Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
40
Completed
60
In Progress
45
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.ENDC.1300 RPL10.Interior.End-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Active 04/15/26 04/27/26 10.0 1.2
0%
191.2
RPL10.INT.NS2.01350 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 4 Active 04/15/26 06/24/26 62.5 20.0
0%
-11.2
RPL10.INT.NS2.02565 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle) - Row 10 OFE NS2 Control Fault Domain 4 Complete 04/15/26 04/15/26 1.2 0.0
100%
0.0
RPL10.INT.NS2.03285 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (LV Side Aisle) - Remaining (11-13) OFE NS2 Control Fault Domain 4 Complete 04/15/26 04/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.01130 RPL10.Interior.SSB - BoW - Paint (1st Coat) Balance of Walls and OverHead Complete 04/15/26 04/17/26 3.8 0.0
100%
0.0
RPL10.SSBC.BB.3195 RPL10.Int.Build Back.SSB-Corr - LO #2,3 - Hang Drywall Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Complete 04/15/26 04/20/26 25.0 0.0
100%
0.0
RPL10.INT.ENDC.06820 RPL10.Interior.End-Corridor - BoW - Install Remaining Unistruts & Hangers Balance of Walls & Overhead Complete 04/16/26 04/22/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01112 RPL10.Interior.NS2 - MES Skids - Final Piping Tie-Ins & Inspections NS2 - MES Skids Active 04/16/26 05/19/26 30.0 21.2
0%
47.5
RPL10.INT.NS2.02465 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (HAC) OFE NS2 Control Fault Domain 6 Active 04/16/26 05/11/26 25.0 13.8
0%
-18.8
RPL10.INT.SSB.01290 RPL10.Interior.SSB - BoW - Frame Hard Lid Balance of Walls and OverHead Complete 04/16/26 04/22/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1940 RPL10.MCUP.Loop 1 - Tie-in BMS #7 Tie-Ins BMS Active 04/16/26 05/20/26 10.0 22.5
0%
12.5
RPL.CM.D.N5665.XR Smalling Widening (LA 183 to Jaggers) Logistics - Off-Site Receive XREF Milsetones Complete 04/17/26 04/17/26 0.0 0.0
100%
0.0
RPL.CM.D.N5670.XR Smalling Repave (LA 183 to Jaggers) Logistics - Off-Site Receive XREF Milsetones Complete 04/17/26 04/17/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01150 RPL10.EY.EF1 - Install RPL-2 FSP Columns F/R/P Fiber Support Platform - RPL-2 Complete 04/17/26 04/22/26 7.5 0.0
100%
0.0
RPL10.EY.ENDC.01270 RPL10.Interior.End-Corridor - Install Temp Conditioning Return Duct (Inside) Priority Walls & OverHead Complete 04/17/26 04/24/26 11.2 0.0
100%
0.0
RPL10.INT.CTRC.01210 RPL10.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall Balance of Walls & OverHead Active 04/17/26 04/27/26 6.2 1.2
0%
60.0
RPL10.INT.CTRC.01930 RPL10.Interior.Center-Corridor - BoW - QC BoW - Backing/In-Wall Balance of Walls & OverHead Complete 04/17/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.07060 RPL10.Interior.SSB - Kitchen - Hang Drywall, Tape, Float, Paint (Remaining) Kitchen and Office Spaces Active 04/17/26 04/28/26 6.2 2.5
100%
188.8
RPL10.INT.SSBC.02280 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Carrier MDF (10.N2.09) Balance of Walls & OverHead Active 04/17/26 04/27/26 8.8 1.2
0%
96.2
RPL10.INT.SSBC.02600 RPL10.Interior.SSB-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) Balance of Walls & OverHead Complete 04/17/26 04/23/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2040 RPL10.MCUP.Loop 1 - Install Mcup Paving *Start 04/10 Hardscape and Landscape Active 04/17/26 05/22/26 18.8 25.0
100%
471.2
RPL10.MCUP.LP2.1560 RPL10.MCUP.Loop 2 - Tie-in Electrical (LOE) Tie-Ins Electrical Active 04/17/26 05/26/26 26.2 26.2
0%
136.2
RPL10.MCUP.LP2.1620 RPL10.MCUP.Loop 2 - Tie-in Electrical #2 Tie-Ins Electrical Active 04/17/26 05/21/26 11.2 23.8
