Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
61
Completed
39
In Progress
64
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.EY.NS1.01260 RPL10.EY.NS1 - Tie-ins - WBS Summary Tie-ins Active 04/06/26 05/26/26 45.0 26.2
0%
65.0
RPL10.INT.CTRC.01120 RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Lowside OH and In-wall Balance of Walls & OverHead Active 04/06/26 04/27/26 5.0 1.2
0%
125.0
RPL10.INT.CTRC.01240 RPL10.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & OverHead Active 04/06/26 04/27/26 8.8 1.2
0%
125.0
RPL10.INT.CTRC.02480 RPL10.Interior.Center-Corridor - Priority - Hang Drywall (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06960 RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (West Side) Priority Wall (P6) - Grid Line 10-16 Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.EF2.01100 RPL10.Interior.EF2 - Priority OH - Electrical OverHead Complete 04/06/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6240 RPL10.Interior.End-Corridor - Priority - QC Exterior Wall - Backing/In-Wall Priority Walls & OverHead Complete 04/06/26 04/07/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01350 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (LV SIde) LV Side Tie-ins Complete 04/06/26 04/06/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01380 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 5 SQ2.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 5 Active 04/06/26 06/23/26 70.0 51.2
0%
42.5
RPL10.INT.NS1.02440 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (Mech Side Aisle) OFE NS1 Control Fault Domain 6 Complete 04/06/26 04/20/26 22.5 0.0
100%
0.0
RPL10.INT.NS2.01093 RPL10.Interior.NS2 - LV Skids and TopHat - Top Hat Busway NS2 - LV Skids and TopHat Complete 04/06/26 04/24/26 18.8 0.0
100%
0.0
RPL10.INT.SSB.01320 RPL10.Interior.SSB - BoW - Hang Drywall (Remaining) Balance of Walls and OverHead Complete 04/06/26 04/16/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.07040 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 04/06/26 04/14/26 8.0 0.0
100%
0.0
RPL10.INT.SSBC.02380 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Tie-Ins Balance of Walls & OverHead Complete 04/06/26 04/20/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.02940 RPL10.Interior.SSB-Corridor - BoW - F/R/P Pads / Curbs Balance of Walls & OverHead Complete 04/06/26 04/07/26 3.8 0.0
100%
0.0
RPL10.SKN.SSB.01050 RPL10.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Complete 04/06/26 04/17/26 5.0 0.0
100%
0.0
RPL10.WP2.01080 RPL10.Conn Int IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5275 LF - WBS Summary Interior Active 04/06/26 12/18/26 223.8 205.0
0%
303.8
RPL10.WP2.EF1.1000 RPL10.Conn GS.EF1 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.WP2.EF2.1000 RPL10.Conn GS.EF2 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.CFCI.5140 RPL10- Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Active 04/07/26 05/22/26 25.0 25.0
0%
125.0
RPL10.CFCI.7140 RPL10- Fabricate / Deliver - Cabinets (CFCI) Div. 09 - Epoxy Flooring Active 04/07/26 07/06/26 25.0 61.2
0%
121.2
RPL10.EY.EF2.01090 RPL10.EY.EF2 - Install RPL-3 FSP Deep Foundation ((TCCO est Release 27-Jul-26)) Fiber Support Platform - RPL-3 Complete 04/07/26 04/16/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6140 RPL10.Interior.End-Corridor - Priority - Install Drywall at IMP Exterior Wall Priority Walls & OverHead Complete 04/07/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01880 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 1 Active 04/07/26 08/05/26 106.2 20.0
0%
-5.0
RPL10.INT.NS1.02700 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle) OFE NS1 Control Fault Domain 1 Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
