Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
61
Completed
39
In Progress
64
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.EY.NS1.01260 |
RPL10.EY.NS1 - Tie-ins - WBS Summary | Tie-ins | Active | 04/06/26 | 05/26/26 | 45.0 | 26.2 |
|
65.0 |
RPL10.INT.CTRC.01120 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Lowside OH and In-wall | Balance of Walls & OverHead | Active | 04/06/26 | 04/27/26 | 5.0 | 1.2 |
|
125.0 |
RPL10.INT.CTRC.01240 |
RPL10.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & OverHead | Active | 04/06/26 | 04/27/26 | 8.8 | 1.2 |
|
125.0 |
RPL10.INT.CTRC.02480 |
RPL10.Interior.Center-Corridor - Priority - Hang Drywall (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 04/06/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06960 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (West Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 04/06/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01100 |
RPL10.Interior.EF2 - Priority OH - Electrical | OverHead | Complete | 04/06/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6240 |
RPL10.Interior.End-Corridor - Priority - QC Exterior Wall - Backing/In-Wall | Priority Walls & OverHead | Complete | 04/06/26 | 04/07/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01350 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (LV SIde) | LV Side Tie-ins | Complete | 04/06/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01380 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 5 SQ2.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 5 | Active | 04/06/26 | 06/23/26 | 70.0 | 51.2 |
|
42.5 |
RPL10.INT.NS1.02440 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (Mech Side Aisle) | OFE NS1 Control Fault Domain 6 | Complete | 04/06/26 | 04/20/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01093 |
RPL10.Interior.NS2 - LV Skids and TopHat - Top Hat Busway | NS2 - LV Skids and TopHat | Complete | 04/06/26 | 04/24/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01320 |
RPL10.Interior.SSB - BoW - Hang Drywall (Remaining) | Balance of Walls and OverHead | Complete | 04/06/26 | 04/16/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.07040 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 04/06/26 | 04/14/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02380 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical Tie-Ins | Balance of Walls & OverHead | Complete | 04/06/26 | 04/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02940 |
RPL10.Interior.SSB-Corridor - BoW - F/R/P Pads / Curbs | Balance of Walls & OverHead | Complete | 04/06/26 | 04/07/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01050 |
RPL10.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Complete | 04/06/26 | 04/17/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.WP2.01080 |
RPL10.Conn Int IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5275 LF - WBS Summary | Interior | Active | 04/06/26 | 12/18/26 | 223.8 | 205.0 |
|
303.8 |
RPL10.WP2.EF1.1000 |
RPL10.Conn GS.EF1 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Complete | 04/06/26 | 04/08/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.WP2.EF2.1000 |
RPL10.Conn GS.EF2 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Complete | 04/06/26 | 04/08/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.CFCI.5140 |
RPL10- Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) | (CFCI) Div. 09 - Epoxy Flooring | Active | 04/07/26 | 05/22/26 | 25.0 | 25.0 |
|
125.0 |
RPL10.CFCI.7140 |
RPL10- Fabricate / Deliver - Cabinets | (CFCI) Div. 09 - Epoxy Flooring | Active | 04/07/26 | 07/06/26 | 25.0 | 61.2 |
|
121.2 |
RPL10.EY.EF2.01090 |
RPL10.EY.EF2 - Install RPL-3 FSP Deep Foundation ((TCCO est Release 27-Jul-26)) | Fiber Support Platform - RPL-3 | Complete | 04/07/26 | 04/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6140 |
RPL10.Interior.End-Corridor - Priority - Install Drywall at IMP Exterior Wall | Priority Walls & OverHead | Complete | 04/07/26 | 04/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01880 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 1 | Active | 04/07/26 | 08/05/26 | 106.2 | 20.0 |
|
-5.0 |
