Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
76
Completed
24
In Progress
79
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.EY.NS2.01220 |
RPL10.EY.NS2 - Install MV, RMUs & Electrical Panels (15) | OFE | Complete | 03/23/26 | 04/10/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01230 |
RPL10.EY.NS2 - OFE - MV - WBS Summary | OFE | Active | 03/23/26 | 04/28/26 | 32.5 | 2.5 |
|
37.5 |
RPL10.EY.NS4.01090 |
RPL10.EY.NS4 - Install Tent | Tent and Temp Conditions | Complete | 03/23/26 | 04/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS4.01170 |
RPL10.EY.NS4 - Install Tent Fit-out | Tent and Temp Conditions | Complete | 03/23/26 | 04/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07140 |
RPL10.Interior.Center-Corridor - Priority - Install Hilti Steel for Cable Tray | Priority Walls & OverHead | Complete | 03/23/26 | 04/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01610 |
RPL10.Interior.EF2 - Priority OH - Install Plumbing (*No Scope) | OverHead | Complete | 03/23/26 | 03/23/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01650 |
RPL10.Interior.EF1 - Priority OH - Install Plumbing (*No Scope) | OverHead | Complete | 03/23/26 | 03/23/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01210 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 6 | Complete | 03/23/26 | 04/20/26 | 32.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02400 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (LV Side Aisle) | OFE NS1 Control Fault Domain 6 | Complete | 03/23/26 | 03/25/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01090 |
RPL10.Interior.NS2 - LV Skids and TopHat Tie-ins (LOE) | NS2 - LV Skids and TopHat | Complete | 03/23/26 | 04/24/26 | 37.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01091 |
RPL10.Interior.NS2 - LV Skids and TopHat - Set & Anchor Interconnects | NS2 - LV Skids and TopHat | Complete | 03/23/26 | 03/27/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01092 |
RPL10.Interior.NS2 - LV Skids and TopHat - Maintenance and Reserve Busways | NS2 - LV Skids and TopHat | Complete | 03/23/26 | 04/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01100 |
RPL10.Interior.NS2 - Tie-ins - WBS Summary | Tie-Ins | Active | 03/23/26 | 10/01/26 | 168.8 | 138.8 |
|
101.2 |
RPL10.INT.SSBC.02300 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N2.10) | Balance of Walls & OverHead | Complete | 03/23/26 | 03/31/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1400 |
RPL10.MCUP.Loop 2 - Tie-ins - WBS Summary | Tie-ins | Active | 03/23/26 | 06/05/26 | 78.8 | 36.2 |
|
136.2 |
RPL10.MCUP.LP2.1420 |
RPL10.MCUP.Loop 2 - Tie-in SD, DW *No Scope | Tie-Ins Mechanical | Complete | 03/23/26 | 03/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01110 |
RPL10.SKIN.NS43 - Install Roof System - Final Roof (Grid 10-10 / 10-01) | Roofing | Complete | 03/24/26 | 03/30/26 | 11.2 | 0.0 |
|
0.0 |
RPL.10.D.X3710.XG |
RMUs/MV Skids Set (Loop 1) - RPL10 NS1 | Give Milestones (XREFs) | Complete | 03/25/26 | 03/25/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3715.XG |
RMUs/MV Skids Set (Loop 2) - RPL10 NS1 | Give Milestones (XREFs) | Complete | 03/25/26 | 03/25/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01230 |
RPL10.EY.End - Install AHU Duct Stands & Ducts | OFE | Complete | 03/25/26 | 04/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07540 |
RPL10.Interior.Center-Corridor - Priority - Install Remaining Mechanical Valves & Piping (Highside OH space) | Priority Walls & OverHead | Complete | 03/25/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07680 |
RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (North Side) | Priority Walls & OverHead | Complete | 03/25/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01070 |
RPL10.SKIN.NS43 - Install Roof System - Exterior Wall Sheething | Roofing | Complete | 03/25/26 | 03/30/26 | 3.8 | 0.0 |
|
0.0 |
FR01.1080 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Fourth Delivery (6,7,8,9) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/26/26 | 03/27/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01210 |
