Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer
· Uploaded May 05, 2026 02:13 PM
· 8463 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
90
Completed
10
In Progress
90
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.CFCI.5700 |
RPL10 - Submittal Rvw/App'l - Glass / Frames (Awaiting Substitiute Approval) | Glass & Glazing (Alum. Entrances & Curtainwall) | Active | 02/24/26 | 04/27/26 | 1.2 | 0.0 |
|
126.2 |
RPL10.INT.CTRC.01010 |
RPL10.Interior.Center-Corridor - Priority - Install Duct (LOE) | Priority Walls & OverHead | Complete | 02/24/26 | 03/27/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01011 |
RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) | Priority Walls & OverHead | Complete | 02/24/26 | 03/10/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01090 |
RPL10.SKIN.EF12 - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ | Roofing | Complete | 02/24/26 | 02/25/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01012 |
RPL10.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) | Priority Walls & OverHead | Complete | 02/25/26 | 03/24/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01260 |
RPL10.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls and OverHead | Active | 02/25/26 | 04/27/26 | 8.8 | 1.2 |
|
137.5 |
RPL10.EY.NS4.01060 |
RPL10.EY.NS4 - Tent SOG Cure | Tent and Temp Conditions | Complete | 02/26/26 | 02/27/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06820 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Hang Drywall (East Side) | Priority Wall (P3) - Grid Line 10-25 | Complete | 02/26/26 | 03/02/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.2580 |
RPL10.MCUP.Loop 2 - F/R/P Pad for GS.IDF NX10 | Foundations | Complete | 02/26/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
NW.1040 |
MCUP 600 Ton Crane Movement 2 | 600 Ton Crane (MCUP) | Complete | 02/27/26 | 02/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3860.XG |
Ready for MV Cable Pull NS 2 (Loop 1) | Give Milestones (XREFs) | Complete | 02/27/26 | 02/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3865.XG |
Ready for MV Cable Pull NS 2 (Loop 2) | Give Milestones (XREFs) | Complete | 02/27/26 | 02/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3880.XG |
Ready for MV Cable Pull NS 3 (Loop 1) | Give Milestones (XREFs) | Complete | 02/27/26 | 02/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL.10.D.X3885.XG |
Ready for MV Cable Pull NS 3 (Loop 2) | Give Milestones (XREFs) | Complete | 02/27/26 | 02/27/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06860 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Tape, Float and Paint (East Side) | Priority Wall (P3) - Grid Line 10-25 | Complete | 02/27/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06920 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall MEP In-Wall Rough Ins | Priority Wall (P6) - Grid Line 10-16 | Complete | 02/27/26 | 03/09/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06940 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Backing | Priority Wall (P6) - Grid Line 10-16 | Complete | 02/27/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02110 |
RPL10.Interior.NS4 - Priority - Install Plumbing / Mechanical Piping | OverHead | Complete | 02/27/26 | 03/13/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.W.01000 |
RPL10.SKIN.West - Install IMP Flashing,Panels & Caulking - Grid lines 10A/10F(10) (with temp closures for openings) | West | Complete | 02/27/26 | 03/02/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.SKN.W.01010 |
RPL10.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary | West | Complete | 02/27/26 | 03/11/26 | 13.8 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01160 |
RPL10.Structure.NS1 - SOG Sealant Cure | F/R/P | Complete | 02/28/26 | 02/28/26 | 1.2 | 0.0 |
|
0.0 |
FR03.1220 |
FR03: PSI - NS1 & NS2 - PCX H01 & H02 - Delivery | FR03: House Power Skid Missing Panel Delay | Active | 03/02/26 | 06/02/26 | 1.2 | 32.5 |
|
15.0 |
GCD.RPL10.1390 |
IMP Complete - RPL10 | Construction Milestones | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.1700 |
Start LV Electrical Skid Set-In-Place - RPL10 | Construction Milestones | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL10.1826 |
