Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.2 entries
## Overview
The entries from April 30 to May 1, 2026, detail inspections and findings related to the VCM installations at various locations. Key themes include identification of issues in CMDF1 and CMDF2, as well as inventory checks of VCM units.
## By Area / Equipment
- **CMDF1**
- Issue #6394: Concrete hole on East Wall (66 1/2 inches from South wall) where the first VCM will be located.
- **CMDF2**
- Issue #6391: Vertical ladder rack locations blocked by EPMS/BAS conduit on South & West walls.
- Verified VCM measurements met requirements.
- **IDFNX5**
- Verified splicing; findings reported for necessary changes.
## Issues / Open Items
- Issue #6394: Concrete hole in CMDF1 (2026-04-30).
- Issue #6391: Blocked ladder rack locations in CMDF2 (2026-04-30).
- Follow-up needed with Clearcore regarding splicing changes in IDFNX5 (2026-04-30).
## Progress / Completed
- Inspected and counted 11 VCM units at the warehouse (2026-05-01).
- Verified all measurements for CMDF2 VCMs met specifications (2026-04-30).
## People Mentioned
- Caleb Bourghs
- Perry Brocato
- Chance (Superintendent)
Friday, May 01, 2026
Perry brocato
· logged 05/01/2026 09:51 AM CT
We were at the warehouse and we counted and inspected 554 2 post,12 4 post and 11 VCM.
Thursday, April 30, 2026
Caleb Bourghs
RPL10, CMDF1, CMDF2, GSIDFNX5
· logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination.
CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team.
Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located.
Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit.
Other team members placed 3 other issues today we found in the field during our walk-through.
Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards.
Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.