RPL10.EY.NS1 - HAC Prefab prior to install | Tent and Temp Conditions | Complete | 03/26/26 | 03/27/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01160 |
RPL10.EY.NS2 - Install Tent Overhead Doors | Tent and Temp Conditions | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07600 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall, Tape, Float and Paint (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/26/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07700 |
RPL10.Interior.Center-Corridor - Priority - Exterior Wall Tape, Float and Paint | Priority Walls & OverHead | Complete | 03/26/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01670 |
RPL10.Interior.EF1 - Priority OH - Install Mechanical Piping (Drops On South EF wall for CRAH) | OverHead | Complete | 03/26/26 | 04/06/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6120 |
RPL10.Interior.End-Corridor - Priority - Install IMP Exterior MEP In-Wall Rough-Ins | Priority Walls & OverHead | Complete | 03/26/26 | 03/31/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01183 |
RPL10.Interior.NS1 - LV Skids and TopHat - Top Hat Busway | NS1 - LV Skids and TopHat | Complete | 03/26/26 | 03/27/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01320 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 5 | Active | 03/26/26 | 05/13/26 | 42.5 | 16.2 |
|
2.5 |
RPL10.INT.NS1.02460 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (LV Side Aisle) (upto 9) | OFE NS1 Control Fault Domain 5 | Complete | 03/26/26 | 03/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.N.01020 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-31/30 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01040 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-21/20 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.N.01060 |
RPL10.SKIN.North - Install IMP EJ - Grid lines 10-11/10 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01020 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-31/30 | Expansion Joint | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01040 |
RPL10.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Complete | 03/26/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.NS43.01180 |
RPL10.Structure.NS43 - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/26/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
GCD.RPL10.1725 |
Start FSHAC set in place - RPL10 - NS12 | Construction Milestones | Complete | 03/27/26 | 03/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01100 |
RPL10.EY.EF1 - Install RPL-2 FSP Deep Foundation (TCCO est Release 01-May-26) | Fiber Support Platform - RPL-2 | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01140 |
RPL10.EY.NS2 - Install Tent Electrical Panels | Tent and Temp Conditions | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01150 |
RPL10.EY.NS2 - Install Tent Heating and Cooling Equipment | Tent and Temp Conditions | Complete | 03/27/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01120 |
RPL10.EY.SSB - Install AHU (4) - CFCI | OFE | Complete | 03/27/26 | 03/27/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01630 |
RPL10.Interior.EF2 - Priority OH - Install Mechanical Piping (Drops On North EF wall for CRAH) | OverHead | Complete | 03/27/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01440 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 4 | Active | 03/27/26 | 06/02/26 | 57.5 | 20.0 |
|
2.5 |
RPL10.INT.NS1.02520 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Row 10 | OFE NS1 Control Fault Domain 4 | Complete | 03/27/26 | 03/27/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02800 |
RPL10.Interior.SSB-Corridor - BoW - Hang Drywall BoW | Balance of Walls & OverHead | Complete | 03/27/26 | 04/08/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01190 |
RPL10.EY.NS2 - Install Tent Mechanical Tie-ins | Tent and Temp Conditions | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01110 |
RPL10.EY.NS3 - Install Tent | Tent and Temp Conditions | Complete | 03/30/26 | 04/24/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01170 |
