Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
2
Completed
20
In Progress
4
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.MCUP.LP2.1720 RPL10.MCUP.Loop 2 - Tie-in BMS #2 Tie-Ins BMS Active 04/22/26 05/26/26 11.2 11.2
0%
138.8
RPL10.MCUP.LP2.1820 RPL10.MCUP.Loop 2 - Tie-in BMS #4 Tie-Ins BMS Active 04/22/26 05/28/26 8.8 8.8
0%
136.2
RPL10.MCUP.LP2.1880 RPL10.MCUP.Loop 2 - Tie-in BMS #6 Tie-Ins BMS Active 04/22/26 05/28/26 8.8 8.8
0%
136.2
RPL10.MCUP.LP2.1980 RPL10.MCUP.Loop 2 - Tie-in BMS #8 Tie-Ins BMS Active 04/22/26 05/28/26 11.2 11.2
0%
136.2
RPL10.CTRC.BB.2000 RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Active 04/23/26 04/27/26 2.5 1.2
0%
135.0
RPL10.EY.EF1.01660 RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Erect Shoring & Decking & F/R/P Fiber Support Platform - RPL-2 Active 04/23/26 05/04/26 7.5 7.5
0%
207.5
RPL10.INT.NS4.02440 RPL10.Interior.NS43 - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Complete 04/23/26 04/24/26 2.5 0.0
100%
0.0
RPL10.INT.NS4.02460 RPL10.Interior.NS43 - Temp Conditions - Install Early Temp Conditions Temp Conditions Complete 04/23/26 04/24/26 2.5 0.0
100%
0.0
RPL10.INT.SSB.01310 RPL10.Interior.SSB - BoW - MEPF Hard Lid Rough-In Balance of Walls and OverHead Active 04/23/26 04/27/26 6.2 1.2
0%
137.5
RPL10.MCUP.LP2.1840 RPL10.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Active 04/23/26 05/27/26 7.5 7.5
0%
136.2
RPL10.MCUP.LP2.1900 RPL10.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Active 04/23/26 05/26/26 8.8 23.8
0%
136.2
RPL10.MCUP.LP2.1940 RPL10.MCUP.Loop 2 - Tie-in EPMS #8 Tie-Ins EPMS Active 04/23/26 05/27/26 8.8 8.8
0%
136.2
RPL10.MCUP.LP2.2620 RPL10.MCUP.Loop 2 - Condenser WaterTie-in Mechanical #2 Tie-in Mechanical #2 Active 04/23/26 05/08/26 10.0 12.5
0%
148.8
RPL10.MCUP.LP2.2660 RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #4 Tie-in Mechanical #4 Active 04/23/26 05/22/26 7.5 25.0
0%
136.2
RPL10.MCUP.LP2.2700 RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #6 Tie-in Mechanical #6 Active 04/23/26 05/22/26 7.5 25.0
0%
136.2
RPL10.MCUP.LP2.2740 RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #8 Tie-in Mechanical #8 Active 04/23/26 05/22/26 10.0 25.0
0%
136.2
RPL10.EY.EF2.01200 RPL10.EY.EF2 - Install RPL-5 FSP Columns F/R/P Fiber Support Platform - RPL-5 Active 04/24/26 05/01/26 6.2 6.2
0%
198.8
RPL10.INT.CTRC.01650 RPL10.Interior.Center-Corridor - BoW - Tape, Float and Paint BoW Balance of Walls & OverHead Active 04/24/26 04/29/26 5.0 3.8
0%
125.0
RPL10.INT.NS1.01204 RPL10.Interior.NS1 - MES Skids - BMS Tie-Ins NS1 - MES Skids Active 04/24/26 06/04/26 30.0 13.8
0%
140.0
RPL10.INT.NS2.01630 RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 2 Active 04/24/26 08/06/26 91.2 90.0
0%
-16.2
RPL10.INT.NS2.02685 RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle) OFE NS2 Control Fault Domain 2 Active 04/24/26 04/29/26 5.0 3.8
0%
51.2
RPL10.MCUP.LP2.2000 RPL10.MCUP.Loop 2 - Tie-in Electrical #8 Tie-Ins Electrical Active 04/24/26 05/26/26 11.2 23.8
0%
136.2
RPL10.EY.EF1.01640 RPL10.EY.EF1 - Install RPL-1 FSP Columns Cap Cure Fiber Support Platform - RPL-1 Not Started 04/26/26 05/02/26 8.8 8.8
0%
286.2
DCC.B10.3010 [NWB] Production Gear Delivered [Network Suite] DR/EBB Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3015 [NWB] Production Gear Delivered [Network Suite] MA Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
433.8
DCC.B10.3020 [NWB] Production Gear Delivered [Network Suite] XSW Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
433.8
DCC.B10.3025 [NWB] Production Gear Delivered [NWS1] Front End (SSW & FSW) Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3027 [NWB] Production Gear Delivered [NWS1] Back End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3035 [NWB] Production Gear Delivered [NWS2] Front End (SSW & FSW) Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3037 [NWB] Production Gear Delivered [NWS2] Back End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3045 [NWB] Production Gear Delivered [NWS3] Front End (SSW & FSW) Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3047 [NWB] Production Gear Delivered [NWS3] Back End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3055 [NWB] Production Gear