Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
94
Completed
6
In Progress
94
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SKN.NS12.01070 RPL10.SKIN.NS12 - Install Roof System - Exterior Wall Sheething and EJ Roofing Complete 01/07/26 01/13/26 2.5 0.0
100%
0.0
RPL10.SKN.NS12.01080 RPL10.SKIN.NS12 - Install Roof System - WBS Summary Roofing Complete 01/07/26 03/18/26 56.2 0.0
100%
0.0
RPL10.SKN.NS12.01100 RPL10.SKIN.NS12 - Install Roof System - DenseDeck & Peel & Stick Roofing Complete 01/07/26 02/13/26 6.2 0.0
100%
0.0
RPL10.STR.NS12.01120 RPL10.Structure.NS12 - SOG F/R/P (Pour #10 -01/06 & #11 -01/08) - Grid lines 10-27/10-24 F/R/P Complete 01/07/26 01/09/26 3.8 0.0
100%
0.0
RPL10.MCUP.FWM.01010 RPL10.MCUP.FWM - Install FWM FWM Complete 01/08/26 01/09/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1180 RPL10.MCUP.Loop 1 - Cure for Pads Foundations Complete 01/08/26 01/18/26 8.8 0.0
100%
0.0
RPL10.SKN.NS12.01280 RPL10.SKIN.NS12 - Weather Event 01/08 (Flash Rain) Roofing Weather Impact 10-30 / 10-20 Complete 01/08/26 01/08/26 2.5 0.0
100%
0.0
RPL10.SKN.SSB.01330 RPL10.SKIN.SSB - PSI DPR Request for Recovery Schedule Again Roofing Remediation 10-42 / 10-30 Complete 01/08/26 01/21/26 1.2 0.0
100%
0.0
NW.1180 Dry Cooler 230 Ton Crane Movement 02 - Start 230 Ton Crane (Dry Cooler) Complete 01/09/26 01/09/26 0.0 0.0
100%
0.0
RPL10.CFCI.5090 RPL10 - Fabricate / Deliver - Fire Alarm (CFCI) Div. 26 - Fire Alarm Complete 01/09/26 01/30/26 0.0 0.0
100%
0.0
RPL10.INT.SSB.01060 RPL10.Interior.SSB - Balance of Walls and Overheads - WBS Summary Balance of Walls and OverHead Active 01/09/26 09/02/26 197.5 113.8
0%
126.2
RPL10.INT.SSB.03400 RPL10.Interior.SSB - Priority - Install Drywall at Exterior Walls Priority Walls and OverHead Complete 01/09/26 01/13/26 12.5 0.0
100%
0.0
RPL10.INT.SSB.04020 RPL10.Interior.SSB - Priority - P5 Frame Pony Walls Priority Wall (P5) - Grid Line 10-C Complete 01/09/26 01/14/26 3.0 0.0
100%
0.0
RPL10.INT.SSB.04320 RPL10.Interior.SSB - BoW - Frame Pony Walls Balance of Walls and OverHead Complete 01/09/26 01/16/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03520 RPL10.Interior.SSB-Corridor - Priority - Install Hang/Tape/Float/ Paint @ GS.MDF wall location Priority Walls & OverHead Complete 01/09/26 01/22/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.1320 RPL10.MCUP.Loop 1 - Set mCup #5 - Dry Coolers (6) (4 per week) OFE Complete 01/09/26 01/13/26 8.8 0.0
100%
0.0
RPL10.SKN.NS12.01220 RPL10.SKIN.NS12 - WI Removing Vapor Barrier/Dense Deck Roofing Weather Impact 10-30 / 10-20 Complete 01/09/26 01/09/26 2.5 0.0
100%
0.0
RPL10.SKN.NS12.01240 RPL10.SKIN.NS12 - WI Replacing Vapor Barrier/Dense Deck Roofing Weather Impact 10-30 / 10-20 Complete 01/09/26 01/09/26 1.2 0.0
100%
0.0
RPL10.STR.NS43.01030 RPL10.Structure.NS43 - Install Decking & Detailing turnover #11 - Grid lines 10-10/10-07 Steel and Decking Complete 01/09/26 01/13/26 3.8 0.0
100%
0.0
JCL.C.1300 RPL10 - Cost Risk LOE-16 Fire Alarm Systems Cost LOEs Active 01/12/26 02/12/27 315.0 251.2
0%
73.8
