Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
97
Completed
3
In Progress
97
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SKIN.01000 RPL10.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary Skin Active 11/19/25 01/20/27 361.2 230.0
0%
121.2
RPL10.SKN.S.01000 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-41/10-42(1) (with temp closures for openings) South Complete 11/19/25 11/19/25 1.2 0.0
100%
0.0
RPL10.SKN.S.01010 RPL10.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary South Complete 11/19/25 03/11/26 100.0 0.0
100%
0.0
NW.1740 IMP Crane #1 Movement 02 IMP Crane #1 Complete 11/20/25 11/20/25 0.0 0.0
100%
0.0
RPL10.MCUP.LP1.1020 RPL10.MCUP.Loop 1 - Install Foundations - WBS Summary Foundations Complete 11/20/25 01/18/26 48.8 0.0
100%
0.0
RPL10.MCUP.LP1.1100 RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Pre WI#04) Foundations Complete 11/20/25 11/24/25 25.0 0.0
100%
0.0
RPL10.SKN.E.01000 RPL10.SKIN.East - Install IMP Flashing,Panels & Caulking - Grid lines 10F/10A(2) (with temp closures for openings) East Complete 11/20/25 11/21/25 2.5 0.0
100%
0.0
RPL10.SKN.E.01010 RPL10.SKIN.East - Install IMP Insulated Metal Panels System - WBS Summary East Complete 11/20/25 02/13/26 71.2 0.0
100%
0.0
RPL10.STR.SSB.01120 RPL10.Structure.SSB - Install AB final grade and Vapor Barrier Prep Complete 11/20/25 11/24/25 6.2 0.0
100%
0.0
NW.2000 111925 - Non Weather Impact #1 - NS1 & NS2 MV Skid Foundation Demolition Project Impacts Complete 11/21/25 12/05/25 7.5 0.0
100%
0.0
RPL10.CFCI.4610 RPL10 - Prep / Submit for Review - Interior Painting (Spec 09 91 23) (CFCI) Div. 09 - Painting Complete 11/21/25 01/23/26 25.0 0.0
100%
0.0
RPL10.STR.SSB.01090 RPL10.Structure.SSB - Install Decking & Detailing turnover #4 - Grid lines 10-33/10-30 Steel and Decking Complete 11/21/25 11/26/25 2.5 0.0
100%
0.0
NW.1780 IMP Crane #1 Movement 03 IMP Crane #1 Complete 11/24/25 11/24/25 0.0 0.0
100%
0.0
RPL.CM.D.C5660.XR Wayward Path Logistics - Onsite Receive XREF Milestones Complete 11/24/25 11/24/25 0.0 0.0
100%
0.0
RPL10.EY.NS2.01000 RPL10.EY.NS2 - Install Shallow Tent UG (Pre WI#04) Tent and Temp Conditions Complete 11/24/25 11/24/25 3.8 0.0
100%
0.0
RPL10.EY.NS2.01060 RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Pre WI#04) Underground Complete 11/24/25 11/24/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01540 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Pre WI#04) Foundations Complete 11/24/25 11/24/25 6.2 0.0
100%
0.0
RPL10.EY.NS4.01010 RPL10.EY.NS4 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) (12'' Larger For Tolerance) - (LOE due to WI) Foundations Complete 11/24/25 02/18/26 18.8 0.0
100%
0.0
RPL10.EY.NS4.01020 RPL10.EY.NS4 - Install Foundations - WBS Summary Foundations Complete 11/24/25 02/20/26 105.0 0.0
100%
0.0
RPL10.EY.NS4.01550 RPL10.EY.NS4 - Install F/R/P Equipment Pads - 1-8 (Grid 10-16/10-09) - (Pre WI#08) Foundations Complete 11/24/25 01/23/26 18.8 0.0
100%
0.0
RPL10.SKN.N.01000 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Pre WI #04) North Complete 11/24/25 11/24/25 2.5 0.0
100%
0.0
RPL10.SKN.N.01010 RPL10.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary North Complete 11/24/25 02/13/26 66.2 0.0
100%
0.0
RPL10.VDC.4520 RPL10.BIM TIER 2 - 4 - Shops/Model Revise Resubmit TIER 2 - 4 Complete 11/24/25 12/12/25 18.8 0.0
100%
0.0
NW.2020 Weather Event #4 - 11/25/25 Project Impacts Complete 11/25/25 11/25/25 1.2 0.0
100%
0.0
RPL10.CFCI.4140 RPL10 - Fabricate / Deliver - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Complete 11/25/25 02/23/26 63.8 0.0
100%
0.0