0%
138.8
RPL10.MCUP.LP2.1740 RPL10.MCUP.Loop 2 - Tie-in Electrical #4 Tie-Ins Electrical Active 04/17/26 05/26/26 8.8 23.8
0%
136.2
RPL10.SSB.BB.1000 RPL10.Ext.Build Back.SSB - Exterior Leave Out #5 ( East SSB Area) WBS Summary Build Back Exterior Leave Out Wall #5 (East SSB) Active 04/17/26 06/10/26 47.5 40.0
0%
437.5
RPL10.SSB.BB.1140 RPL10.Ext.Build Back.SSB - LO #5 - F/R/P Stem wall Build Back Exterior Leave Out Wall #5 (East SSB) Complete 04/17/26 04/20/26 3.8 0.0
100%
0.0
JCL.C.1360 RPL10 - Cost Risk LOE-19 Connectivity Package 2 - GS Carrier SFZ Cost LOEs Active 04/20/26 01/15/27 233.8 227.5
0%
105.0
RPL.CM.D.C5500.XR Galaxy Road Logistics - Onsite Receive XREF Milestones Complete 04/20/26 04/20/26 0.0 0.0
100%
0.0
RPL.CM.D.N5605.XR LA 183 /Burn Road - Traffic Signal Logistics - Off-Site Receive XREF Milsetones Complete 04/20/26 04/20/26 0.0 0.0
100%
0.0
RPL10.EY.NS4.01140 RPL10.EY.NS4 - Install Tent Electrical Panels Tent and Temp Conditions Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.EY.NS4.01150 RPL10.EY.NS4 - Install Tent Heating and Cooling Equipment Tent and Temp Conditions Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.EY.NS4.01190 RPL10.EY.NS4 - Install Tent Mechanical Tie-ins Tent and Temp Conditions Complete 04/20/26 04/24/26 7.5 0.0
100%
0.0
RPL10.INT.CTRC.01230 RPL10.Interior.Center-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & OverHead Active 04/20/26 04/28/26 8.8 2.5
0%
145.0
RPL10.INT.EF1.01210 RPL10.Interior.EF1 - Tie-ins - WBS Summary Tie-Ins Active 04/20/26 07/24/26 85.0 78.8
0%
158.8
RPL10.INT.EF1.01750 RPL10.Interior.EF1 - Piping Tie-Ins to FW Loop (From MES Skids) Tie-Ins Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.EF2.01210 RPL10.Interior.EF2 - Tie-ins - WBS Summary Tie-Ins Active 04/20/26 08/19/26 107.5 88.8
0%
148.8
RPL10.INT.EF2.01810 RPL10.Interior.EF2 - Piping Tie-Ins to FW Loop (From MES Skids) Tie-Ins Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01225 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Complete 04/20/26 04/21/26 25.0 0.0
100%
0.0
RPL10.INT.NS1.01770 RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/20/26 04/20/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01800 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 2 SQ5.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 2 Active 04/20/26 08/06/26 96.2 75.0
0%
62.5
RPL10.INT.NS1.01910 RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/20/26 04/20/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01940 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 1 SQ6.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 1 Active 04/20/26 08/20/26 108.8 85.0
0%
56.2
RPL10.INT.NS1.02480 RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (HAC) OFE NS1 Control Fault Domain 5 Active 04/20/26 05/08/26 18.8 12.5
0%
-5.0
RPL10.INT.NS2.01065 RPL10.Interior.NS2 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Active 04/20/26 04/27/26 6.2 1.2
0%
33.8
RPL10.INT.NS2.01130 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (LV Side) LV Side Tie-ins Complete 04/20/26 04/20/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01160 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 6 SQ1.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 6 Active 04/20/26 06/22/26 56.2 50.0
0%
27.5
RPL10.INT.NS2.01220 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Active 04/20/26 05/11/26 6.2 13.8
0%
31.2
RPL10.INT.NS2.01260 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install Duct (LV Side) LV Side Tie-ins Complete 04/20/26 04/20/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.01300 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 5 SQ2.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 5 Active 04/20/26 07/14/26 68.8 57.5