PRE.FA.1200 Glass / Glazing - Final Agreement Trade Partner Final Agreement Complete 01/12/26 01/12/26 0.0 0.0
100%
0.0
RPL10.EY.NS1.01015 RPL10.EY.NS1 - Install F/R/P Equipment Pads - 9-15 (Grid 10-32/10-42) (12'' Larger For Tolerance) Foundations Complete 01/12/26 01/19/26 27.5 0.0
100%
0.0
RPL10.INT.CTRC.01000 RPL10.Interior.Center-Corridor - Install Priority Walls and OverHead - WBS Summary Priority Walls & OverHead Active 01/12/26 04/29/26 90.0 3.8
0%
125.0
RPL10.INT.CTRC.01020 RPL10.Interior.Center-Corridor - Install Priority OH, Walls, Fitout and Build Back - WBS Summary Center Corridor Active 01/12/26 07/24/26 168.8 78.8
0%
150.0
RPL10.INT.CTRC.01040 RPL10.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) Priority Walls & OverHead Complete 01/12/26 01/14/26 3.8 0.0
100%
0.0
RPL10.INT.NS1.01030 RPL10.Interior.NS1 - Priority - Install Fire Sprinkler OverHead Complete 01/12/26 01/16/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01030 RPL10.Interior.NS2 - Priority - Install Fire Sprinkler OverHead Complete 01/12/26 01/16/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01110 RPL10.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) Priority Walls and OverHead Complete 01/12/26 01/21/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.01660 RPL10.Interior.SSB - Priority - Install Plumbing (Highside OH space) - (LOE due to WI) Priority Walls and OverHead Complete 01/12/26 02/25/26 12.5 0.0
100%
0.0
RPL10.INT.SSB.06900 RPL10.Interior.SSB - Priority - Install Plumbing (Highside OH space) - (Pre WI#08) Priority Walls and OverHead Complete 01/12/26 01/23/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.02460 RPL10.Interior.SSB-Corridor - Priority - Install Backing Exterior Wall Priority Walls & OverHead Complete 01/12/26 01/16/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03620 RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall - (LOE due to WI) Priority Walls & OverHead Complete 01/12/26 03/02/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03800 RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall - (Pre WI#08) Priority Walls & OverHead Complete 01/12/26 01/23/26 10.0 0.0
100%
0.0
RPL10.MCUP.LP1.2300 RPL10.MCUP.Loop 1 - Set mCup #7 - Dry Coolers (6) (4 per week) OFE Complete 01/12/26 01/14/26 10.0 0.0
100%
0.0
RPL10.MCUP.LP1.2380 RPL10.MCUP.Loop 1 - Set mCup #7 Facility water piping rack - (LOE due to WI) OFE Complete 01/12/26 02/02/26 12.5 0.0
100%
0.0
RPL10.MCUP.LP1.2460 RPL10.MCUP.Loop 1 - F/R/P Pads for MVS Pad Foundations Complete 01/12/26 01/15/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP1.2520 RPL10.MCUP.Loop 1 - Set mCup #7 Facility water piping rack - (Pre WI#08) OFE Complete 01/12/26 01/23/26 12.5 0.0
100%
0.0
RPL10.STR.NS12.01130 RPL10.Structure.NS12 - SOG F/R/P (Pour #12 -01/10 & #13 -01/13) - Grid lines 10-24/10-20 F/R/P Complete 01/12/26 01/14/26 2.5 0.0
100%
0.0