RPL10.CFCI.4190 RPL10 - Fabricate / Deliver - Fire Suppression (CFCI) Div. 21 - Fire Suppression Complete 11/25/25 12/09/25 13.8 0.0
100%
0.0
GCD.RPL10.1500 Start Slab-On-Grade Concrete - RPL10 Construction Milestones Complete 11/26/25 11/26/25 0.0 0.0
100%
0.0
RPL10.CFCI.3900 RPL10 - Fabricate / Deliver - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Complete 11/26/25 12/05/25 11.2 0.0
100%
0.0
RPL10.CFCI.6740 RPL10 - Prep / Submit for Review -Cable Tray (CFCI) Div. 26 - Power Equip. & Material Complete 11/26/25 12/02/25 25.0 0.0
100%
0.0
RPL10.EY.EF2.01710 RPL10.EY.EF2 - Install Mechanical UG (Post WI#04) (Pre WI#08) Underground Complete 11/26/25 01/23/26 12.5 0.0
100%
0.0
RPL10.EY.NS1.01000 RPL10.EY.NS1 - Install Shallow Tent UG (Pre WI#05) Tent and Temp Conditions Complete 11/26/25 11/26/25 3.8 0.0
100%
0.0
RPL10.EY.NS1.01540 RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (WI#04-Start) (Pre WI#05) Foundations Complete 11/26/25 11/26/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01560 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#04) (Pre WI#05) Foundations Complete 11/26/25 11/26/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01600 RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#04) (Pre WI#05) Underground Complete 11/26/25 11/26/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01640 RPL10.EY.NS2 - Install Shallow Tent UG (Post WI#04) (Pre WI#05) Tent and Temp Conditions Complete 11/26/25 11/26/25 3.8 0.0
100%
0.0
RPL10.EY.SSB.01020 RPL10.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary SSB Active 11/26/25 12/03/26 308.8 191.2
0%
317.5
RPL10.EY.SSB.01040 RPL10.EY.SSB - Install Electrical UG (Pre WI#05) Underground Complete 11/26/25 11/26/25 6.2 0.0
100%
0.0
RPL10.EY.SSB.01060 RPL10.EY.SSB - Install UG Utilities - WBS Summary Underground Complete 11/26/25 01/20/26 33.8 0.0
100%
0.0
RPL10.MCUP.LP1.2400 RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#04) (Pre WI#05) Foundations Complete 11/26/25 11/26/25 25.0 0.0
100%
0.0
RPL10.SKN.N.01160 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #04) (Pre WI#05) North Complete 11/26/25 11/26/25 1.2 0.0
100%
0.0
RPL10.STR.NS12.01200 RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#04) (Pre WI#05) Steel and Decking Complete 11/26/25 11/26/25 2.5 0.0
100%
0.0
RPL10.STR.SSB.01140 RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Trigger Int Wall) (Pre WI#05) F/R/P Complete 11/26/25 11/26/25 6.2 0.0
100%
0.0
RPL10.STR.SSB.01150 RPL10.Structure.SSB - SOG F/R/P - WBS Summary F/R/P Complete 11/26/25 03/06/26 80.0 0.0
100%
0.0
NW.2040 Weather Event #5 - 12/01/25 Project Impacts Complete 12/01/25 12/01/25 1.2 0.0
100%
0.0
RPL10.EY.NS3.01015 RPL10.EY.NS3 - Install F/R/P Equipment Pads - 9-16 (Grid 10-09/10-01) (12'' Larger For Tolerance) Foundations Complete 12/01/25 12/08/25 18.8 0.0
100%
0.0
RPL10.EY.EF1.01500 RPL10.EY.EF1 - Install Mechanical UG (Post WI#04) (Pre WI#06) Underground Complete 12/02/25 12/03/25 1.2 0.0
100%
0.0
RPL10.EY.NS1.01560 RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Post WI#05) (Pre WI#06) Foundations Complete 12/02/25 12/03/25 6.2 0.0
100%
0.0
RPL10.EY.NS1.01580 RPL10.EY.NS1 - Install Shallow Tent UG (Post WI#05) (Pre WI#06) Tent and Temp Conditions Complete 12/02/25 12/03/25 3.8 0.0
100%
0.0
RPL10.EY.NS1.01620 RPL10.EY.NS1 - Install Shallow Tent UG (Post WI#06) Tent and Temp Conditions Complete 12/02/25 12/08/25 3.8 0.0
100%
0.0
RPL10.EY.NS2.01100 RPL10.EY.NS2 - Install Mechanical UG (Pre WI#06) Underground Complete 12/02/25 12/03/25 12.5 0.0
100%
0.0
