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 4 SQ3.2 (including IDF) - WBS Summary | Tie-Ins NS2 Control Fault Domain 4 | Not Started | 04/27/26 | 07/28/26 | 81.2 | 81.2 |
|
33.8 |
RPL10.INT.NS2.02180 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
27.5 |
RPL10.INT.NS2.02805 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
27.5 |
RPL10.INT.SSB.01720 |
RPL10.Interior.SSB - BoW - Install Refrigerant Piping Lowside OH (ERAD Room) | Balance of Walls and OverHead | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
181.2 |
RPL10.INT.SSB.01840 |
RPL10.Interior.SSB - BoW - Install Split Systems/Humidifiers | Balance of Walls and OverHead | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
213.8 |
RPL10.INT.SSBC.02860 |
RPL10.Interior.SSB-Corridor - BoW - Install Doors (Verify with Trades before Installation) | Balance of Walls & OverHead | Not Started | 04/27/26 | 04/29/26 | 3.8 | 3.8 |
|
136.2 |