Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
2 entries
Clear
2 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview The entries from April 28 and April 30, 2026, detail pre-installation activities and site walkthroughs for the CMDF 1/2 area, highlighting issues identified during inspections and ongoing coordination among the QA team. ## By Area / Equipment - **RPL10.CMDF 1/2** - Completed pre-installation walkthrough and measurements (4/28). - Documented Issue #5174 during walkthrough. - **RPL10.CMDF1** - Conducted walkthrough with QA team; identified Issue #6394 regarding a hole in the East Wall (4/30). - **RPL10.CMDF2** - Walkthrough revealed Issue #6391 concerning blocked vertical ladder rack locations (4/30). - **GSIDFNX5** - Verified splicing; reported findings for necessary changes to meet specifications (4/30). ## Issues / Open Items - Issue #5174: Documented issue from CMDF 1/2 walkthrough (4/28). - Issue #6394: Hole in East Wall of CMDF1 (4/30). - Issue #6391: Blocked ladder rack locations in CMDF2 (4/30). - Follow-up needed with Clearcore regarding splicing specifications and housekeeping for IDFNX5 (4/30). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed with measurements taken (4/28). - Verified specifications and measurements for CMDF2 VCMs, all met requirements (4/30). ## People Mentioned - Timeon P. - Caleb Bourghs - Chance (Superintendent)
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).