RPL10.EY.NS3 - Install Tent Fit-out | Tent and Temp Conditions | Active | 03/30/26 | 04/27/26 | 25.0 | 1.2 |
|
93.8 |
RPL10.EY.SSB.01170 |
RPL10.EY.SSB - Install Mechanical Duct Stands & Main Duct (include penetration detail) | Tie-ins | Complete | 03/30/26 | 04/20/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01180 |
RPL10.EY.SSB - Tie-ins - WBS Summary | Tie-ins | Active | 03/30/26 | 07/15/26 | 93.8 | 70.0 |
|
87.5 |
RPL10.INT.CTRC.01060 |
RPL10.Interior.Center-Corridor - Balance Of Walls - WBS Summary | Balance of Walls & OverHead | Active | 03/30/26 | 06/19/26 | 72.5 | 48.8 |
|
180.0 |
RPL10.INT.CTRC.01150 |
RPL10.Interior.Center-Corridor - BoW - Frame Balance Of Walls (Spoke Tech,Spoke Part, Bathroom, Fire Riser) | Balance of Walls & OverHead | Complete | 03/30/26 | 04/03/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07040 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (East Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/30/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07120 |
RPL10.Interior.Center-Corridor - BoW - Install Remaining Unistruts & Hangers | Balance of Walls & OverHead | Complete | 03/30/26 | 04/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01100 |
RPL10.Interior.EF1 - Priority OH - Electrical | OverHead | Complete | 03/30/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01440 |
RPL10.Interior.End-Corridor - Priority - Install Plumbing (Highside OH Space) | Priority Walls & OverHead | Complete | 03/30/26 | 04/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6340 |
RPL10.Interior.End-Corridor - Priority - Tape, Float and Paint Priority Soffit, Fire Safing Both Sides | Priority Walls & OverHead | Complete | 03/30/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01202 |
RPL10.Interior.NS1 - MES Skids - Final Piping Tie-Ins & Inspections | NS1 - MES Skids | Active | 03/30/26 | 05/08/26 | 30.0 | 12.5 |
|
56.2 |
RPL10.INT.NS1.01220 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Duct (LV SIde) | LV Side Tie-ins | Complete | 03/30/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01250 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 1 SQ6.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 6 | Active | 03/30/26 | 06/10/26 | 63.8 | 40.0 |
|
37.5 |
RPL10.INT.NS1.03160 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (LV Side Aisle) - Remaining (11-13) | OFE NS1 Control Fault Domain 4 | Complete | 03/30/26 | 03/30/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02840 |
RPL10.Interior.SSB-Corridor - BoW - QC BoW Backing/In-Wall | Balance of Walls & OverHead | Complete | 03/30/26 | 04/02/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01130 |
RPL10.SKIN.EF12 - Install Roof System - Install EJ Grid lines 10-11/10 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01130 |
RPL10.SKIN.NS12 - Install Roof System - Install EJ Grid lines 10-21/20 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.S.01040 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-21/20 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01070 |
RPL10.SKIN.South - Install IMP EJ - Grid lines 10-11/10 | Expansion Joint | Complete | 03/30/26 | 04/01/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01180 |
RPL10.EY.NS2 - Install Tent Electrical Tie-ins | Tent and Temp Conditions | Complete | 03/31/26 | 04/01/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6280 |
RPL10.Interior.End-Corridor - Priority - P7 Wall Hang Drywall (Both Sides) | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/31/26 | 04/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01580 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 3 | Active | 03/31/26 | 06/23/26 | 73.8 | 20.0 |
|
0.0 |
RPL10.INT.NS1.02580 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 3 | Complete | 03/31/26 | 04/01/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03380 |
RPL10.Interior.SSB - BoW - QC Backings/In-Walls | Balance of Walls and OverHead | Complete | 03/31/26 | 04/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02420 |