RPL10.INT.CTRC.07080 RPL10.Interior.Center-Corridor - Priority - P3 Frame Soffit and Hang Drywall Priority Wall (P3) - Grid Line 10-25 Complete 01/13/26 01/19/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.04340 RPL10.Interior.SSB - BoW - Hang Drywall Pony Wall (both sides) Balance of Walls and OverHead Complete 01/13/26 01/22/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01050 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-30/10-20(5)(with temp closures for openings) South Complete 01/13/26 01/14/26 2.5 0.0
100%
0.0
GCD.RPL10.1320 Steel Complete - RPL10 Construction Milestones Complete 01/14/26 01/14/26 0.0 0.0
100%
0.0
RPL10.EY.NS1.01050 RPL10.EY.NS1 - Install Tent F/R/P SOG (30k Mock Up) - Changed as LOE due to WI#07 Tent and Temp Conditions Complete 01/14/26 01/23/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01640 RPL10.EY.NS1 - Install Tent F/R/P SOG (Pre WI#07) Tent and Temp Conditions Complete 01/14/26 01/20/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.01011 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) - (LOE due to WI) Priority Walls & OverHead Complete 01/14/26 02/13/26 18.8 0.0
100%
0.0
RPL10.INT.SSBC.03840 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-A/10-C) - (Pre WI#08) Priority Walls & OverHead Complete 01/14/26 01/23/26 18.8 0.0
100%
0.0
RPL10.SKN.EF12.01010 RPL10.SKIN.EF12 - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary EF1 & EF2 Active 01/14/26 07/24/26 166.2 22.5
0%
235.0
RPL10.SKN.EF12.01070 RPL10.SKIN.EF12 - Install Roof System - Exterior Wall Sheething and EJ Roofing Complete 01/14/26 01/15/26 2.5 0.0
100%
0.0
RPL10.SKN.EF12.01080 RPL10.SKIN.EF12 - Install Roof System - WBS Summary Roofing Complete 01/14/26 03/27/26 65.0 0.0
100%
0.0
RPL10.SKN.EF12.01100 RPL10.SKIN.EF12 - Install Roof System - DenseDeck & Peel & Stick Roofing Complete 01/14/26 02/06/26 6.2 0.0
100%
0.0
RPL10.SKN.S.01060 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-20/10-10 (8) (with temp closures for openings) South Complete 01/14/26 01/16/26 2.5 0.0
100%
0.0
RPL10.STR.NS43.01040 RPL10.Structure.NS43 - Install Decking & Detailing turnover #12 - Grid lines 10-07/10-04 Steel and Decking Complete 01/14/26 01/20/26 3.8 0.0
100%
0.0
NW.1200 Dry Cooler 230 Ton Crane Movement 02 - Finish 230 Ton Crane (Dry Cooler) Complete 01/15/26 01/15/26 0.0 0.0
100%
0.0
NW.1860 Steel Crane #1 Demobilzation Steel Crane #1 Complete 01/15/26 01/15/26 0.0 0.0
100%
0.0
NW.1880 Steel Crane #2 Demobilization Steel Crane #2 Complete 01/15/26 01/15/26 0.0 0.0
100%
0.0
RPL10.INT.NS1.02340 RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (LOE due to WI) OverHead Complete 01/15/26 02/27/26 15.0 0.0
100%
0.0
RPL10.INT.NS1.03020 RPL10.Interior.NS1 - Priority - Install Draft Curtains (#4) - (Pre WI#08) OverHead Complete 01/15/26 01/23/26 15.0 0.0
100%
0.0
RPL10.INT.NS2.02000 RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (LOE due to WI) OverHead Complete 01/15/26 02/27/26 15.0 0.0
100%
0.0
RPL10.INT.NS2.03105 RPL10.Interior.NS2 - Priority - Install Draft Curtains (#4) - (Pre WI#08) OverHead Complete 01/15/26 01/23/26 15.0 0.0
100%
0.0
RPL10.INT.SSB.04060 RPL10.Interior.SSB - Priority - P5 Hang Drywall Pony Wall (both sides) Priority Wall (P5) - Grid Line 10-C Complete 01/15/26 01/21/26 4.0 0.0
100%
0.0
