Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 8463 activities — 05/05/2026 09:13 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260426.xer · Uploaded May 05, 2026 02:13 PM · 8463 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
87
Completed
13
In Progress
87
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SUB.NS12.01040 RPL10.SubStructure.NS12 - Install Stem Walls - Grid lines 10-30/10-20 Foundations Complete 10/06/25 10/13/25 5.0 0.0
100%
0.0
RPL10.SUB.NS12.01060 RPL10.SubStructure.NS12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 1 Underground Complete 10/06/25 10/14/25 8.8 0.0
100%
0.0
RPL10.SUB.SSB.01080 RPL10.SubStructure.SSB - Strip Form Work And Apply Water Proofing System Foundations Complete 10/06/25 10/14/25 3.8 0.0
100%
0.0
RPL10.SUB.EF12.01090 RPL10.SubStructure.EF12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part 1 Underground Complete 10/07/25 10/13/25 6.2 0.0
100%
0.0
RPL10.SUB.NS12.01090 RPL10.SubStructure.NS12 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part1 Underground Complete 10/07/25 10/13/25 8.8 0.0
100%
0.0
RPL10.SUB.NS12.01100 RPL10.SubStructure.NS12 - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) Underground Complete 10/07/25 10/13/25 3.8 0.0
100%
0.0
RPL.CM.D.C5560.XR Republic Road ( 3 TO's , Ist Upto GL 10-20, 2nd 10-01,3rd Mcup Logistics - Onsite Receive XREF Milestones Complete 10/09/25 10/09/25 0.0 0.0
100%
0.0
RPL10.SUB.NS12.01240 RPL10.SubStructure.NS12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 2 Underground Complete 10/09/25 10/28/25 8.8 0.0
100%
0.0
RPL10.SUB.NS12.01260 RPL10.SubStructure.NS12 - Install UG Utilities - Electrical/Inspection & Tie-ins-Part2 Underground Complete 10/09/25 10/13/25 8.8 0.0
100%
0.0
RPL10.SUB.NS43.01030 RPL10.SubStructure.NS43 - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 10-10/10-01 Foundations Complete 10/09/25 10/16/25 8.8 0.0
100%
0.0
RPL.10.D.X1110.XR Pad Ready - RPL10 - mCup Pad Ready (XREFs) Complete 10/10/25 10/10/25 0.0 0.0
100%
0.0
RPL.CM.D.C5580.XR Empire Road ( 3 TO's , Ist Upto GL 10-20, 2nd 10-01,3rd Mcup Logistics - Onsite Receive XREF Milestones Complete 10/10/25 10/10/25 0.0 0.0
100%
0.0
RPL10.INT.NS1.03180 RPL10.Interior.NS1 - OFE - MES Skids - Set Remaining 30"" Piping OBSOLETE (Duplicated) Obsolete Complete 10/10/25 10/13/25 12.5 0.0
100%
0.0
RPL10.INT.NS2.03305 RPL10.Interior.NS2 - OFE - MES Skids - Set Remaining 30"" Piping OBSOLETE (Duplicated) Obsolete Complete 10/10/25 10/13/25 12.5 0.0
100%
0.0
PRE.MIR.1200 Glass & Metal Panel SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/13/25 10/28/25 10.0 0.0
100%
0.0
PRE.MIR.1220 Hot Aisle Containment Install SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/13/25 10/27/25 8.8 0.0
100%
0.0
RPL10.CFCI.3680 RPL10- Submittals - FSC -Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Complete 10/13/25 11/17/25 25.0 0.0
100%
0.0
