Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
87
Completed
13
In Progress
87
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.SSB.04240 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/10/26 | 03/13/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04280 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/10/26 | 03/13/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.04100 |
RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall (Remaining Work) | Priority Walls & OverHead | Complete | 03/10/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
GCD.RPL10.1655 |
Start MES Installation - RPL10 | Construction Milestones | Complete | 03/11/26 | 03/11/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01280 |
RPL10.EY.EF2 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Complete | 03/11/26 | 04/06/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01290 |
RPL10.EY.EF2 - Tie-ins - WBS Summary | Tie-ins | Active | 03/11/26 | 05/27/26 | 67.5 | 25.0 |
|
182.5 |
RPL10.INT.CTRC.01830 |
RPL10.Interior.Center-Corridor - Priority - Install FA/ Linear Heat Detection (Highside OH space) | Priority Walls & OverHead | Complete | 03/11/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07160 |
RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF1) | EF Perimeter Walls | Complete | 03/11/26 | 03/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07620 |
RPL10.Interior.Center-Corridor - Priority - MEP In-Wall Rough Ins/Backing (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 03/11/26 | 03/20/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6220 |
RPL10.Interior.End-Corridor - Priority - P7 Wall MEP In-Wall Rough Ins | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/11/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6380 |
RPL10.Interior.End-Corridor - Priority - P7 Wall Backing | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/11/26 | 04/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01150 |
RPL10.Interior.NS1 - OFE - MES Skids - Set / Place / Anchor **03/12 | OFE | Complete | 03/11/26 | 04/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02320 |
RPL10.Interior.NS3 - Priority - Install Drywall at Exterior Wall | OverHead | Complete | 03/11/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01251 |
RPL10.Interior.SSB-Corridor - Install Electrical - SSB Electrical Room (10.S2.06) | Balance of Walls & OverHead | Complete | 03/11/26 | 03/19/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02240 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N1.08) | Balance of Walls & OverHead | Complete | 03/11/26 | 03/31/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02620 |
RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Piping Lowside OH and In-Wall | Balance of Walls & OverHead | Complete | 03/11/26 | 03/20/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02680 |
RPL10.Interior.SSB-Corridor - BoW - Install VAV's | Balance of Walls & OverHead | Complete | 03/11/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1360 |
RPL10.MCUP.Loop 2 - Set mCUPs #8 (1 per 5 days) | OFE | Complete | 03/11/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01140 |
RPL10.SKIN.SSB - Install Roof System - Install EJ Grid lines 10-31/30 | Expansion Joint | Complete | 03/11/26 | 03/13/26 | 5.0 | 0.0 |
|
0.0 |
FR01.1020 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - First Delivery (Benchmark) ((1)) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
FR01.1040 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Second Delivery (2,3) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1120 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - First Delivery (Row 1) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
FR02.1140 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Second Delivery (Row 2) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/07/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1160 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Third Delivery (Row 3,4,5) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/09/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1180 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 6,7,8) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/10/26 | 2.5 | 0.0 |
|
0.0 |
FR02.1200 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 9) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/10/26 | 2.5 | 0.0 |
|
0.0 |
NW.2140 |
031226 - Non Weather Impact #3 - Power Outage Due to Severe Weather 031226 | Project Impacts | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01050 |
RPL10.Interior.NS4 - Priority - Install FA / Linear heat detection | OverHead | Complete | 03/12/26 | 03/18/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01130 |
RPL10.EY.EF1 - Install UPS-CU (2) | OFE | Complete | 03/13/26 | 03/13/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01080 |
RPL10.EY.End - Cure (High Early Mix) | Foundations | Complete | 03/13/26 | 03/19/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01200 |
RPL10.EY.NS1 - Tent Temp Conditioning Startup and Available (Including Acclimation) (02/23/26) | Tent and Temp Conditions | Complete | 03/13/26 | 03/20/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01080 |