Delivered [NWS4] Front End (SSW & FSW) Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3057 [NWB] Production Gear Delivered [NWS4] Back End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3165 [NWB] PortMaps Delivered : GS Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3170 [NWB] PortMaps Delivered : Elevations & Cabling Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3175 [NWB] PortMaps Delivered :Backbone Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3180 [NWB] PortMaps Delivered :Front End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3185 [NWB] PortMaps Delivered :Back End Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3300 [NWB] Cabling Start : OSP Pathways - Primary GS Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3410 [NWB] IBB1.1 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3420 [NWB] IBB1.2 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3430 [NWB] DCN 1 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3440 [NWB] CORP 1 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3450 [NWB] CORP OOB1 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3460 [NWB] Production Dark Fiber Path 1 - Circuit Delivered Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
DCC.B10.3707 [NWB] Cabling Start : General Services (GS) Connectivity Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
ICM.B10.1805 [NWB] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
JCL.C.1260 RPL10 - Cost Risk LOE-14 Cabling Cost LOEs Not Started 04/27/26 05/22/26 25.0 25.0
0%
208.8
RPL.10.D.X1410.XR Ready for Fiber Support Platform Construction - AI 1 (TCCO est Release 09-Feb-26) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
207.5
RPL.10.D.X3210.XR 500kva Temp Power Skids Energized (First 10 MW or Gen) Power (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
41.2
RPL.10.D.X4510.XR Storm Available for Roof Drain Tie-ins Pad Ready (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
182.5
RPL.CM.D.C5620.XR Naboo Road Logistics - Onsite Receive XREF Milestones Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
RPL.CM.D.N5620.XR LA 183 /Wade - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Not Started 04/27/26 04/27/26 0.0 0.0
0%
140.0
RPL.CM.D.N5630.XR LA 183 /Fortenberry - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Not Started 04/27/26 04/27/26 0.0 0.0
0%
496.2
RPL.CM.D.N5650.XR I-20 / LA 583 Right Turn Lane Logistics - Off-Site Receive XREF Milsetones Not Started 04/27/26 04/27/26 0.0 0.0
0%
150.0
RPL.CM.D.N5655.XR US 80 Traffic Signals at LA 583, LA 183 and LA 609 Logistics - Off-Site Receive XREF Milsetones Not Started 04/27/26 04/27/26 0.0 0.0
0%
150.0
RPL.CM.D.N5695.XR LA 854 - (Donahue Rd - LA183) Repaving / Overlay Logistics - Off-Site Receive XREF Milsetones Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
RPL.GF.D.N0110.XR 2 of 4 Fiber Pulls Complete (CAV1/4) MMH to GS.EF1/ Prod.EF1F Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
178.8
RPL.GF.D.N0120.XR 4 of 4 Fiber Pulls Complete CAV2/3 to GS.EF2/ Prod.EF2B Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL.GF.D.N0261.XR GS.IDF Hut 10-Way Install Complete (03, 04, 08, 09, 10) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
221.2
RPL.GF.D.N0262.XR GS.IDF Hut 10-Way Install Complete (01, 02, 06, 07) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
36.2
RPL.GF.D.N0263.XR GS.IDF Hut 10-Way Install Complete (11, 12, 13, 05) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
903.8
RPL.GF.D.N0520.XR Radio Tower(s) Available for DAS/PS - SSB, NWS1, NWS2, EF1, EF2 RPL10 ( WP3B - Successor) - Commissoning affect? Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
93.8
RPL.GF.D.N0530.XR Radio Tower(s) Available for DAS/PS - NWS3, NWS4 (WP3B-Successor) - Commissoning affect? Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
93.8
RPL.GF.D.N0540.XR GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to iBOS (META's Ware House logistics) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL.GF.D.N0550.XR GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to Admin Building Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL.GF.D.N0560.XR GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH1 (Guard House) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL.GF.D.N0570.XR GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH2 (Guard House) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL.GF.D.N0580.XR GS Fiber Pulls, Test & Term Complete - NWB RPL 10 to GH3 (Guard House) Connectivity (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