RPL10.SKN.NS12.01260 RPL10.SKIN.NS12 - WI Inspection Vapor Barrier/Dense Deck Roofing Weather Impact 10-30 / 10-20 Complete 01/15/26 01/15/26 1.2 0.0
100%
0.0
RPL10.STR.EF12.01100 RPL10.Structure.EF12 - SOG F/R/P (Pour #14 -01/15) - Grid lines 10-20/10-17 F/R/P Complete 01/15/26 01/16/26 2.5 0.0
100%
0.0
RPL10.STR.EF12.01110 RPL10.Structure.EF12 - SOG F/R/P - WBS Summary F/R/P Complete 01/15/26 03/21/26 58.8 0.0
100%
0.0
RPL10.STR.NS12.01140 RPL10.Structure.NS12 - Zone SOG Cure F/R/P Complete 01/15/26 01/21/26 8.8 0.0
100%
0.0
RPL10.CFCI.3890 RPL10 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) (CFCI) Div. 22 - Plumbing Complete 01/16/26 01/26/26 25.0 0.0
100%
0.0
RPL10.CFCI.7040 RPL10 - Fabricate / Deliver - Mechanical Piping Valve Delivery (CFCI) Div. 22 - Plumbing Complete 01/16/26 03/24/26 25.0 0.0
100%
0.0
RPL10.INT.CTRC.06740 RPL10.Interior.Center-Corridor - Priority - P3 Frame Remaining Wall Priority Wall (P3) - Grid Line 10-25 Complete 01/16/26 01/21/26 3.8 0.0
100%
0.0
RPL10.INT.CTRC.07100 RPL10.Interior.Center-Corridor - Priority - P3 Soffit Tape, Float and Paint, Fire Safing Both Sides Priority Wall (P3) - Grid Line 10-25 Complete 01/16/26 01/22/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2480 RPL10.MCUP.Loop 1 - Cure for MVS Pad Foundations Complete 01/16/26 01/18/26 6.2 0.0
100%
0.0
RPL10.SKN.01280 RPL10.SKIN - PSI Started Install IMP EJ - Grid lines 10-31/30 Install Bent Plate & Gusset Plates (Pre WI#08) Expansion Joint Delay Event Complete 01/16/26 01/23/26 1.2 0.0
100%
0.0
ICM.B10.1875 [NWB] Delivery of mCUP Skids (First Delivery) - RPL10 Construction Complete 01/19/26 01/19/26 0.0 0.0
100%
0.0
RPL10.MCUP.FWM.01000 RPL10.MCUP.FWM - Install PTX FWM Complete 01/19/26 01/19/26 5.0 0.0
100%
0.0
RPL10.MCUP.FWM.01030 RPL10.MCUP.FWM - Install MVS FWM Complete 01/19/26 01/19/26 5.0 0.0
100%
0.0
GCD.RPL10.1182 Start mCUP Unit Set-In-Place - RPL10 Construction Milestones Complete 01/20/26 01/20/26 0.0 0.0
100%
0.0
NW.1000 MCUP 600 Ton Crane Mobilization 600 Ton Crane (MCUP) Complete 01/20/26 01/20/26 0.0 0.0
100%
0.0
NW.1020 MCUP 600 Ton Crane Movement 1 600 Ton Crane (MCUP) Complete 01/20/26 01/20/26 0.0 0.0
100%
0.0
RPL10.EY.NS1.01130 RPL10.EY.NS1 - Cure (High Early Mix) Foundations Complete 01/20/26 01/23/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.01520 RPL10.Interior.Center-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) All Corridor Wall (LOE) Priority Walls & OverHead Complete 01/20/26 02/20/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01670 RPL10.Interior.Center-Corridor - Priority - Frame Priority Soffit and Hang Drywall (All CC & EF) ***Duration(LOE) Priority Walls & OverHead Complete 01/20/26 02/16/26 18.8 0.0
100%
0.0
RPL10.INT.CTRC.07180 RPL10.Interior.Center-Corridor - Priority - Frame Priority Soffit and Hang Drywall (All CC & EF) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 18.8 0.0
100%
0.0