RPL10.EY.NS3 - Tent SOG Cure | Tent and Temp Conditions | Complete | 03/13/26 | 03/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01070 |
RPL10.Interior.NS2 - OFE - MES Skids - Set / Place / Anchor | OFE | Complete | 03/13/26 | 04/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01120 |
RPL10.SKIN.EF12 - Install Roof System - Final Roof (Grid 10-20 / 10-10) | Roofing | Complete | 03/13/26 | 03/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01180 |
RPL10.Structure.EF12 - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/13/26 | 03/19/26 | 6.2 | 0.0 |
|
0.0 |
RPL.CM.D.C5520.XR |
Burn Road East | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5540.XR |
Chewy Court ( Around RPL10 & Admin) | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5840.XR |
R2 Road | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5860.XR |
D2 Pass | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01050 |
RPL10.EY.EF1 - Install Fiber Support Platform (FSP) - WBS Summary | Fiber Support Platform | Active | 03/16/26 | 07/29/26 | 118.8 | 82.5 |
|
223.8 |
RPL10.EY.EF1.01580 |
RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization | Fiber Support Platform | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01600 |
RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization & Setup | Fiber Support Platform | Complete | 03/16/26 | 03/18/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01610 |
RPL10.EY.EF2 - Install Remaining UPS-CU (2) | OFE | Complete | 03/16/26 | 03/16/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01540 |
RPL10.EY.SSB - Install AHU Duct Stands & Ducts | OFE | Complete | 03/16/26 | 03/26/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07560 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Frame Wall (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/16/26 | 03/18/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01000 |
RPL10.Interior.EF1 - Priority OH - Install Duct (Highside OH space) | OverHead | Complete | 03/16/26 | 03/16/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01120 |
RPL10.Interior.EF1 - Priority OH - Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01000 |
RPL10.Interior.EF2 - Priority OH - Install Duct (Highside OH space) | OverHead | Complete | 03/16/26 | 03/16/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01120 |
RPL10.Interior.EF2 - Priority OH - Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01130 |
RPL10.Interior.NS1 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01180 |
RPL10.Interior.NS1 - LV Skids and TopHat Tie-ins (LOE) | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/27/26 | 32.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01181 |
RPL10.Interior.NS1 - LV Skids and TopHat - Set & Anchor Interconnects | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/25/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01182 |
RPL10.Interior.NS1 - LV Skids and TopHat - Maintenance and Reserve Busways | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/25/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01190 |
RPL10.Interior.NS1 - Tie-ins - WBS Summary | Tie-Ins | Active | 03/16/26 | 08/21/26 | 142.5 | 103.8 |
|
125.0 |
RPL10.INT.NS1.01200 |
RPL10.Interior.NS1 - MES Skids Tie-ins (LOE) | NS1 - MES Skids | Active | 03/16/26 | 07/02/26 | 97.5 | 60.0 |
|
140.0 |
RPL10.INT.NS1.01201 |
RPL10.Interior.NS1 - MES Skids - Set & Anchor Interconnects | NS1 - MES Skids | Complete | 03/16/26 | 04/07/26 | 30.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02380 |
RPL10.Interior.NS2 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01010 |
RPL10.Interior.NS3 - Priority - Install Duct | OverHead | Complete | 03/16/26 | 04/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01050 |
RPL10.Interior.NS3 - Priority - Install FA / Linear heat detection | OverHead | Complete | 03/16/26 | 03/20/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02380 |
RPL10.Interior.NS3 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02400 |
RPL10.Interior.NS3 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02380 |
RPL10.Interior.NS4 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02400 |
RPL10.Interior.NS4 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/30/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01100 |
RPL10.Interior.SSB - BoW - Install Controls / EPMS / BMS and In-wall | Balance of Walls and OverHead | Complete | 03/16/26 | 03/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03360 |
RPL10.Interior.SSB - BoW - Install Backings | Balance of Walls and OverHead | Complete | 03/16/26 | 03/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.07000 |
RPL10.Interior.SSB - Priority - P5 MEP In-Wall Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/16/26 | 03/19/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1540 |
RPL10.MCUP.Loop 1 - Tie-in BMS (LOE) | Tie-Ins BMS | Active | 03/16/26 | 05/20/26 | 50.0 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1560 |
RPL10.MCUP.Loop 1 - Tie-in BMS #1 | Tie-Ins BMS | Active | 03/16/26 | 05/20/26 | 10.0 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1580 |
RPL10.MCUP.Loop 1 - Tie-in EPMS (LOE) | Tie-Ins EPMS | Active | 03/16/26 | 05/20/26 | 50.0 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1600 |