RPL10.INT.NS2.01120 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 6 Active 04/07/26 05/11/26 36.2 13.8
0%
-5.0
RPL10.INT.NS2.02445 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle) OFE NS2 Control Fault Domain 6 Complete 04/07/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.02000 RPL10.Interior.NS3 - Priority - Install Draft Curtains (#4 - 6 Days Each * 2 crew) OverHead Complete 04/07/26 04/17/26 15.0 0.0
100%
0.0
RPL10.INT.NS4.02000 RPL10.Interior.NS4 - Priority - Install Draft Curtains (#4 - 6 Days Each* 2 crew) OverHead Complete 04/07/26 04/17/26 15.0 0.0
100%
0.0
RPL10.EY.EF1.01090 RPL10.EY.EF1 - Install RPL-1 FSP Columns F/R/P Fiber Support Platform - RPL-1 Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.EY.EF2.01170 RPL10.EY.EF2 - Install RPL-5 FSP Deep Foundation (TCCO est Release 21-Oct-26) Fiber Support Platform - RPL-5 Complete 04/08/26 04/17/26 6.2 0.0
100%
0.0
RPL10.EY.ENDC.01110 RPL10.EY.End - Install AHU (4) - CFCI OFE Complete 04/08/26 04/10/26 8.8 0.0
100%
0.0
RPL10.EY.NS1.01240 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX01 (04.08.26) OFE Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01270 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX02 (04.08.26) OFE Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01120 RPL10.Interior.SSB - BoW - Tape Finish Paint (Finish Out) Balance of Walls and OverHead Complete 04/08/26 04/17/26 8.8 0.0
100%
0.0
RPL10.CFCI.5110 RPL10 - Submittal Rvw/App'l - Carpet (CFCI) Div. 09 - Carpet Active 04/09/26 04/27/26 25.0 1.2
0%
191.2
RPL10.CFCI.7120 RPL10 - Fabricate / Deliver - Coping Fixed Louvers Active 04/09/26 06/01/26 6.2 31.2
100%
307.5
RPL10.INT.EF2.01160 RPL10.Interior.EF2 - CFCI - WBS Summary OFE Active 04/09/26 06/05/26 66.2 36.2
0%
117.5
RPL10.INT.EF2.01190 RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 East OFE Active 04/09/26 05/14/26 25.0 17.5
0%
18.8
RPL10.INT.ENDC.01060 RPL10.Interior.End-Corridor - Balance of Walls & Overhead (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary Balance of Walls & Overhead Active 04/09/26 08/24/26 120.0 105.0
0%
225.0
RPL10.INT.ENDC.6420 RPL10.Interior.End-Corridor - BoW - BoW Frame Priority Soffit and Hang Drywall Balance of Walls & Overhead Complete 04/09/26 04/14/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1860 RPL10.MCUP.Loop 1 - Tie-in Electrical #5 Tie-Ins Electrical Active 04/09/26 05/20/26 8.8 22.5
100%
12.5
RPL10.MCUP.LP1.1960 RPL10.MCUP.Loop 1 - Tie-in Electrical #7 Tie-Ins Electrical Active 04/09/26 05/20/26 11.2 22.5
0%
12.5
RPL.10.D.X3720.XG RMUs/MV Skids Set (Loop 1) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL.10.D.X3725.XG RMUs/MV Skids Set (Loop 2) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.02500 RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 04/10/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07020 RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (West Side) Priority Wall (P6) - Grid Line 10-16 Complete 04/10/26 04/20/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07060 RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside OH and On-Wall Balance of Walls & OverHead Active 04/10/26 04/27/26 6.2 1.2
0%
117.5
RPL10.INT.ENDC.01050 RPL10.Interior.End-Corridor - BoW - Frame Balance of Wall Balance of Walls & Overhead Complete 04/10/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.ENDC.6360 RPL10.Interior.End-Corridor - Priority - Tape Finish Paint Exterior Wall Priority Walls & OverHead Complete 04/10/26 04/15/26 10.0 0.0
100%
0.0
RPL10.MCUP.LP1.1720 RPL10.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Active 04/10/26 05/20/26 7.5 22.5
0%
12.5
