Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
92
Completed
8
In Progress
94
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.MCUP.LP2.1180 RPL10.MCUP.Loop 2 - Cure for Pads Foundations Complete 02/13/26 03/04/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP2.1260 RPL10.MCUP.Loop 2 - Set mCup #6 - Dry Coolers (6) (4 per week) OFE Complete 02/13/26 02/17/26 7.5 0.0
100%
0.0
RPL10.SKN.NS12.01090 RPL10.SKIN.NS12 - Install Roof System - Install Bent Plate & Gusset Plates & Temp Flashing at EJ Roofing Complete 02/13/26 02/16/26 2.5 0.0
100%
0.0
RPL10.EY.NS2.01130 RPL10.EY.NS2 - Cure (High Early Mix) Foundations Complete 02/15/26 02/21/26 8.8 0.0
100%
0.0
RPL10.EY.EF1.01120 RPL10.EY.EF1 - Install Electrical Panels (2) (GSB and LB Equipment) OFE Complete 02/16/26 02/16/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.01770 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Hang Drywall (Inside) (EF1 & EF2) EF Perimeter Walls Complete 02/16/26 02/19/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01890 RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Inside) (EF1 & EF2) EF Perimeter Walls Complete 02/16/26 03/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.02320 RPL10.Interior.NS1 - Priority - Exterior Wall Tape, Float and Paint NS1 (sanding off hours) *02/16 OverHead Complete 02/16/26 02/23/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.02720 RPL10.Interior.SSB-Corridor - Priority - P2 Wall Hang Drywall (Both Sides) Priority Wall (P2) - Grid Line 10-38 Complete 02/16/26 02/19/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1620 RPL10.MCUP.Loop 1 - Set mCUPs #7 (1 per 5 days) OFE Complete 02/16/26 02/20/26 6.2 0.0
100%
0.0
RPL10.STR.NS43.01120 RPL10.Structure.NS43 - SOG F/R/P (Pour #21 -01/31 & #22 -02/03) - Grid lines 10-07/10-04 F/R/P Complete 02/16/26 02/17/26 2.5 0.0
100%
0.0
RPL10.STR.SSB.01030 RPL10.Structure.SSB - Install Storm Shelter F/R/P Deck Storm Shelter Complete 02/16/26 02/18/26 3.8 0.0
100%
0.0
ICM.B10.1840 [NWB] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Complete 02/17/26 02/17/26 0.0 0.0
100%
0.0
RPL.CM.D.C54X0.XR Logistics Area #10 - Complete Logistics - Area Turnovers XREF Milestones Complete 02/17/26 02/17/26 0.0 0.0
100%
0.0
RPL10.EY.EF2.01590 RPL10.EY.EF2 - Install Remaining Electrical Panels (2) (GSB and LB Equipment) OFE Complete 02/17/26 02/17/26 2.5 0.0
100%
0.0
RPL10.EY.NS2.01090 RPL10.EY.NS2 - Install Tent Tent and Temp Conditions Complete 02/17/26 03/30/26 26.2 0.0
100%
0.0
RPL10.INT.CTRC.01530 RPL10.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) Priority Walls & OverHead Complete 02/17/26 03/06/26 12.5 0.0
100%
0.0
RPL10.INT.CTRC.01550 RPL10.Interior.Center-Corridor - Priority - Install Mechanical Piping (Highside OH space) Priority Walls & OverHead Complete 02/17/26 03/09/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.02420 RPL10.Interior.Center-Corridor - Priority - P4 Hang Drywall (EF2 Wall Along Grid 10-D) Priority Wall (P4) - Grid Line 10-D Complete 02/17/26 03/05/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01100 RPL10.Interior.NS1 - Priority - Install Temp Doors Frame Hardware OverHead Complete 02/17/26 02/19/26 3.8 0.0
100%
0.0
RPL10.INT.NS3.01000 RPL10.Interior.NS3 - Priority - WBS Summary OverHead Complete 02/17/26 04/21/26 53.8 0.0
100%
0.0
RPL10.INT.NS3.01020 RPL10.Interior.NS3 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS3 Active 02/17/26 01/19/27 285.0 222.5
0%
126.2
RPL10.INT.NS3.01030 RPL10.Interior.NS3 - Priority - Install Fire Sprinkler OverHead Complete 02/17/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01000 RPL10.Interior.NS4 - Priority - WBS Summary OverHead Complete 02/17/26 04/21/26 57.5 0.0