RPL10.INT.CTRC.07300 RPL10.Interior.Center-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02140 RPL10.Interior.NS1 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall (LOE) OverHead Complete 01/20/26 02/02/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.03100 RPL10.Interior.NS1 - Priority - Install Layout, Unistruts & Hangers - (Pre WI#08) OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01980 RPL10.Interior.NS2 - Priority - Install Layout, Unistruts & Hangers (All Trades) Both Side Of Corridor Wall(LOE) OverHead Complete 01/20/26 02/02/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.02320 RPL10.Interior.NS2 - Priority - Install Drywall at Exterior Wall - (LOE due to WI) OverHead Complete 01/20/26 02/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03145 RPL10.Interior.NS2 - Priority - Install Drywall at Exterior Wall - (Pre WI#08) OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.03225 RPL10.Interior.NS2 - Priority - Install Layout, Unistruts & Hangers (All Trades) - (Pre WI#08) OverHead Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.04080 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Pony Wall (both sides) - (LOE due to WI) Priority Wall (P5) - Grid Line 10-C Complete 01/20/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.04360 RPL10.Interior.SSB - BoW - Tape Float Paint Pony Wall (both sides) - (LOE due to WI) Balance of Walls and OverHead Complete 01/20/26 02/02/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06780 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Pony Wall (both sides) (Pre WI#08) Priority Wall (P5) - Grid Line 10-C Complete 01/20/26 01/23/26 6.0 0.0
100%
0.0
RPL10.INT.SSB.06860 RPL10.Interior.SSB - BoW - Tape Float Paint Pony Wall (both sides) - (Pre WI#08) Balance of Walls and OverHead Complete 01/20/26 01/23/26 6.0 0.0
100%
0.0
RPL10.INT.SSBC.01012 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) - (LOE due to WI) Priority Walls & OverHead Complete 01/20/26 02/20/26 18.8 0.0
100%
0.0
RPL10.INT.SSBC.02180 RPL10.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) - (LOE due to WI) Priority Walls & OverHead Complete 01/20/26 02/09/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03120 RPL10.Interior.SSB-Corridor - Priority - P2 Wall MEP Backing/In-Wall Rough Ins - (LOE due to WI) Priority Wall (P2) - Grid Line 10-38 Complete 01/20/26 02/12/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03720 RPL10.Interior.SSB-Corridor - Priority - P2 Wall MEP Backing/In-Wall Rough Ins - (Pre WI#08) Priority Wall (P2) - Grid Line 10-38 Complete 01/20/26 01/23/26 10.0 0.0
100%
0.0
RPL10.INT.SSBC.03880 RPL10.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 12.5 0.0
100%
0.0
RPL10.INT.SSBC.03920 RPL10.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (Grid 10-C/10-F) - (Pre WI#08) Priority Walls & OverHead Complete 01/20/26 01/23/26 18.8 0.0
100%
0.0
RPL10.MCUP.LP1.1340 RPL10.MCUP.Loop 1 - Set mCUPs #1 (1 per 5 days) (01.05.26) OFE Complete 01/20/26 01/23/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1200 RPL10.MCUP.Loop 2 - OFE - WBS Summary OFE Active 01/20/26 05/15/26 83.8 18.8
0%
142.5
RPL10.MCUP.LP2.2320 RPL10.MCUP.Loop 2 - Set mCup #2 Facility water piping rack - (LOE due to WI) OFE Complete 01/20/26 02/02/26 15.0 0.0
100%
0.0