RPL10.CFCI.3720 RPL10 - Submittals - Doors, Frames and Hardware Doors, Frames & Hardware (HM and Wood) Complete 10/13/25 10/24/25 25.0 0.0
100%
0.0
RPL10.CFCI.3730 RPL10 - Prep / Submit for Review - Gypsum System and Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Complete 10/13/25 10/16/25 18.8 0.0
100%
0.0
RPL10.CFCI.5210 RPL10- Submittal Rvw/App'l - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 10/13/25 10/24/25 12.5 0.0
100%
0.0
RPL10.MCUP.LP1.1000 RPL10.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 1 Active 10/13/25 06/15/26 206.2 43.8
0%
465.0
RPL10.MCUP.LP1.1040 RPL10.MCUP.Loop 1 - Install UG Utilities - WBS Summary Underground Complete 10/13/25 11/12/25 25.0 0.0
100%
0.0
RPL10.MCUP.LP1.1060 RPL10.MCUP.Loop 1 - Install Mechanical UG Mechanical UG Complete 10/13/25 10/29/25 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.1080 RPL10.MCUP.Loop 1 - Install Electrical UG Electrical UG Complete 10/13/25 11/03/25 25.0 0.0
100%
0.0
RPL10.MCUP.LP1.1140 RPL10.MCUP.Loop 1 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Complete 10/13/25 10/29/25 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.1160 RPL10.MCUP.Loop 1 - Install Grounding Wire Grounding UG Complete 10/13/25 11/12/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2120 RPL10.MCUP.Loop 1 - Industrial Water UG (North) Mechanical UG Complete 10/13/25 10/17/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2160 RPL10.MCUP.Loop 1 - Industrial Water UG (East) Mechanical UG Complete 10/13/25 10/17/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2200 RPL10.MCUP.Loop 1 - Install Grounding Rod (30 ft depth) Grounding UG Complete 10/13/25 11/12/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2240 RPL10.MCUP.Loop 1 - Install Generator Conduit Feed - Grid 10-01 to mCup #1,#3,#5,#7 Electrical UG Complete 10/13/25 10/28/25 5.0 0.0
100%
0.0
RPL10.MCUP.LP2.1000 RPL10.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 2 Active 10/13/25 06/29/26 218.8 56.2
0%
452.5
RPL10.MCUP.LP2.1060 RPL10.MCUP.Loop 2 - Install UG Utilities - WBS Summary Underground Complete 10/13/25 11/24/25 37.5 0.0
100%
0.0
RPL10.MCUP.LP2.1120 RPL10.MCUP.Loop 2 - Install Grounding Wire Grounding UG Complete 10/13/25 11/12/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.2120 RPL10.MCUP.Loop 2 - Industrial Water UG (South) Mechanical UG Complete 10/13/25 10/17/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.2180 RPL10.MCUP.Loop 2 - Install Grounding Rod (30 ft depth) Grounding UG Complete 10/13/25 11/12/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.2200 RPL10.MCUP.Loop 2 - Install Exothermic Weld Grounding UG Complete 10/13/25 11/12/25 8.8 0.0
100%
0.0
RPL10.SUB.EF12.01040 RPL10.SubStructure.EF12 - Install Stem walls - Grid lines 10-20/10-10 Foundations Complete 10/13/25 10/16/25 5.0 0.0
100%
0.0
RPL10.SUB.SSB.01220 RPL10.SubStructure.SSB - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside) -After Impact-Part2 Underground Complete 10/13/25 10/14/25 2.5 0.0
100%
0.0