100%
0.0
RPL10.INT.NS4.01020 RPL10.Interior.NS4 - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary NS4 Active 02/17/26 12/29/26 272.5 212.5
0%
130.0
RPL10.INT.NS4.01030 RPL10.Interior.NS4 - Priority - Install Fire Sprinkler *(02/18) OverHead Complete 02/17/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01170 RPL10.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Active 02/17/26 07/09/26 125.0 58.8
0%
173.8
RPL10.INT.SSB.01510 RPL10.Interior.SSB - Loading Dock and Storage - Install Door Frames Loading Dock and Storage Complete 02/17/26 02/18/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02660 RPL10.Interior.SSB-Corridor - BoW - Frame Hard Lid Balance of Walls & OverHead Complete 02/17/26 02/23/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1400 RPL10.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Active 02/17/26 05/28/26 88.8 28.8
0%
12.5
RPL10.MCUP.LP1.1440 RPL10.MCUP.Loop 1 - Tie-in Mechanical (LOE) Tie-Ins Mechanical Active 02/17/26 05/14/26 40.0 17.5
0%
12.5
RPL10.MCUP.LP1.1460 RPL10.MCUP.Loop 1 - Tie-in Mechanical #1 WBS Summary Tie-in Mechanical #1 Complete 02/17/26 04/15/26 13.8 0.0
100%
0.0
RPL10.MCUP.LP1.1760 RPL10.MCUP.Loop 1 - Tie-in Mechanical #3 WBS Summary Tie-in Mechanical #3 Complete 02/17/26 04/15/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP1.1880 RPL10.MCUP.Loop 1 - Tie-in Mechanical #5 WBS Summary Tie-in Mechanical #5 Complete 02/17/26 04/17/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP1.2580 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #1 Tie-in Mechanical #1 Complete 02/17/26 04/15/26 13.8 0.0
100%
0.0
RPL10.MCUP.LP1.2600 RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #1 Tie-in Mechanical #1 Complete 02/17/26 04/15/26 13.8 0.0
100%
0.0
RPL10.MCUP.LP1.2620 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #3 Tie-in Mechanical #3 Complete 02/17/26 04/15/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP1.2640 RPL10.MCUP.Loop 1 - Condenser Water Tie-in Mechanical #3 Tie-in Mechanical #3 Complete 02/17/26 04/15/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP1.2660 RPL10.MCUP.Loop 1 - Facility Water Tie-in Mechanical #5 Tie-in Mechanical #5 Complete 02/17/26 04/15/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP1.2680 RPL10.MCUP.Loop 1 - Condenser Tie-in Mechanical #5 Tie-in Mechanical #5 Complete 02/17/26 04/17/26 11.2 0.0
100%
0.0
RPL10.MCUP.LP2.2300 RPL10.MCUP.Loop 2 - Set mCup #8 - Dry Coolers (6) (4 per week) OFE Complete 02/17/26 02/19/26 7.5 0.0
100%
0.0
RPL.10.D.X3870.XG Ready for MV Cable Pull NS 4 (Loop 1) Give Milestones (XREFs) Complete 02/18/26 02/18/26 0.0 0.0
100%
0.0
RPL.10.D.X3875.XG Ready for MV Cable Pull NS 4 (Loop 2) Give Milestones (XREFs) Complete 02/18/26 02/18/26 0.0 0.0
100%
0.0
RPL10.CFCI.7080 RPL10 - Submittal Rvw/App'l - Scuppers Fixed Louvers Complete 02/18/26 03/18/26 12.5 0.0
100%
0.0
RPL10.EY.NS2.01170 RPL10.EY.NS2 - Install Tent Fit-out Tent and Temp Conditions Complete 02/18/26 03/30/26 25.0 0.0
100%
0.0
RPL10.INT.CTRC.01200 RPL10.Interior.Center-Corridor - OFE - NS2 (1x GS.IDF) N23 (02.18.26) OFE Complete 02/18/26 02/24/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02420 RPL10.Interior.NS2 - Priority - Install Temp Doors Frame Hardware OverHead Complete 02/18/26 02/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.04200 RPL10.Interior.SSB - Priority - P5 Backing Remaining Wall Priority Wall (P5) - Grid Line 10-C Complete 02/18/26 02/25/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.06960 RPL10.Interior.SSB - BoW - Hang Drywall, Tape Float Paint (Early Work) Balance of Walls and OverHead Complete 02/18/26 03/13/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01060 RPL10.