RPL10.MCUP.Loop 1 - Tie-in EPMS #1 | Tie-Ins EPMS | Active | 03/16/26 | 05/20/26 | 8.8 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1660 |
RPL10.MCUP.Loop 1 - Tie-in SD, DW **Confirm Scope | Tie-Ins Mechanical | Complete | 03/16/26 | 03/17/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01000 |
RPL10.SKIN.EF12 - Install Temp Doors | Glazing, Doors and Ext Devices | Complete | 03/16/26 | 03/17/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01020 |
RPL10.SKIN.EF12 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Active | 03/16/26 | 07/24/26 | 115.0 | 22.5 |
|
235.0 |
RPL10.INT.CTRC.01140 |
RPL10.Interior.Center-Corridor - OFE - NS2 (1x Optical Splice) (03.10.26) (Rev-03.16.26) | OFE | Active | 03/17/26 | 04/27/26 | 12.5 | 1.2 |
|
127.5 |
RPL10.INT.CTRC.07000 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (East Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/17/26 | 03/20/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07640 |
RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF2) | EF Perimeter Walls | Complete | 03/17/26 | 03/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01030 |
RPL10.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH Space) | Priority Walls & OverHead | Complete | 03/17/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01060 |
RPL10.Interior.NS2 - OFE - LV Skids and TopHat - Set / Place / Anchor (03.18.26) | OFE | Complete | 03/17/26 | 03/30/26 | 25.0 | 0.0 |
|
0.0 |
GCD.RPL10.1020 |
Weather tight SSB and NS12 | Construction Milestones | Complete | 03/18/26 | 03/18/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06980 |
RPL10.Interior.Center-Corridor - Priority - QC - P6 Wall - Backing/Wall | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/18/26 | 03/19/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06720 |
RPL10.Interior.SSB - BoW - Install Remaining Unistruts & Hangers | Balance of Walls and OverHead | Complete | 03/18/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.7060 |
RPL10 - Fabricate / Deliver - Scuppers, Awning over Doors | Fixed Louvers | Active | 03/19/26 | 06/15/26 | 6.2 | 43.8 |
|
125.0 |
RPL10.CFCI.7100 |
RPL10 - Fabricate / Deliver - Metal Canopy | Fixed Louvers | Active | 03/19/26 | 06/08/26 | 6.2 | 37.5 |
|
155.0 |
RPL10.EY.EF1.01040 |
RPL10.EY.EF1 - Install RPL-1 FSP Deep Foundation (TCCO est Release 09-Feb-26) | Fiber Support Platform - RPL-1 | Complete | 03/19/26 | 03/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01710 |
RPL10.Interior.Center-Corridor - Priority - QC Exterior Wall - Backing/In-Wall | Priority Walls & OverHead | Complete | 03/19/26 | 03/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07580 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall MEP In-Wall/Backing (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/19/26 | 03/25/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6260 |
RPL10.Interior.End-Corridor - Priority - Install IMP Backing Exterior Wall | Priority Walls & OverHead | Complete | 03/19/26 | 03/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04300 |
RPL10.Interior.SSB - Priority - P5 QC - Backings/In-Wall | Priority Wall (P5) - Grid Line 10-C | Complete | 03/19/26 | 03/19/26 | 3.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04400 |
RPL10.Interior.SSB - BoW - Notify META for TV Installation & Conf Sound (+25d Install TV) | Balance of Walls and OverHead | Complete | 03/19/26 | 03/19/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02740 |
RPL10.Interior.SSB-Corridor - BoW - MEPF Frame Hard Lid Rough Ins/Close of Inspection | Balance of Walls & OverHead | Complete | 03/19/26 | 03/19/26 | 1.2 | 0.0 |
|
0.0 |
NW.1100 |
MCUP 600 Ton Crane Demobilization | 600 Ton Crane (MCUP) | Complete | 03/20/26 | 03/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01730 |
RPL10.Interior.Center-Corridor - Priority - Install Drywall at Exterior Wall | Priority Walls & OverHead | Complete | 03/20/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02390 |
RPL10.Interior.NS3 - Priority - Exterior Wall Tape, Float and Paint NS3 (sanding off hours) | OverHead | Complete | 03/20/26 | 04/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02330 |
RPL10.Interior.NS4 - Priority - Exterior Wall Tape, Float and Paint NS4 (sanding off hours) | OverHead | Complete | 03/20/26 | 04/08/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04260 |
RPL10.Interior.SSB - Priority - P5 Two Side Drywall Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/20/26 | 03/30/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.07020 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/20/26 | 04/02/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01160 |
RPL10.Structure.EF12 - SOG Sealant Cure | F/R/P | Complete | 03/20/26 | 03/21/26 | 2.5 | 0.0 |
|
0.0 |
FR01.1060 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Third Delivery (4,5) (4/21/26 Saturday) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/23/26 | 03/23/26 | 1.2 | 0.0 |
|
0.0 |
ICM.B10.1845 |
[NWB] Delivery of FSHAC - Hot Aisle Containment (First Delivery) - RPL10 | Construction | Complete | 03/23/26 | 03/23/26 | 0.0 | 0.0 |
|
0.0 |
JCL.C.1160 |
RPL10 - Cost Risk LOE-9 HAC Install | Cost LOEs | Active | 03/23/26 | 11/30/26 | 206.2 | 187.5 |
|
55.0 |