RPL10.VDC.3780 RPL10.T0 (mCUP/Exterior) - BIM Review & Approve Shops - Priority 1 Priority 1 mCUP Yard / Exterior Complete 10/13/25 10/17/25 6.2 0.0
100%
0.0
RPL10.mCUP.1060 RPL10.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-8 - WBS Summary mCUP Yard Active 10/13/25 06/29/26 218.8 56.2
0%
452.5
RPL.CM.D.C5440.XR Logistics Area #4 - DPR Orientation Trailer & Services Available Logistics - Area Turnovers XREF Milestones Complete 10/14/25 10/14/25 0.0 0.0
100%
0.0
RPL10.CFCI.6680 RPL10 - Fabricate / Deliver - MDF CU Units (8) (CFCI) Div. 23 - MDF CU Units Active 10/14/25 04/27/26 67.5 0.0
0%
126.2
RPL10.CFCI.6860 RPL10 - Fabricate / Deliver - CRAC Units EF - 3&4 EF Corridor Rooms (Inverter Room & IDF) (CFCI) Div. 23 - CRAH Units Active 10/14/25 04/30/26 67.5 5.0
100%
143.8
RPL10.CFCI.6920 RPL10 - Fabricate / Deliver - CRAH Units EF2 (CFCI) Div. 23 - CRAH Units Active 10/14/25 04/30/26 67.5 5.0
0%
136.2
RPL10.CFCI.6940 RPL10 - Fabricate / Deliver - CRAH Units EF1 (CFCI) Div. 23 - CRAH Units Active 10/14/25 04/30/26 67.5 5.0
0%
113.8
RPL10.CFCI.6960 RPL10 - Fabricate / Deliver - CRAC Units NS1 (CFCI) Div. 23 - CRAH Units Active 10/14/25 06/17/26 67.5 46.2
0%
41.2
RPL10.CFCI.6980 RPL10 - Fabricate / Deliver - CRAC Units NS2 (CFCI) Div. 23 - CRAH Units Active 10/14/25 06/17/26 67.5 46.2
0%
47.5
RPL10.CFCI.7000 RPL10 - Fabricate / Deliver - CRAC Units EF - 3&4 EF Corridor Rooms (UPS Room) (CFCI) Div. 23 - CRAH Units Active 10/14/25 04/30/26 67.5 5.0
0%
143.8
RPL10.SUB.NS12.01050 RPL10.SubStructure.NS12 - Strip Form Work And Apply Water Proofing System Foundations Complete 10/14/25 10/17/25 2.5 0.0
100%
0.0
RPL10.VDC.4320 RPL10.T1 (Center EF to End Corr.) - BIM Prepare & Submit Shops - Priority 2 Priority 2 - EF to End Corridor Complete 10/14/25 10/20/25 6.2 0.0
100%
0.0
RPL10.VDC.4400 RPL10.T1 (Misc. Steel) - BIM Prepare & Submit Shops - Priority 3 Priority 3 - Misc Steel Complete 10/14/25 10/20/25 6.2 0.0
100%
0.0
RPL10.MCUP.LP1.2220 RPL10.MCUP.Loop 1 - Install Exothermic Weld Grounding UG Complete 10/15/25 11/12/25 8.8 0.0
100%
0.0
RPL10.SUB.EF12.01110 RPL10.SubStructure.EF12 - Scan, Install Backfill and Grading - Grid lines 10-20/10-10 (1st Layer Backfill) Underground Complete 10/15/25 10/27/25 3.8 0.0
100%
0.0
RPL10.SUB.NS12.01110 RPL10.SubStructure.NS12 - Scan, Install Backfill and Grading - Grid lines 10-30/10-20 (1st Layer Backfill) Underground Complete 10/15/25 10/15/25 6.2 0.0
100%
0.0
RPL10.SUB.NS12.01220 RPL10.SubStructure.NS12 - Adjust,Scan, Install Backfill and Grading - Grid lines 10-30/10-20 (2nd Layer Backfill) Underground Complete 10/15/25 10/15/25 6.2 0.0
100%
0.0
RPL10.CFCI.4560 RPL10 - Submittal Rvw/App'l - Gypsum System and Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Complete 10/17/25 11/03/25 25.0 0.0
100%
0.0
GCD.RPL10.1360 Steel Erection Start - RPL10 Construction Milestones Complete 10/20/25 10/20/25 0.0 0.0
100%
0.0
NW.1340 Steel Crane #1 Mobilization Steel Crane #1 Complete 10/20/25 10/20/25 0.0 0.0