RPL10.INT.NS1.02700 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 1 | Complete | 04/07/26 | 04/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01120 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS2 Control Fault Domain 6 | Active | 04/07/26 | 05/11/26 | 36.2 | 13.8 |
|
-5.0 |
RPL10.INT.NS2.02445 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle) | OFE NS2 Control Fault Domain 6 | Complete | 04/07/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02000 |
RPL10.Interior.NS3 - Priority - Install Draft Curtains (#4 - 6 Days Each * 2 crew) | OverHead | Complete | 04/07/26 | 04/17/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02000 |
RPL10.Interior.NS4 - Priority - Install Draft Curtains (#4 - 6 Days Each* 2 crew) | OverHead | Complete | 04/07/26 | 04/17/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01090 |
RPL10.EY.EF1 - Install RPL-1 FSP Columns F/R/P | Fiber Support Platform - RPL-1 | Complete | 04/08/26 | 04/15/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01170 |
RPL10.EY.EF2 - Install RPL-5 FSP Deep Foundation (TCCO est Release 21-Oct-26) | Fiber Support Platform - RPL-5 | Complete | 04/08/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01110 |
RPL10.EY.End - Install AHU (4) - CFCI | OFE | Complete | 04/08/26 | 04/10/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01240 |
RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX01 (04.08.26) | OFE | Complete | 04/08/26 | 04/15/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01270 |
RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX02 (04.08.26) | OFE | Complete | 04/08/26 | 04/15/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01120 |
RPL10.Interior.SSB - BoW - Tape Finish Paint (Finish Out) | Balance of Walls and OverHead | Complete | 04/08/26 | 04/17/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.CFCI.5110 |
RPL10 - Submittal Rvw/App'l - Carpet | (CFCI) Div. 09 - Carpet | Active | 04/09/26 | 04/27/26 | 25.0 | 1.2 |
|
191.2 |
RPL10.CFCI.7120 |
RPL10 - Fabricate / Deliver - Coping | Fixed Louvers | Active | 04/09/26 | 06/01/26 | 6.2 | 31.2 |
|
307.5 |
RPL10.INT.EF2.01160 |
RPL10.Interior.EF2 - CFCI - WBS Summary | OFE | Active | 04/09/26 | 06/05/26 | 66.2 | 36.2 |
|
117.5 |
RPL10.INT.EF2.01190 |
RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 East | OFE | Active | 04/09/26 | 05/14/26 | 25.0 | 17.5 |
|
18.8 |
RPL10.INT.ENDC.01060 |
RPL10.Interior.End-Corridor - Balance of Walls & Overhead (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Balance of Walls & Overhead | Active | 04/09/26 | 08/24/26 | 120.0 | 105.0 |
|
225.0 |
RPL10.INT.ENDC.6420 |
RPL10.Interior.End-Corridor - BoW - BoW Frame Priority Soffit and Hang Drywall | Balance of Walls & Overhead | Complete | 04/09/26 | 04/14/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1860 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #5 | Tie-Ins Electrical | Active | 04/09/26 | 05/20/26 | 8.8 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1960 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #7 | Tie-Ins Electrical | Active | 04/09/26 | 05/20/26 | 11.2 | 22.5 |
|
12.5 |
RPL.10.D.X3720.XG |
RMUs/MV Skids Set (Loop 1) - RPL10 NS2 | Give Milestones (XREFs) | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3725.XG |
RMUs/MV Skids Set (Loop 2) - RPL10 NS2 | Give Milestones (XREFs) | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02500 |
RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 04/10/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07020 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (West Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 04/10/26 | 04/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07060 |
RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside OH and On-Wall | Balance of Walls & OverHead | Active | 04/10/26 | 04/27/26 | 6.2 | 1.2 |
|
117.5 |
RPL10.INT.ENDC.01050 |
RPL10.Interior.End-Corridor - BoW - Frame Balance of Wall | Balance of Walls & Overhead | Complete | 04/10/26 | 04/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6360 |
RPL10.Interior.End-Corridor - Priority - Tape Finish Paint Exterior Wall | Priority Walls & OverHead | Complete | 04/10/26 | 04/15/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1720 |