Delivery of RMU - (First Delivery) - RPL10 - NS12 | Construction Milestones | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1825 |
[NWB] Delivery of MVS - Medium Voltage Switches (First Delivery) | Construction | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
ICM.B10.1850 |
[NWB] Delivery of NES - Network Electrical Room Skid (First Delivery) - RPL10 | Construction | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
NW.1800 |
IMP Crane #1 Movement 09 | IMP Crane #1 | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01560 |
RPL10.EY.EF2 - Install F/R/P Remaining Equipment Pads (IDF/CRAH/CRAC) | Foundations | Complete | 03/02/26 | 03/03/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01140 |
RPL10.EY.NS1 - Install Tent Electrical Panels | Tent and Temp Conditions | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01150 |
RPL10.EY.NS1 - Install Tent Heating and Cooling Equipment | Tent and Temp Conditions | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01170 |
RPL10.EY.NS1 - Install Tent Fit-out | Tent and Temp Conditions | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01190 |
RPL10.EY.NS1 - Install Tent Mechanical Tie-ins | Tent and Temp Conditions | Complete | 03/02/26 | 03/09/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07520 |
RPL10.Interior.Center-Corridor - Priority - P6 Hang Drywall Tape, Float and Paint (for IDFs) (03.05.26) | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/02/26 | 03/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01140 |
RPL10.Interior.NS1 - OFE - LV Skids and TopHat - Set / Place / Anchor (03.04.26) | OFE | Complete | 03/02/26 | 03/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02420 |
RPL10.Interior.NS4 - Priority - Install Temp Doors Frame Hardware | OverHead | Complete | 03/02/26 | 03/04/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1420 |
RPL10.MCUP.Loop 1 - Tie-in Electrical (LOE) | Tie-Ins Electrical | Active | 03/02/26 | 05/20/26 | 51.2 | 22.5 |
|
12.5 |
RPL10.MCUP.LP1.1480 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #1 | Tie-Ins Electrical | Active | 03/02/26 | 05/20/26 | 11.2 | 22.5 |
|
12.5 |
RPL10.MCUP.LP2.1300 |
RPL10.MCUP.Loop 2 - Set mCUPs #4 (1 per 5 days) | OFE | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.NS12.01120 |
RPL10.SKIN.NS12 - Install Roof System - Final Roof (Grid 10-30 / 10-20) | Roofing | Complete | 03/02/26 | 03/18/26 | 11.2 | 0.0 |
|
0.0 |
RPL10.SKN.S.01160 |
RPL10.SKIN - Install Comeback Leave out IMP Flashing,Panels & Caulking (EF Area/FSP) | IMP System | Complete | 03/02/26 | 03/03/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01320 |
RPL10.Structure.NS2 - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.STR.SSB.01230 |
RPL10.Structure.SSB - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.WA.OFE.01000 |
RPL10.WA - FDN to OFE | Weather Allowance | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.04060 |
RPL10.Interior.SSB-Corridor - BoW - Hang Drywall Tape Finish Paint (GS MDF Electrical Room) BoW | Balance of Walls & OverHead | Complete | 03/03/26 | 03/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.04080 |
RPL10.Interior.SSB-Corridor - Priority - OFE Waterproofing Protection Layer Delay | Priority Walls & OverHead | Complete | 03/03/26 | 03/09/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01580 |
RPL10.EY.EF2 - Cure for Remaining Equipment Pads (High Early Mix) | Foundations | Complete | 03/04/26 | 03/06/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01180 |
RPL10.EY.NS1 - Install Tent Electrical Tie-ins | Tent and Temp Conditions | Complete | 03/04/26 | 03/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01000 |
RPL10.Interior.End-Corridor - Install Priority Walls and OverHead- WBS Summary | Priority Walls & OverHead | Active | 03/04/26 | 05/05/26 | 55.0 | 8.8 |
|
111.2 |
RPL10.INT.ENDC.01020 |
RPL10.Interior.End-Corridor - Install Priority OH, Walls, Fitout and Build Back - WBS Summary | End Corridor | Active | 03/04/26 | 02/12/27 | 297.5 | 251.2 |
|
78.8 |
RPL10.INT.ENDC.6320 |