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) (02.18.26) OFE Complete 02/18/26 02/20/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.01100 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall Balance of Walls & OverHead Complete 02/18/26 03/11/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01120 RPL10.Interior.SSB-Corridor - BoW - Controls / EPMS / BMS OH and In-Wall Balance of Walls & OverHead Complete 02/18/26 03/09/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.01130 RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Lowside OH and In-Wall Balance of Walls & OverHead Complete 02/18/26 03/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.02640 RPL10.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & OverHead Complete 02/18/26 03/09/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01140 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-10/10-1 (11) (with temp closures for openings) South Complete 02/18/26 02/27/26 5.0 0.0
100%
0.0
RPL10.STR.NS43.01130 RPL10.Structure.NS43 - SOG F/R/P (Pour #23 -02/05 & #24 -02/07) - Grid Lines 10-04/10-01 F/R/P Complete 02/18/26 02/20/26 5.0 0.0
100%
0.0
NW.1280 Dry Cooler 230 Ton Crane Movement 04 - Finish 230 Ton Crane (Dry Cooler) Complete 02/19/26 02/19/26 0.0 0.0
100%
0.0
RPL10.EY.NS3.01130 RPL10.EY.NS3 - Cure (High Early Mix) Foundations Complete 02/19/26 02/20/26 8.8 0.0
100%
0.0
RPL10.EY.NS4.01120 RPL10.EY.NS4 - Cure (High Early Mix) Foundations Complete 02/19/26 02/20/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.01130 RPL10.Interior.Center-Corridor - OFE - NS1 (1x GS.IDF) N13 (02.18.26) OFE Complete 02/19/26 02/25/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.02300 RPL10.Interior.NS4 - Priority - Install IMP Exterior In-Wall Rough-Ins OverHead Complete 02/19/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.04140 RPL10.Interior.SSB - Priority - P5 MEP Remaining Wall In-wall Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 02/27/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.04220 RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (South) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 03/09/26 4.0 0.0
100%
0.0
RPL10.INT.SSB.06940 RPL10.Interior.SSB - Priority - P5 Frame Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 02/23/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.06980 RPL10.Interior.SSB - Priority - P5 One Side Drywall Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 02/19/26 03/09/26 4.0 0.0
100%
0.0
RPL10.MCUP.LP1.1680 RPL10.MCUP.Loop 1 - Set Electrical Skids #7 OFE Complete 02/19/26 02/19/26 1.2 0.0
100%
0.0
NW.1300 Dry Cooler 230 Ton Crane Demobilization 230 Ton Crane (Dry Cooler) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X2110.XG Trestle Construction Ready - East - RPL10 Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X3750.XG RMUs/MV Skids Set - mCUP North Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL.10.D.X3890.XG Ready for MV Cable Pull mCUP North Loop (Loop#1) Give Milestones (XREFs) Complete 02/20/26 02/20/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.01190 RPL10.Interior.Center-Corridor - OFE - EF1 (1x GS.IDF) NE1 (02.18.26) OFE Complete 02/20/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06880 RPL10.Interior.Center-Corridor - Priority - QC - P3 Wall - Backing/In-Wall Priority Wall (P3) - Grid Line 10-25 Complete 02/20/26 02/23/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.06900 RPL10.Interior.Center-Corridor - Priority - P6 Frame Remaining Wall Priority Wall (P6) - Grid Line 10-16 Complete 02/20/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01050 RPL10.Interior.NS2 - Priority - Install FA / Linear heat detection OverHead Complete 02/20/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02400 RPL10.Interior.NS2 - Priority - Install Fire Life Safety (Sprinkler Drops) OverHead Complete 02/20/26 03/09/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.01040 RPL10.Interior.NS3 - Priority - Install Temp Lighting OverHead Complete 02/20/26 03/06/26 3.8 0.0