RPL10.MCUP.Loop 1 - Tie-in EPMS #3 | Tie-Ins EPMS | Active | 04/10/26 | 05/20/26 | 7.5 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1740 |
RPL10.MCUP.Loop 1 - Tie-in BMS #3 | Tie-Ins BMS | Active | 04/10/26 | 05/20/26 | 8.8 | 22.5 |
|
12.5 |
RPL10.MCUP.LP2.1440 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #2 | OFE | Complete | 04/10/26 | 04/13/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1460 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #4 | OFE | Complete | 04/10/26 | 04/13/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01160 |
RPL10.Structure.NS43 - SOG Sealant Cure | F/R/P | Complete | 04/10/26 | 04/10/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01740 |
RPL10.EY.EF1 - Install RPL-2 FSP Steel Delivery & Assembly (Logistic #7 Install) | Fiber Support Platform - RPL-2 | Active | 04/13/26 | 04/27/26 | 12.5 | 1.2 |
|
261.2 |
RPL10.EY.ENDC.01140 |
RPL10.EY.End - Install Mechanical Main (include penetration detail) | Tie-ins | Active | 04/13/26 | 04/27/26 | 18.8 | 1.2 |
|
286.2 |
RPL10.EY.ENDC.01150 |
RPL10.EY.End - Tie-ins - WBS Summary | Tie-ins | Active | 04/13/26 | 06/22/26 | 56.2 | 50.0 |
|
256.2 |
RPL10.EY.NS2.01210 |
RPL10.EY.NS2 - HAC Prefab prior to install | Tent and Temp Conditions | Complete | 04/13/26 | 04/17/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01160 |
RPL10.EY.SSB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Active | 04/13/26 | 05/15/26 | 25.0 | 18.8 |
|
17.5 |
RPL10.INT.CTRC.07760 |
RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside On Hilti Steel (North) | Priority Walls & OverHead | Complete | 04/13/26 | 04/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6440 |
RPL10.Interior.End-Corridor - BoW - BoW Soffit Tape, Float and Paint Priority, Fire Safing Both Sides | Balance of Walls & Overhead | Complete | 04/13/26 | 04/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01240 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Active | 04/13/26 | 05/06/26 | 25.0 | 10.0 |
|
36.2 |
RPL10.INT.NS1.01310 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Complete | 04/13/26 | 04/21/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01490 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Duct (LV Side) | LV Side Tie-ins | Complete | 04/13/26 | 04/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01520 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 4 SQ3.1 (including IDF) - WBS Summary | Tie-Ins NS1 Control Fault Domain 4 | Active | 04/13/26 | 07/06/26 | 73.8 | 51.2 |
|
42.5 |
RPL10.INT.NS1.01630 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Duct (LV Side) | LV Side Tie-ins | Complete | 04/13/26 | 04/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01660 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 3 SQ4.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 3 | Active | 04/13/26 | 07/27/26 | 92.5 | 67.5 |
|
48.8 |
RPL10.INT.NS1.02120 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Active | 04/13/26 | 05/06/26 | 25.0 | 10.0 |
|
36.2 |
RPL10.INT.NS2.01230 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS2 Control Fault Domain 5 | Active | 04/13/26 | 06/03/26 | 46.2 | 20.0 |
|
-8.8 |
RPL10.INT.NS2.02505 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle) Upto Row 9 | OFE NS2 Control Fault Domain 5 | Complete | 04/13/26 | 04/15/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02340 |
RPL10.Interior.NS3 - Priority - Install Electrical (Exterior Drywall mounted Branch) | OverHead | Complete | 04/13/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02340 |
RPL10.Interior.NS4 - Priority - Install Electrical (Exterior Drywall mounted Branch) | OverHead | Complete | 04/13/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03320 |
RPL10.Interior.SSB - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) | Balance of Walls and OverHead | Complete | 04/13/26 | 04/21/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02340 |
RPL10.Interior.SSB-Corridor - BoW - Shell Space Walls (micro plan for finishes) | Balance of Walls & OverHead | Complete | 04/13/26 | 04/15/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1800 |
RPL10.MCUP.Loop 1 - Tie-in BMS #5 | Tie-Ins BMS | Active | 04/13/26 | 05/20/26 | 8.8 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1980 |