RPL10.Interior.End-Corridor - Priority - Frame Priority Soffit and Hang Drywall | Priority Walls & OverHead | Complete | 03/04/26 | 03/10/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07460 |
RPL10.Interior.Center-Corridor - Priority - Install Remaining Supplemental Steel (Exterior Walls) | Priority Walls & OverHead | Complete | 03/05/26 | 03/27/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01080 |
RPL10.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall *Lowside Separate Activity | Balance of Walls and OverHead | Complete | 03/05/26 | 04/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01740 |
RPL10.Interior.SSB - Loading Dock and Storage - Install VAV's/ Duct Branches | Loading Dock and Storage | Complete | 03/05/26 | 03/20/26 | 12.5 | 0.0 |
|
0.0 |
FR01.1000 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Issue Identification & Notification | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/06/26 | 03/06/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1100 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Issue Identification & Notification | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/06/26 | 03/06/26 | 1.2 | 0.0 |
|
0.0 |
NW.1080 |
MCUP 600 Ton Crane Movement 4 (If Needed) | 600 Ton Crane (MCUP) | Complete | 03/06/26 | 03/06/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01090 |
RPL10.EY.End - Install GS.IDF Hut (1x GS.IDF) NX10 (05.29.26) | OFE | Complete | 03/06/26 | 03/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01100 |
RPL10.EY.End - OFE - WBS Summary | OFE | Complete | 03/06/26 | 04/22/26 | 41.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01250 |
RPL10.Interior.Center-Corridor - OFE - NS4 (1x GS.IDF) N41 (03.06.26) | OFE | Complete | 03/06/26 | 03/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01310 |
RPL10.Interior.Center-Corridor - OFE - NS3 (1x GS.IDF) N31 (03.06.26) | OFE | Complete | 03/06/26 | 03/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02440 |
RPL10.Interior.Center-Corridor - Priority - P4 Tape, Float and Paint (EF2 Wall Along Grid 10-D) (02.17.26) | Priority Wall (P4) - Grid Line 10-D | Complete | 03/06/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.02460 |
RPL10.Interior.Center-Corridor - Priority - Frame Wall (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 03/06/26 | 03/11/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07440 |
RPL10.Interior.Center-Corridor - Priority - Install Remaining Supplemental Steel (Wing Walls) | Priority Walls & OverHead | Complete | 03/06/26 | 03/27/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6180 |
RPL10.Interior.End-Corridor - Priority - P7 Frame Remaining Wall | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/06/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02340 |
RPL10.Interior.NS2 - Priority - Install Electrical **to clarify scope *03/02 | OverHead | Complete | 03/06/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01010 |
RPL10.Interior.NS4 - Priority - Install Duct | OverHead | Complete | 03/06/26 | 03/27/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1700 |
RPL10.MCUP.Loop 1 - Tie-in Electrical #3 | Tie-Ins Electrical | Active | 03/06/26 | 05/20/26 | 8.8 | 22.5 |
|
12.5 |
RPL10.STR.SSB.01210 |
RPL10.Structure.SSB - SOG Sealant Cure | F/R/P | Complete | 03/06/26 | 03/06/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.STR.NS12.01340 |
RPL10.Structure.NS2 - SOG Sealant Cure | F/R/P | Complete | 03/07/26 | 03/07/26 | 1.2 | 0.0 |
|
0.0 |
GCD.RPL10.1290 |
Interior fit-out Start RPL10 - NS43 | Construction Milestones | Complete | 03/09/26 | 03/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01060 |
RPL10.EY.End - Install F/R/P Equipment Pads | Foundations | Complete | 03/09/26 | 03/12/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01070 |
RPL10.EY.End - Install Foundations - WBS Summary | Foundations | Complete | 03/09/26 | 03/19/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01160 |
RPL10.EY.NS1 - Install Tent Overhead Doors | Tent and Temp Conditions | Complete | 03/09/26 | 03/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01220 |
RPL10.EY.NS1 - Install MV, RMUs & Electrical Panels (15) | OFE | Complete | 03/09/26 | 03/25/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01230 |