0%
18.8
RPL10.INT.NS2.02020 RPL10.Interior.NS2 - OFE - Ancillary Skids - Set / Place / Anchor (04.01.26) OFE Complete 04/20/26 04/24/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.02360 RPL10.Interior.NS3 - Priority - Install Security OverHead Complete 04/20/26 04/21/26 2.5 0.0
100%
0.0
RPL10.INT.NS4.02360 RPL10.Interior.NS4 - Priority - Install Security OverHead Complete 04/20/26 04/21/26 2.5 0.0
100%
0.0
RPL10.INT.SSBC.02900 RPL10.Interior.SSB-Corridor - BoW - Final Paint Balance of Walls & OverHead Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1780 RPL10.MCUP.Loop 1 - Tie-in EPMS #5 Tie-Ins EPMS Active 04/20/26 05/20/26 7.5 22.5
0%
12.5
RPL10.MCUP.LP1.1840 RPL10.MCUP.Loop 1 - Install Sleeves MEPL Hardscape and Landscape Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1900 RPL10.MCUP.Loop 1 - Tie-in EPMS #7 Tie-Ins EPMS Active 04/20/26 05/20/26 8.8 22.5
0%
12.5
RPL10.MCUP.LP2.1520 RPL10.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Active 04/20/26 06/29/26 62.5 56.2
0%
452.5
RPL10.MCUP.LP2.1540 RPL10.MCUP.Loop 2 - Install Sleeves MEPL Hardscape and Landscape Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1800 RPL10.MCUP.Loop 2 - Tie-in Mechanical #4 WBS Summary Tie-in Mechanical #4 Active 04/20/26 05/22/26 11.2 25.0
0%
136.2
RPL10.MCUP.LP2.1920 RPL10.MCUP.Loop 2 - Tie-in Mechanical #6 WBS Summary Tie-in Mechanical #6 Active 04/20/26 05/22/26 11.2 25.0
0%
136.2
RPL10.MCUP.LP2.2020 RPL10.MCUP.Loop 2 - Tie-in Mechanical #8 WBS Summary Tie-in Mechanical #8 Active 04/20/26 05/22/26 13.8 25.0
0%
136.2
RPL10.MCUP.LP2.2640 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #4 Tie-in Mechanical #4 Active 04/20/26 05/15/26 3.8 18.8
0%
142.5
RPL10.MCUP.LP2.2680 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #6 Tie-in Mechanical #6 Active 04/20/26 05/15/26 3.8 18.8
0%
142.5
RPL10.MCUP.LP2.2720 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #8 Tie-in Mechanical #8 Active 04/20/26 05/18/26 3.8 0.0
0%
142.5
RPL10.SSB.BB.1160 RPL10.Ext.Build Back.SSB - LO #5 - Install Waterproofing and Flashing Build Back Exterior Leave Out Wall #5 (East SSB) Complete 04/20/26 04/20/26 2.5 0.0
100%
0.0
RPL10.WP2.GSIDF.2000 RPL10.Conn Ext IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5060 LF - WBS Summary Exterior Active 04/20/26 08/17/26 105.0 98.8
0%
410.0
RPL10.WP2.GSIDF.2800 RPL10.Conn IDF Huts - (GSMDF to GSIDF) mCup NX11 WBS Summary GSIDFNX11 Active 04/20/26 05/20/26 28.8 22.5
0%
486.2
RPL10.WP2.GSIDF.2820 RPL10.Conn GSIDFNX11 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2880 RPL10.Conn IDF Huts - (GSMDF to GSIDF) mCup NX12 WBS Summary GSIDFNX12 Active 04/20/26 06/01/26 37.5 31.2
0%
477.5
RPL10.WP2.GSIDF.2900 RPL10.Conn GSIDFNX12 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2960 RPL10.Conn GSIDFNX13 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 04/20/26 04/24/26 6.2 0.0
100%
0.0
RPL10.EY.NS4.01160 RPL10.EY.NS4 - Install Tent Overhead Doors Tent and Temp Conditions Active 04/21/26 04/27/26 6.2 1.2
100%
110.0
RPL10.INT.CTRC.01180 RPL10.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & OverHead Active 04/21/26 04/27/26 6.2 1.2
0%
136.2
RPL10.INT.ENDC.6300 RPL10.Interior.End-Corridor - Priority - P7 Wall Tape Finish Paint (Both Sides) Priority Wall (P7) - Grid Line 10-02 Active 04/21/26 04/29/26 10.0 3.8
0%
195.0
RPL10.INT.NS1.01145 RPL10.Interior.NS1 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Active 04/21/26 04/27/26 6.2 1.2