RPL10.MCUP.Loop 1 - Tie-in Mechanical #7 WBS Summary | Tie-in Mechanical #7 | Complete | 04/13/26 | 04/17/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2700 |
RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #7 | Tie-in Mechanical #7 | Complete | 04/13/26 | 04/15/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.2720 |
RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #7 | Tie-in Mechanical #7 | Complete | 04/13/26 | 04/17/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1580 |
RPL10.MCUP.Loop 2 - Tie-in Mechanical (LOE) | Tie-Ins Mechanical | Active | 04/13/26 | 06/04/26 | 30.0 | 35.0 |
|
137.5 |
RPL10.MCUP.LP2.1600 |
RPL10.MCUP.Loop 2 - Tie-in Mechanical #2 WBS Summary | Tie-in Mechanical #2 | Active | 04/13/26 | 05/08/26 | 20.0 | 12.5 |
|
148.8 |
RPL10.MCUP.LP2.2560 |
RPL10.MCUP.Loop 2 - Set Remaining Facility water piping rack with All Racks Welding | OFE | Active | 04/13/26 | 05/15/26 | 12.5 | 18.8 |
|
142.5 |
RPL10.MCUP.LP2.2600 |
RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #2 | Tie-in Mechanical #2 | Active | 04/13/26 | 05/08/26 | 3.8 | 12.5 |
|
148.8 |
RPL10.SSBC.BB.1340 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Arch Finishes - Frame, Hang Drywall, Paint, Final Finishes (LOE) | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Active | 04/13/26 | 05/14/26 | 25.0 | 17.5 |
|
178.8 |
RPL10.SSBC.BB.1440 |
RPL10.Int.Build Back.SSB-Corr - Interior Leave Out (SSB Corridor) #2, #3, #4 WBS Summary | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Active | 04/13/26 | 06/08/26 | 50.0 | 37.5 |
|
178.8 |
RPL10.SSBC.BB.3155 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3 - Frame | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Complete | 04/13/26 | 04/14/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SSBC.BB.3175 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3 - MEPF - In Wall | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Complete | 04/13/26 | 04/14/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SSBC.BB.3215 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3 - Tape, Float and Paint | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Active | 04/13/26 | 05/01/26 | 25.0 | 6.2 |
|
190.0 |
RPL10.EY.EF1.01620 |
RPL10.EY.EF1 - Install RPL-1 FSP Columns Cap Erect Shoring & Decking & F/R/P | Fiber Support Platform - RPL-1 | Complete | 04/14/26 | 04/24/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01175 |
RPL10.EY.SSB - Install Mechanical Tie-ins | Tie-ins | Active | 04/14/26 | 04/27/26 | 12.5 | 1.2 |
|
35.0 |
RPL10.INT.CTRC.01380 |
RPL10.Interior.Center-Corridor - BoW - Install Cable Tray (Early) | Balance of Walls & OverHead | Complete | 04/14/26 | 04/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01080 |
RPL10.Interior.End-Corridor - BoW - Install Electrical Lowside OH and In-wall | Balance of Walls & Overhead | Active | 04/14/26 | 04/27/26 | 8.8 | 1.2 |
|
183.8 |
RPL10.INT.ENDC.1520 |
RPL10.Interior.End-Corridor - BoW - Install Backing and In-Wall BoW | Balance of Walls & Overhead | Complete | 04/14/26 | 04/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6400 |
RPL10.Interior.End-Corridor - Priority - QC - P7 Wall - Backing/In-Wall | Priority Wall (P7) - Grid Line 10-02 | Complete | 04/14/26 | 04/15/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01203 |
RPL10.Interior.NS1 - MES Skids - CDU Tie-Ins | NS1 - MES Skids | Active | 04/14/26 | 05/22/26 | 30.0 | 18.8 |
|
140.0 |
RPL10.MCUP.LP2.1480 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #6 | OFE | Complete | 04/14/26 | 04/15/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1500 |
RPL10.MCUP.Loop 2 - Set Electrical Skids #8 | OFE | Complete | 04/14/26 | 04/15/26 | 2.5 | 0.0 |
|
0.0 |
RPL.10.D.X3760.XG |
RMUs/MV Skids Set - mCUP South | Give Milestones (XREFs) | Complete | 04/15/26 | 04/15/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01330 |
RPL10.Interior.Center-Corridor - BoW - Hang Drywall BoW | Balance of Walls & OverHead | Complete | 04/15/26 | 04/24/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01910 |
RPL10.Interior.Center-Corridor - BoW - Install Backing | Balance of Walls & OverHead | Complete | 04/15/26 | 04/21/26 | 6.2 | 0.0 |
|
0.0 |