100%
0.0
NW.1360 Steel Crane #2 Mobilization Steel Crane #2 Complete 10/20/25 10/20/25 0.0 0.0
100%
0.0
NW.1980 Weather Event #3 - 10/20/25 - 10/21/25 Project Impacts Complete 10/20/25 10/21/25 5.0 0.0
100%
0.0
PRE.TPA.1300 Architectural/Security Fencing - Award and Issue Subcontract OBSOLETE Obsolete Complete 10/20/25 11/04/25 15.0 0.0
100%
0.0
RPL10.CFCI.3390 RPL10 - Prep / Submit for Review - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Complete 10/20/25 11/11/25 25.0 0.0
100%
0.0
RPL10.CFCI.4010 RPL10 - Submittal Rvw/App'l - Roofing Roofing Complete 10/20/25 10/31/25 12.5 0.0
100%
0.0
RPL10.CFCI.5040 RPL10 - Fabricate / Deliver - Joint Sealants Joint Sealants Complete 10/20/25 11/17/25 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.2260 RPL10.MCUP.Loop 1 - Industrial Water UG Fill & Testing Mechanical UG Complete 10/20/25 11/05/25 6.2 0.0
100%
0.0
RPL10.SUB.EF12.01050 RPL10.SubStructure.EF12 - Strip Form Work And Apply Water Proofing System Foundations Complete 10/20/25 10/27/25 6.2 0.0
100%
0.0
RPL10.SUB.NS43.01040 RPL10.SubStructure.NS43 - Install Stem walls - Grid lines 10-10/10-01 ( Before Impact) Foundations Complete 10/20/25 10/21/25 8.8 0.0
100%
0.0
RPL10.SUB.NS43.01060 RPL10.SubStructure.NS43 - Install UG Utilities - Plumbing/Testing/Backfill-Part1 Underground Complete 10/20/25 10/28/25 8.8 0.0
100%
0.0
RPL10.SUB.NS43.01070 RPL10.SubStructure.NS43 - Install UG Utilities - WBS Summary Underground Complete 10/20/25 11/19/25 28.8 0.0
100%
0.0
RPL10.VDC.3840 RPL10.T0 (mCUP/Exterior) - BIM Model/Shops - Priority 1 Final Review (Page Turn) Priority 1 mCUP Yard / Exterior Complete 10/20/25 10/30/25 11.2 0.0
100%
0.0
JCL.C.1100 RPL10 - Cost Risk LOE-6 Structure Cost LOEs Complete 10/21/25 04/10/26 71.2 0.0
100%
0.0
RPL10.CFCI.6210 RPL10 - SOG Mock-up (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 10/21/25 10/24/25 1.2 0.0
100%
0.0
RPL10.CFCI.6580 RPL10 - (DBC) Fabricate / Deliver - IWP Exterior Metal Panels Complete 10/21/25 11/14/25 15.0 0.0
100%
0.0
RPL10.STR.SSB.01040 RPL10.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 10-42/10-30 Steel and Decking Complete 10/21/25 11/14/25 15.0 0.0
100%
0.0
RPL10.STR.SSB.01050 RPL10.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Complete 10/21/25 11/26/25 30.0 0.0
100%
0.0
RPL10.SUB.NS43.01090 RPL10.SubStructure.NS43 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part1 Underground Complete 10/21/25 10/27/25 7.5 0.0
100%
0.0
RPL.CM.D.C5805.XR Far Far Away Lane (Around School) Logistics - Onsite Receive XREF Milestones Complete 10/22/25 10/22/25 0.0 0.0
100%
0.0
RPL10.EY.NS1.01030 RPL10.EY.NS1 - Install Foundations, UG Utilities, OFE - WBS Summary NS1 Active 10/22/25 10/15/26 305.0 151.2
0%
357.5
RPL10.EY.NS1.01070 RPL10.EY.NS1 - Install UG Utilities - WBS Summary Underground Complete 10/22/25 12/19/25 68.8 0.0
100%
0.0
RPL10.EY.NS1.01520 RPL10.EY.NS1 - Install Electrical UG (Grid 10-32/10-25) Underground Complete 10/22/25 10/29/25 6.2 0.0