100%
0.0
RPL10.INT.NS4.01040 RPL10.Interior.NS4 - Priority - Install Temp Lighting OverHead Complete 02/20/26 03/06/26 3.8 0.0
100%
0.0
RPL10.INT.SSBC.01110 RPL10.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-Wall Balance of Walls & OverHead Complete 02/20/26 03/09/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP1.2560 RPL10.MCUP.Loop 1 - Set Remaining Facility water piping rack with All Racks Welding OFE Complete 02/20/26 04/15/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.1380 RPL10.MCUP.Loop 2 - Cure for Remaining Electrical Pads Foundations Complete 02/20/26 03/04/26 8.8 0.0
100%
0.0
RPL10.STR.NS43.01140 RPL10.Structure.NS43 - Zone SOG Cure F/R/P Complete 02/20/26 02/26/26 8.8 0.0
100%
0.0
GCD.RPL10.3727 [RPL10] TC Ready: All General Services [RPL10-MDFs] TC Ready: General Services Complete 02/23/26 02/23/26 0.0 0.0
100%
0.0
RPL10.CFCI.4620 RPL10 - Prep / Submit for Review -Epoxy Flooring (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Complete 02/23/26 03/31/26 25.0 0.0
100%
0.0
RPL10.CFCI.4810 RPL10 - Prep / Submit for Review - Specialities (CFCI) Div. 10 - Specialities Active 02/23/26 04/27/26 25.0 1.2
0%
147.5
RPL10.EY.NS4.01050 RPL10.EY.NS4 - Install Tent F/R/P SOG (30k Mock Up) Tent and Temp Conditions Complete 02/23/26 02/26/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01060 RPL10.Interior.NS12 - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Complete 02/23/26 02/24/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01090 RPL10.Interior.NS12 - Temp Conditions - Install Early Temp Conditions Temp Conditions Complete 02/23/26 02/24/26 2.5 0.0
100%
0.0
RPL10.INT.NS1.01110 RPL10.Interior.NS1 - Priority - Install Electrical **to clarify scope OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01160 RPL10.Interior.NS1 - OFE - WBS Summary OFE Active 02/23/26 08/05/26 143.8 88.8
0%
-5.0
RPL10.INT.NS1.02380 RPL10.Interior.NS1 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 02/23/26 03/09/26 12.5 0.0
100%
0.0
RPL10.INT.NS2.01010 RPL10.Interior.NS2 - Priority - Install Duct OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01080 RPL10.Interior.NS2 - OFE - WBS Summary OFE Active 02/23/26 08/27/26 163.8 108.8
0%
-18.8
RPL10.INT.NS2.02330 RPL10.Interior.NS2 - Priority - Exterior Wall Tape, Float and Paint NS2 (sanding off hours) *02/23 OverHead Complete 02/23/26 02/27/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.02425 RPL10.Interior.NS2 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 02/23/26 03/09/26 12.5 0.0
100%
0.0
RPL10.INT.NS3.01980 RPL10.Interior.NS3 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/23/26 03/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.02300 RPL10.Interior.NS3 - Priority - Install IMP Exterior In-Wall Rough-Ins OverHead Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01980 RPL10.Interior.NS4 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall OverHead Complete 02/23/26 03/23/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1280 RPL10.MCUP.Loop 2 - Set mCUPs #2 (1 per 5 days) OFE Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL10.STR.NS12.01180 RPL10.Structure.NS1 - Install SOG Joint Sealant & Floor Sealer F/R/P Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
GCD.RPL10.5945 Temporary Conditioning Achieved in NS1 Construction Milestones Complete 02/24/26 02/24/26 0.0 0.0
100%
0.0