Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.2 entries
Thursday, April 30, 2026
Caleb Bourghs
RPL10, CMDF1, CMDF2, GSIDFNX5
· logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination.
CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team.
Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located.
Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit.
Other team members placed 3 other issues today we found in the field during our walk-through.
Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards.
Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Tuesday, April 28, 2026
Timeon P.
RPL10.CMDF 1/2
· logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).