RPL10.Interior.SSB-Corridor - BoW - Tape Finish Paint BoW | Balance of Walls & OverHead | Complete | 03/31/26 | 04/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1820 |
RPL10.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Active | 03/31/26 | 06/15/26 | 66.2 | 43.8 |
|
465.0 |
RPL10.MCUP.LP1.1920 |
RPL10.MCUP.Loop 1 - Install Site Grading for Paving *Start 03/30 | Hardscape and Landscape | Active | 03/31/26 | 05/15/26 | 18.8 | 18.8 |
|
452.5 |
RPL10.SKN.SSB.01370 |
RPL10.SKIN.BLDG - RFI1103 Parapet Coping PVC Termication Incompatible material | Skin | Active | 03/31/26 | 04/27/26 | 5.0 | 1.2 |
|
307.5 |
RPL.CM.D.N5690.XR |
Bridge at LA 583 ( META GIVE MILESTONE) | Logistics - Off-Site Receive XREF Milsetones | Complete | 04/01/26 | 04/01/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4830 |
RPL10 - Prep / Submit for Review - Carpet | (CFCI) Div. 09 - Carpet | Complete | 04/01/26 | 04/08/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.CFCI.4880 |
RPL10 - Submittal Rvw/App'l -Epoxy Flooring (Spec 09 67 23) | (CFCI) Div. 09 - Epoxy Flooring | Complete | 04/01/26 | 04/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01100 |
RPL10.EY.EF2 - Install FSP - WBS Summary | Fiber Support Platform | Active | 04/01/26 | 01/15/27 | 248.8 | 227.5 |
|
91.2 |
RPL10.EY.EF2.01790 |
RPL10.EY.EF2 - Trade Partner Mobilization from North to South | Fiber Support Platform | Complete | 04/01/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS2.01200 |
RPL10.EY.NS2 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/13/26) | Tent and Temp Conditions | Complete | 04/01/26 | 04/03/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07660 |
RPL10.Interior.Center-Corridor - BoW - Install EZ Path | Balance of Walls & OverHead | Complete | 04/01/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6090 |
RPL10.Interior.End-Corridor - Priority - Install FA (Highside OH space) | Priority Walls & OverHead | Complete | 04/01/26 | 04/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.02420 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (HAC) | OFE NS1 Control Fault Domain 6 | Complete | 04/01/26 | 04/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01110 |
RPL10.Interior.NS2 - MES Skids Tie-ins (LOE) | NS2 - MES Skids | Active | 04/01/26 | 06/25/26 | 75.0 | 53.8 |
|
157.5 |
RPL10.INT.NS2.01111 |
RPL10.Interior.NS2 - MES Skids - Set & Anchor Interconnects | NS2 - MES Skids | Complete | 04/01/26 | 04/07/26 | 30.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01080 |
RPL10.Interior.NS3 - OFE - WBS Summary | OFE | Active | 04/01/26 | 11/30/26 | 208.8 | 181.2 |
|
55.0 |
RPL10.INT.NS3.02480 |
RPL10.Interior.NS3 - OFE - MES Skids - Pre Set 30"" Piping | OFE | Complete | 04/01/26 | 04/17/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01080 |
RPL10.Interior.NS4 - OFE - WBS Summary | OFE | Active | 04/01/26 | 11/03/26 | 188.8 | 167.5 |
|
88.8 |
RPL10.INT.NS4.02425 |
RPL10.Interior.NS4 - OFE - MES Skids - Pre Set 30"" Piping | OFE | Complete | 04/01/26 | 04/17/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01090 |
RPL10.Interior.EF1 - Priority OH - Security | OverHead | Active | 04/02/26 | 04/27/26 | 2.5 | 1.2 |
|
160.0 |
RPL10.INT.EF1.01160 |
RPL10.Interior.EF1 - CFCI - WBS Summary | OFE | Active | 04/02/26 | 05/22/26 | 37.5 | 25.0 |
|
111.2 |
RPL10.INT.EF1.01190 |
RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 East | OFE | Active | 04/02/26 | 05/04/26 | 12.5 | 7.5 |
|
47.5 |
RPL10.INT.NS1.01720 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS1 Control Fault Domain 2 | Active | 04/02/26 | 07/15/26 | 90.0 | 20.0 |
|
-2.5 |
RPL10.INT.NS1.02640 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle) | OFE NS1 Control Fault Domain 2 | Complete | 04/02/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.CBL.1160 |
RPL10.Conn BLDG - Install GS and Production Cabling - WBS Summary | Connectivity | Active | 04/06/26 | 03/20/29 | 922.5 | 903.8 |
|
0.0 |
RPL10.EY.NS1.01250 |
RPL10.EY.NS1 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Active | 04/06/26 | 04/27/26 | 12.5 | 1.2 |
|
22.5 |