RPL10.MCUP.LP1.1740 RPL10.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Active 04/10/26 05/20/26 8.8 22.5
0%
12.5
RPL10.MCUP.LP2.1440 RPL10.MCUP.Loop 2 - Set Electrical Skids #2 OFE Complete 04/10/26 04/13/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.1460 RPL10.MCUP.Loop 2 - Set Electrical Skids #4 OFE Complete 04/10/26 04/13/26 2.5 0.0
100%
0.0
RPL10.STR.NS43.01160 RPL10.Structure.NS43 - SOG Sealant Cure F/R/P Complete 04/10/26 04/10/26 1.2 0.0
100%
0.0
RPL10.EY.EF1.01740 RPL10.EY.EF1 - Install RPL-2 FSP Steel Delivery & Assembly (Logistic #7 Install) Fiber Support Platform - RPL-2 Active 04/13/26 04/27/26 12.5 1.2
0%
261.2
RPL10.EY.ENDC.01140 RPL10.EY.End - Install Mechanical Main (include penetration detail) Tie-ins Active 04/13/26 04/27/26 18.8 1.2
0%
286.2
RPL10.EY.ENDC.01150 RPL10.EY.End - Tie-ins - WBS Summary Tie-ins Active 04/13/26 06/22/26 56.2 50.0
0%
256.2
RPL10.EY.NS2.01210 RPL10.EY.NS2 - HAC Prefab prior to install Tent and Temp Conditions Complete 04/13/26 04/17/26 7.5 0.0
100%
0.0
RPL10.EY.SSB.01160 RPL10.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Active 04/13/26 05/15/26 25.0 18.8
0%
17.5
RPL10.INT.CTRC.07760 RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside On Hilti Steel (North) Priority Walls & OverHead Complete 04/13/26 04/20/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6440 RPL10.Interior.End-Corridor - BoW - BoW Soffit Tape, Float and Paint Priority, Fire Safing Both Sides Balance of Walls & Overhead Complete 04/13/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01240 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install TW Remaining Tie-ins post Mech Side Aisle install Active 04/13/26 05/06/26 25.0 10.0
0%
36.2
RPL10.INT.NS1.01310 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Complete 04/13/26 04/21/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01490 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/13/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01520 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 4 SQ3.1 (including IDF) - WBS Summary Tie-Ins NS1 Control Fault Domain 4 Active 04/13/26 07/06/26 73.8 51.2
0%
42.5
RPL10.INT.NS1.01630 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/13/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01660 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 3 SQ4.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 3 Active 04/13/26 07/27/26 92.5 67.5
0%
48.8
RPL10.INT.NS1.02120 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install FW Remaining Tie-ins post Mech Side Aisle install Active 04/13/26 05/06/26 25.0 10.0
0%
36.2
RPL10.INT.NS2.01230 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 5 Active 04/13/26 06/03/26 46.2 20.0
0%
-8.8
RPL10.INT.NS2.02505 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle) Upto Row 9 OFE NS2 Control Fault Domain 5 Complete 04/13/26 04/15/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.02340 RPL10.Interior.NS3 - Priority - Install Electrical (Exterior Drywall mounted Branch) OverHead Complete 04/13/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.02340 RPL10.Interior.NS4 - Priority - Install Electrical (Exterior Drywall mounted Branch) OverHead Complete 04/13/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.03320 RPL10.Interior.SSB - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) Balance of Walls and OverHead Complete 04/13/26 04/21/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02340 RPL10.Interior.SSB-Corridor - BoW - Shell Space Walls (micro plan for finishes) Balance of Walls & OverHead Complete 04/13/26 04/15/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1800 RPL10.MCUP.Loop 1 - Tie-in BMS #5 Tie-Ins BMS Active 04/13/26 05/20/26 8.8 22.5
0%
12.5