RPL10.EY.NS2.01580 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#05) (Pre WI#06) Foundations Complete 12/02/25 12/03/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01620 RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#05) (Pre WI#06) Underground Complete 12/02/25 12/03/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01660 RPL10.EY.NS2 - Install Shallow Tent UG (Post WI#05) Tent and Temp Conditions Complete 12/02/25 12/03/25 3.8 0.0
100%
0.0
RPL10.EY.SSB.01380 RPL10.EY.SSB - Install Electrical UG (Post WI#05) (Pre WI#06) Underground Complete 12/02/25 12/03/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2420 RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#05) (Pre WI#06) Foundations Complete 12/02/25 12/03/25 25.0 0.0
100%
0.0
RPL10.SKN.N.01180 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #05) (Pre WI#06) North Complete 12/02/25 12/03/25 1.2 0.0
100%
0.0
RPL10.STR.NS12.01030 RPL10.Structure.NS12 - Install Decking & Detailing turnover #5 - Grid lines 10-30/10-27 (WI#05 to Start)(Pre WI#06) Steel and Decking Complete 12/02/25 12/03/25 3.8 0.0
100%
0.0
RPL10.STR.NS12.01220 RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#05) (Pre WI#06) Steel and Decking Complete 12/02/25 12/03/25 2.5 0.0
100%
0.0
RPL10.STR.SSB.01250 RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Post WI#05) (Pre WI#06) F/R/P Complete 12/02/25 12/03/25 6.2 0.0
100%
0.0
RPL10.VDC.4500 RPL10.BIM TIER 2 - 4 - Finalize Model TIER 2 - 4 Complete 12/02/25 12/05/25 18.8 0.0
100%
0.0
RPL10.CFCI.6760 RPL10 - Submittal Rvw/App'l - Cable Tray (CFCI) Div. 26 - Power Equip. & Material Complete 12/03/25 12/16/25 12.5 0.0
100%
0.0
RPL10.EY.NS4.01015 RPL10.EY.NS4 - Install F/R/P Equipment Pads - 9-16 (Grid 10-09/10-01) (12'' Larger For Tolerance) Foundations Complete 12/03/25 12/12/25 18.8 0.0
100%
0.0
NW.2060 Weather Event #6 - 12/04/25 Project Impacts Complete 12/04/25 12/04/25 1.2 0.0
100%
0.0
RPL10.CFCI.4320 RPL10 - Fabricate / Deliver - Lighting (CFCI) Div. 26 - Lighting Complete 12/05/25 02/20/26 37.5 0.0
100%
0.0
RPL10.EY.EF1.01520 RPL10.EY.EF1 - Install Mechanical UG (Post WI#06) Underground Complete 12/05/25 12/22/25 1.2 0.0
100%
0.0
RPL10.EY.NS1.01600 RPL10.EY.NS1 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Reconstruction Impact) (Post WI#06) Foundations Complete 12/05/25 01/16/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01680 RPL10.EY.NS2 - Install F/R/P Equipment Pads - 1-8 (Grid 10-25/10-32) (Post WI#06) (Pre WI#07) Foundations Complete 12/05/25 01/20/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01700 RPL10.EY.NS2 - Install Electrical UG (Grid 10-42\10-32) (Post WI#06) Underground Complete 12/05/25 12/22/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01720 RPL10.EY.NS2 - Install Mechanical UG (Post WI#06) Underground Complete 12/05/25 01/07/26 12.5 0.0
100%
0.0
RPL10.EY.SSB.01400 RPL10.EY.SSB - Install Electrical UG (Post WI#06) Underground Complete 12/05/25 12/16/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2440 RPL10.MCUP.Loop 1 - F/R/P Pads (12'' larger) (Post WI#06) Foundations Complete 12/05/25 01/07/26 25.0 0.0
100%
0.0
RPL10.SKN.N.01200 RPL10.SKIN.North - Install IMP Flashing,Panels & Caulking - Grid lines 10-42/10-30 (3) (Post WI #06) North Complete 12/05/25 12/05/25 1.2 0.0
100%
0.0
RPL10.STR.NS12.01240 RPL10.Structure.NS12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-30/10-20(Post WI#06) Steel and Decking Complete 12/05/25 12/05/25 2.5 0.0
100%
0.0
RPL10.STR.NS12.01260 RPL10.Structure.NS12 - Install Decking & Detailing turnover #5 - Grid lines 10-30/10-27 (Post WI#06) Steel and Decking Complete 12/05/25 12/05/25 3.8 0.0