211.2
RPL10.CFCI.5690 RPL10 - Fabricate / Deliver - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 04/27/26 08/04/26 87.5 87.5
0%
126.2
RPL10.EY.EF1.01310 RPL10.EY.EF1 - Install RPL-1 FSP Roofing Z Purlin (Logistic #7 Install) Fiber Support Platform - RPL-1 Not Started 04/27/26 05/08/26 12.5 12.5
0%
248.8
RPL10.EY.EF1.01560 RPL10.EY.EF1 - Install CU (12) OFE Not Started 04/27/26 04/28/26 2.5 2.5
0%
126.2
RPL10.EY.EF2.01770 RPL10.EY.EF2 - Install Remaining CU (12) OFE Not Started 04/27/26 04/28/26 2.5 2.5
0%
191.2
RPL10.EY.ENDC.01120 RPL10.EY.End - Install Perm Paving Hardscape and Landscape Not Started 04/27/26 05/01/26 6.2 6.2
0%
446.2
RPL10.EY.ENDC.01130 RPL10.EY.End - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 04/27/26 05/22/26 25.0 25.0
0%
177.5
RPL10.EY.ENDC.01160 RPL10.EY.End - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 04/27/26 07/07/26 62.5 62.5
0%
446.2
RPL10.EY.NS2.01250 RPL10.EY.NS2 - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 04/27/26 05/08/26 12.5 12.5
0%
27.5
RPL10.EY.NS2.01260 RPL10.EY.NS2 - Tie-ins - WBS Summary Tie-ins Not Started 04/27/26 06/08/26 37.5 37.5
0%
62.5
RPL10.EY.NS3.01140 RPL10.EY.NS3 - Install Tent Electrical Panels Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
80.0
RPL10.EY.NS3.01150 RPL10.EY.NS3 - Install Tent Heating and Cooling Equipment Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
86.2
RPL10.EY.NS3.01160 RPL10.EY.NS3 - Install Tent Overhead Doors Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
86.2
RPL10.EY.NS3.01190 RPL10.EY.NS3 - Install Tent Mechanical Tie-ins Tent and Temp Conditions Not Started 04/27/26 05/04/26 7.5 7.5
0%
86.2
RPL10.INT.EF1.01390 RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 West OFE Not Started 04/27/26 05/22/26 25.0 25.0
0%
30.0
RPL10.INT.EF1.01400 RPL10.Interior.EF1 - Tie-ins - EF1 East - WBS Summary East EF-1 Not Started 04/27/26 06/23/26 51.2 51.2
0%
180.0
RPL10.INT.EF1.01435 RPL10.Interior.EF1 - EF1 East - Install Wall Mounted Ladder Racks on Full Height EF Walls East EF-1 Not Started 04/27/26 05/01/26 6.2 6.2
0%
218.8
RPL10.INT.ENDC.01110 RPL10.Interior.End-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 04/27/26 05/05/26 8.8 8.8
0%
183.8
RPL10.INT.ENDC.01130 RPL10.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary Fit out Not Started 04/27/26 04/27/26 0.0 0.0
0%
0.0
RPL10.INT.NS1.01230 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
40.0
RPL10.INT.NS1.02500 RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (Mech Side Aisle) OFE NS1 Control Fault Domain 5 Not Started 04/27/26 05/13/26 16.2 16.2
0%
2.5
RPL10.INT.NS2.01094 RPL10.Interior.NS2 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-Ins NS2 - LV Skids and TopHat Not Started 04/27/26 05/15/26 18.8 18.8
0%
33.8
RPL10.INT.NS2.01140 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
40.0
RPL10.INT.NS2.01150 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
27.5
RPL10.INT.NS2.01400 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/27/26 04/30/26 5.0 5.0
0%
53.8
RPL10.INT.NS2.01430 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 4 SQ3.2 (including IDF) - WBS Summary Tie-Ins NS2 Control Fault Domain 4 Not Started 04/27/26 07/28/26 81.2 81.2
0%
33.8
RPL10.INT.NS2.02180 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
27.5
RPL10.INT.NS2.02805 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
27.5
RPL10.INT.SSB.01720 RPL10.Interior.SSB - BoW - Install Refrigerant Piping Lowside OH (ERAD Room) Balance of Walls and OverHead Not Started 04/27/26 05/01/26 6.2 6.2
0%
181.2
RPL10.INT.SSB.01840 RPL10.Interior.SSB - BoW - Install Split Systems/Humidifiers Balance of Walls and OverHead Not Started 04/27/26 05/01/26 6.2 6.2
0%
213.8
RPL10.INT.SSBC.02860 RPL10.Interior.SSB-Corridor - BoW - Install Doors (Verify with Trades before Installation) Balance of Walls & OverHead Not Started 04/27/26 04/29/26 3.8 3.8
0%
136.2