Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
1 entry
Clear
1 entry match current filters.
AI Summary (read-only — original entries not modified)
## Overview On April 30, 2026, a field walk was conducted by the FE team through the GSEF 1/2, CMDF 1/2, and IDFNX5 areas. Key activities included the completion of temporary splices and discussions regarding necessary adjustments to the horizontal ladder runway in the CMDFs. ## By Area / Equipment - **RPL10 GSEF 1/2** - Field walk completed with FE team. - Photos taken of the temporary 2 post rack for temporary splices. - **CMDF 1/2** - Horizontal ladder runway needs to be moved 5" from walls for fiber routing. - Changes to be redlined post-installation per Hargis. - Review ongoing to determine if adjustments will result in a change order. - **IDFNX5** - Temporary splices of two 192 fibers completed by Clear Core. ## Issues / Open Items - Need to assess if the horizontal ladder runway adjustment will require a change order (April 30, 2026). ## Progress / Completed - Temporary splices in IDFNX5 completed by Clear Core (April 30, 2026). - Field walk completed with FE team (April 30, 2026). ## People Mentioned - Timeon P. - SFE Paul - Hargis - Clear Core
Thursday, April 30, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.