100%
0.0
RPL10.STR.SSB.01020 RPL10.Structure.SSB - Install Storm Shelter Steel and Decking (WI#05 to Start) Storm Shelter Complete 12/05/25 01/07/26 6.2 0.0
100%
0.0
RPL10.STR.SSB.01270 RPL10.Structure.SSB - SOG F/R/P (Pour #1 -12/04 & #2 -12/06) - Grid lines 10-42/10-38 (Post WI#06) F/R/P Complete 12/05/25 12/08/25 6.2 0.0
100%
0.0
RPL10.VDC.4580 RPL10.BIM TIER 2 - 4 - Model Completion TIER 2 - 4 Complete 12/05/25 12/05/25 0.0 0.0
100%
0.0
RPL10.VDC.4600 RPL10.BIM TIER 2 - 4 - Release & Fabricate TIER 2 - 4 Complete 12/05/25 12/05/25 1.2 0.0
100%
0.0
NW.1820 IMP Crane #1 Movement 04 IMP Crane #1 Complete 12/08/25 12/08/25 0.0 0.0
100%
0.0
PRE.BNS.1420 GMP Approved by Meta Legal Precon - Budget & Schedule Complete 12/08/25 12/08/25 0.0 0.0
100%
0.0
PRE.BNS.1480 Execution of fGMP Precon - Budget & Schedule Complete 12/08/25 12/08/25 0.0 0.0
100%
0.0
RPL.CM.D.C5160.XR Logistics Area #6 - Complete Logistics - Area Turnovers XREF Milestones Complete 12/08/25 12/08/25 0.0 0.0
100%
0.0
RPL.CM.D.N5615.XR LA 183 /Wade - Turn Lane Logistics - Off-Site Receive XREF Milsetones Complete 12/08/25 12/08/25 0.0 0.0
100%
0.0
RPL10.EY.SSB.01080 RPL10.EY.SSB - Install BMS UG Underground Complete 12/08/25 12/16/25 6.2 0.0
100%
0.0
RPL10.SKN.01220 RPL10.SKIN - RFI783 - To Provide Bent Plate sizing and Welding Requirements Expansion Joint Delay Event Complete 12/08/25 12/09/25 1.2 0.0
100%
0.0
RPL10.SKN.S.01030 RPL10.SKIN.South - Install IMP Flashing,Panels & Caulking - Grid lines 10-41/10-30(4) (with temp closures for openings) South Complete 12/08/25 12/12/25 2.5 0.0
100%
0.0
RPL10.STR.EF12.01000 RPL10.Structure.EF12 - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 10-20/10-10 Steel and Decking Complete 12/08/25 12/24/25 11.2 0.0
100%
0.0
RPL10.STR.EF12.01010 RPL10.Structure.EF12 - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Complete 12/08/25 01/06/26 23.8 0.0
100%
0.0
RPL10.STR.EF12.01020 RPL10.Structure.EF12 - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary EF1 & EF2 Complete 12/08/25 03/21/26 86.2 0.0
100%
0.0
RPL10.STR.NS12.01040 RPL10.Structure.NS12 - Install Decking & Detailing turnover #6 - Grid lines 10-27/10-24 Steel and Decking Complete 12/08/25 12/10/25 2.5 0.0
100%
0.0
RPL10.EY.NS1.01060 RPL10.EY.NS1 - Install Electrical UG (Grid 10-42/10-32) Underground Complete 12/09/25 12/15/25 6.2 0.0
100%
0.0
RPL10.EY.NS1.01090 RPL10.EY.NS1 - Install Mechanical UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.EY.NS1.01100 RPL10.EY.NS1 - Install SD, DW, FW UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.EY.NS1.01120 RPL10.EY.NS1 - Install BMS UG Underground Complete 12/09/25 12/19/25 12.5 0.0
100%
0.0
RPL10.SKN.SSB.01020 RPL10.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary SSB Active 12/09/25 10/09/26 261.2 127.5
0%
53.8
RPL10.SKN.SSB.01080 RPL10.SKIN.SSB - Install Roof System - Exterior Wall Sheething and EJ (See SmartSheet for Seq Div 7 & Roofer) (WI #06) Roofing Complete 12/09/25 12/19/25 5.0 0.0
100%
0.0
RPL10.SKN.SSB.01090 RPL10.SKIN.SSB - Install Roof System - WBS Summary Roofing Complete 12/09/25 03/13/26 62.5 0.0
100%
0.0
RPL10.STR.SSB.01160 RPL10.Structure.SSB - SOG F/R/P (Pour #3 -12/09 & #4 -12/11) - Grid lines 10-38/10-36 F/R/P Complete 12/09/25 12/16/25 6.2 0.0
100%
0.0
RPL10.INT.SSB.02680 RPL10.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls and OverHead Complete 12/10/25 01/12/26 17.5 0.0
100%
0.0
RPL10.INT.SSB.02820 RPL10.Interior.SSB - Priority - Priority - Frame Priority Soffit and Hang Drywall Priority Walls and OverHead Complete 12/10/25 01/07/26 17.5 0.0
100%
0.0