100%
0.0
RPL10.EY.NS2.01030 RPL10.EY.NS2 - Install Foundations, UG Utilities, OFE- WBS Summary NS2 Active 10/22/25 11/12/26 328.8 175.0
0%
333.8
RPL10.EY.NS2.01070 RPL10.EY.NS2 - Install UG Utilities - WBS Summary Underground Complete 10/22/25 01/07/26 62.5 0.0
100%
0.0
RPL10.EY.NS2.01520 RPL10.EY.NS2 - Install Electrical UG (Grid 10-32\10-25) Underground Complete 10/22/25 10/29/25 6.2 0.0
100%
0.0
RPL10.EY.SSB.01030 RPL10.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary Electrical Yard (within ring road) Active 10/22/25 02/23/27 412.5 258.8
0%
250.0
RPL10.MCUP.LP2.1080 RPL10.MCUP.Loop 2 - Install Mechanical UG Mechanical UG Complete 10/22/25 11/03/25 12.5 0.0
100%
0.0
RPL10.MCUP.LP2.2160 RPL10.MCUP.Loop 2 - Industrial Water UG (West) Mechanical UG Complete 10/22/25 11/03/25 6.2 0.0
100%
0.0
RPL10.SUB.NS43.01250 RPL10.SubStructure.NS43 - Install Stem walls - Grid lines 10-10/10-01 (After Impact) Foundations Complete 10/22/25 10/31/25 8.8 0.0
100%
0.0
RPL10.CFCI.5340 RPL10 - Fabricate / Deliver - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 10/24/25 10/24/25 1.2 0.0
100%
0.0
PRE.MIR.1260 Balance of Trades SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/27/25 11/03/25 0.0 0.0
100%
0.0
RPL10.CFCI.3710 RPL10- Prep / Submit for Review - Roofing Roofing Complete 10/27/25 10/27/25 0.0 0.0
100%
0.0
RPL10.MCUP.LP2.1140 RPL10.MCUP.Loop 2 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Complete 10/27/25 11/03/25 8.8 0.0
100%
0.0
RPL10.SUB.EF12.01170 RPL10.SubStructure.EF12 - Adjust,Scan,Install Backfill and Grading - Grid lines 10-20/10-10 (2nd Layer Backfill) Underground Complete 10/27/25 11/04/25 3.8 0.0
100%
0.0
RPL10.SUB.EF12.01190 RPL10.SubStructure.EF12 - Install UG Utilities - Plumbing/Testing/Backfill-Part 2 Underground Complete 10/27/25 11/04/25 8.8 0.0
100%
0.0
RPL10.VDC.4340 RPL10.T1 (Center EF to End Corr.) - BIM Review & Approve Shops - Priority 2 Priority 2 - EF to End Corridor Complete 10/27/25 11/04/25 8.8 0.0
100%
0.0
RPL10.VDC.4420 RPL10.T1 (Misc. Steel) - BIM Review & Approve Shops - Priority 3 Priority 3 - Misc Steel Complete 10/28/25 11/03/25 6.2 0.0
100%
0.0
PRE.TPA.1240 Glass / Metal Panel / Glazing - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 10/29/25 01/07/26 10.0 0.0
100%
0.0
RPL10.SUB.NS43.01050 RPL10.SubStructure.NS43 - Strip Form Work And Apply Water Proofing System Foundations Complete 10/29/25 11/03/25 5.0 0.0
100%
0.0
RPL10.SUB.NS43.01190 RPL10.SubStructure.NS43 - Install UG Utilities - Plumbing/Testing/Backfill-Part2 Underground Complete 10/29/25 11/14/25 8.8 0.0
100%
0.0
RPL10.SUB.NS43.01210 RPL10.SubStructure.NS43 - Install UG Utilities - Electrical/Inspection & Tie-ins (Outside to Inside)-Part2 Underground Complete 10/29/25 11/18/25 7.5 0.0
100%
0.0
RPL10.CFCI.3590 RPL10 - Submittal Rvw/App'l - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Complete 10/30/25 11/25/25 12.5 0.0
100%
0.0