0%
37.5
RPL10.INT.NS1.02070 RPL10.Interior.NS1 - OFE - Ancillary Skids - Set / Place / Anchor (04.01.26) OFE Complete 04/21/26 04/24/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.01490 RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 3 Active 04/21/26 07/16/26 76.2 20.0
0%
-13.8
RPL10.INT.NS2.02625 RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (LV Side Aisle) OFE NS2 Control Fault Domain 3 Complete 04/21/26 04/23/26 5.0 0.0
100%
0.0
RPL10.INT.NS4.01070 RPL10.Interior.NS4 - OFE - MES Skids - Set / Place / Anchor OFE Active 04/21/26 05/18/26 25.0 20.0
0%
135.0
RPL10.INT.SSBC.02260 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Carrier MDF (10.N1.09) Balance of Walls & OverHead Active 04/21/26 04/29/26 8.8 3.8
0%
218.8
RPL10.MCUP.LP2.1680 RPL10.MCUP.Loop 2 - Tie-in EPMS (LOE) Tie-Ins EPMS Active 04/21/26 05/27/26 32.5 27.5
0%
136.2
RPL10.MCUP.LP2.1700 RPL10.MCUP.Loop 2 - Tie-in EPMS #2 Tie-Ins EPMS Active 04/21/26 05/22/26 8.8 8.8
0%
138.8
RPL10.MCUP.LP2.1780 RPL10.MCUP.Loop 2 - Tie-in EPMS #4 Tie-Ins EPMS Active 04/21/26 05/27/26 7.5 7.5
0%
136.2
RPL10.SSB.BB.1180 RPL10.Ext.Build Back.SSB - LO #5 - Install IMP Exterior Panel Build Back Exterior Leave Out Wall #5 (East SSB) Complete 04/21/26 04/21/26 2.5 0.0
100%
0.0
RPL10.EY.EF2.01160 RPL10.EY.EF2 - Install RPL-3 FSP Columns F/R/P Fiber Support Platform - RPL-3 Active 04/22/26 04/29/26 6.2 3.8
0%
195.0
RPL10.EY.ENDC.01250 RPL10.EY.End - Install Temp Conditioning Units OFE Complete 04/22/26 04/22/26 1.2 0.0
100%
0.0
RPL10.EY.NS2.01240 RPL10.EY.NS2 - Install GS.IDF Hut (1x GS.IDF) NX06 (04.22.26) OFE Active 04/22/26 04/28/26 6.2 2.5
0%
37.5
RPL10.EY.NS2.01270 RPL10.EY.NS2 - Install GS.IDF Hut (1x GS.IDF) NX07 (04.22.26) OFE Active 04/22/26 04/28/26 6.2 2.5
0%
37.5
RPL10.EY.NS4.01180 RPL10.EY.NS4 - Install Tent Electrical Tie-ins Tent and Temp Conditions Complete 04/22/26 04/24/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.01630 RPL10.Interior.Center-Corridor - BoW - Install Refrigerant Piping Lowside OH on Supplemental Steel Balance of Walls & OverHead Active 04/22/26 04/28/26 6.2 2.5
0%
141.2
RPL10.INT.CTRC.07720 RPL10.Interior.Center-Corridor - Priority - Install Exterior Wall Drywall, Tape, Float, Paint (Remaining) Priority Walls & OverHead Active 04/22/26 04/29/26 3.8 3.8
0%
125.0
RPL10.INT.ENDC.01010 RPL10.Interior.End-Corridor - Priority - Install Duct (Highside OH space) Priority Walls & OverHead Active 04/22/26 05/05/26 12.5 8.8
0%
111.2
RPL10.INT.ENDC.1400 RPL10.Interior.End-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Active 04/22/26 04/28/26 6.2 2.5
0%
190.0
RPL10.INT.NS1.01184 RPL10.Interior.NS1 - Electrical Panels/Ancillary Skid (ATS,SB House,MCB,MLO, Transformer) - Tie-ins NS1 - LV Skids and TopHat Active 04/22/26 05/12/26 18.8 15.0
0%
37.5
RPL10.INT.NS1.01280 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Set TWMS, UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Active 04/22/26 05/13/26 25.0 16.2
0%
36.2
RPL10.INT.NS1.01330 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Active 04/22/26 04/28/26 6.2 2.5
0%
43.8
RPL10.INT.NS1.01460 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Active 04/22/26 05/08/26 5.0 12.5
0%
47.5
RPL10.INT.NS2.02485 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (Mech Side Aisle) OFE NS2 Control Fault Domain 6 Active 04/22/26 05/11/26 22.5 13.8
0%
-5.0
RPL10.INT.SSB.02520 RPL10.Interior.SSB - BoW - ACT - Set Wall Angle Balance of Walls and OverHead Active 04/22/26 04/27/26 8.8 1.2
0%
71.2
RPL10.MCUP.LP2.1660 RPL10.MCUP.Loop 2 - Tie-in BMS (LOE) Tie-Ins BMS Active 04/22/26 05/28/26 31.2 28.8
0%
136.2