RPL10.MCUP.LP1.1980 RPL10.MCUP.Loop 1 - Tie-in Mechanical #7 WBS Summary Tie-in Mechanical #7 Complete 04/13/26 04/17/26 3.8 0.0
100%
0.0
RPL10.MCUP.LP1.2700 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #7 Tie-in Mechanical #7 Complete 04/13/26 04/15/26 3.8 0.0
100%
0.0
RPL10.MCUP.LP1.2720 RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #7 Tie-in Mechanical #7 Complete 04/13/26 04/17/26 3.8 0.0
100%
0.0
RPL10.MCUP.LP2.1580 RPL10.MCUP.Loop 2 - Tie-in Mechanical (LOE) Tie-Ins Mechanical Active 04/13/26 06/04/26 30.0 35.0
0%
137.5
RPL10.MCUP.LP2.1600 RPL10.MCUP.Loop 2 - Tie-in Mechanical #2 WBS Summary Tie-in Mechanical #2 Active 04/13/26 05/08/26 20.0 12.5
0%
148.8
RPL10.MCUP.LP2.2560 RPL10.MCUP.Loop 2 - Set Remaining Facility water piping rack with All Racks Welding OFE Active 04/13/26 05/15/26 12.5 18.8
0%
142.5
RPL10.MCUP.LP2.2600 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #2 Tie-in Mechanical #2 Active 04/13/26 05/08/26 3.8 12.5
0%
148.8
RPL10.SSBC.BB.1340 RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Arch Finishes - Frame, Hang Drywall, Paint, Final Finishes (LOE) Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Active 04/13/26 05/14/26 25.0 17.5
0%
178.8
RPL10.SSBC.BB.1440 RPL10.Int.Build Back.SSB-Corr - Interior Leave Out (SSB Corridor) #2, #3, #4 WBS Summary Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Active 04/13/26 06/08/26 50.0 37.5
0%
178.8
RPL10.SSBC.BB.3155 RPL10.Int.Build Back.SSB-Corr - LO #2,3 - Frame Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Complete 04/13/26 04/14/26 25.0 0.0
100%
0.0
RPL10.SSBC.BB.3175 RPL10.Int.Build Back.SSB-Corr - LO #2,3 - MEPF - In Wall Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Complete 04/13/26 04/14/26 25.0 0.0
100%
0.0
RPL10.SSBC.BB.3215 RPL10.Int.Build Back.SSB-Corr - LO #2,3 - Tape, Float and Paint Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) Active 04/13/26 05/01/26 25.0 6.2
0%
190.0
RPL10.EY.EF1.01620 RPL10.EY.EF1 - Install RPL-1 FSP Columns Cap Erect Shoring & Decking & F/R/P Fiber Support Platform - RPL-1 Complete 04/14/26 04/24/26 7.5 0.0
100%
0.0
RPL10.EY.SSB.01175 RPL10.EY.SSB - Install Mechanical Tie-ins Tie-ins Active 04/14/26 04/27/26 12.5 1.2
0%
35.0
RPL10.INT.CTRC.01380 RPL10.Interior.Center-Corridor - BoW - Install Cable Tray (Early) Balance of Walls & OverHead Complete 04/14/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01080 RPL10.Interior.End-Corridor - BoW - Install Electrical Lowside OH and In-wall Balance of Walls & Overhead Active 04/14/26 04/27/26 8.8 1.2
0%
183.8
RPL10.INT.ENDC.1520 RPL10.Interior.End-Corridor - BoW - Install Backing and In-Wall BoW Balance of Walls & Overhead Complete 04/14/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6400 RPL10.Interior.End-Corridor - Priority - QC - P7 Wall - Backing/In-Wall Priority Wall (P7) - Grid Line 10-02 Complete 04/14/26 04/15/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01203 RPL10.Interior.NS1 - MES Skids - CDU Tie-Ins NS1 - MES Skids Active 04/14/26 05/22/26 30.0 18.8
0%
140.0
RPL10.MCUP.LP2.1480 RPL10.MCUP.Loop 2 - Set Electrical Skids #6 OFE Complete 04/14/26 04/15/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.1500 RPL10.MCUP.Loop 2 - Set Electrical Skids #8 OFE Complete 04/14/26 04/15/26 2.5 0.0
100%
0.0
RPL.10.D.X3760.XG RMUs/MV Skids Set - mCUP South Give Milestones (XREFs) Complete 04/15/26 04/15/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.01330 RPL10.Interior.Center-Corridor - BoW - Hang Drywall BoW Balance of Walls & OverHead Complete 04/15/26 04/24/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.01910 RPL10.Interior.Center-Corridor - BoW - Install Backing Balance of Walls & OverHead Complete 04/15/26 04/21/26 6.2 0.0
100%
0.0