RPL10.EY.NS1 - OFE - MV - WBS Summary | OFE | Complete | 03/09/26 | 04/15/26 | 32.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01070 |
RPL10.EY.NS3 - Install Tent F/R/P SOG (30k Mock Up) | Tent and Temp Conditions | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01810 |
RPL10.Interior.Center-Corridor - Priority - Install Backing Exterior Wall | Priority Walls & OverHead | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07480 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Hang Drywall (Outside) (EF1 & EF2) | EF Perimeter Walls | Complete | 03/09/26 | 03/12/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01050 |
RPL10.Interior.EF1 - Priority OH - Install Vesda / FA / Linear Heat Detection | OverHead | Complete | 03/09/26 | 03/11/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01050 |
RPL10.Interior.EF2 - Priority OH - Install Vesda / FA / Linear Heat Detection | OverHead | Complete | 03/09/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01040 |
RPL10.Interior.End-Corridor - Priority - Install Temp Lighting (Show in Model) | Priority Walls & OverHead | Complete | 03/09/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6080 |
RPL10.Interior.End-Corridor - Priority - Install Layout Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & OverHead | Complete | 03/09/26 | 03/18/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02420 |
RPL10.Interior.NS3 - Priority - Install Temp Doors Frame Hardware | OverHead | Complete | 03/09/26 | 03/11/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01070 |
RPL10.Interior.SSB - BoW - Doors Frame | Balance of Walls and OverHead | Complete | 03/09/26 | 03/11/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01800 |
RPL10.Interior.SSB - BoW - Install VAV's/ Duct Branches | Balance of Walls and OverHead | Complete | 03/09/26 | 04/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02580 |
RPL10.Interior.SSB-Corridor - Priority - Install FA (Highside OH space) *No Scope | Priority Walls & OverHead | Complete | 03/09/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03100 |
RPL10.Interior.SSB-Corridor - Priority - P2 Wall Tape Finish Paint | Priority Wall (P2) - Grid Line 10-38 | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1320 |
RPL10.MCUP.Loop 2 - Set mCUPs #6 (1 per 5 days) | OFE | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01000 |
RPL10.SKIN.NS43 - Install Temp Doors | Glazing, Doors and Ext Devices | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01020 |
RPL10.SKIN.NS43 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Active | 03/09/26 | 01/20/27 | 272.5 | 167.5 |
|
83.8 |
RPL10.SKN.S.01100 |
RPL10.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin | South | Complete | 03/09/26 | 03/11/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.W.01040 |
RPL10.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | West | Complete | 03/09/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
ICM.B10.1855 |
[NWB] Delivery of MES - Multi Trade Rack (First Delivery) - RPL10 | Construction | Complete | 03/10/26 | 03/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01090 |
RPL10.Interior.Center-Corridor - OFE - NS1 (1x Optical Splice) (03.04.26) (Rev-03.09.26) | OFE | Active | 03/10/26 | 04/27/26 | 12.5 | 1.2 |
|
127.5 |
RPL10.INT.CTRC.07500 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Outside) (EF1 & EF2) | EF Perimeter Walls | Complete | 03/10/26 | 03/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02320 |
RPL10.Interior.NS4 - Priority - Install Drywall at Exterior Wall | OverHead | Complete | 03/10/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01220 |
RPL10.Interior.SSB - BoW - Install Security Lowside OH and In-wall | Balance of Walls and OverHead | Complete | 03/10/26 | 03/25/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01240 |
RPL10.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls and OverHead | Complete | 03/10/26 | 03/30/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03480 |
RPL10.Interior.SSB - Priority - P0 & P1 Wall Tape Float Paint (East Sides) | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 03/10/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |