Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
## Overview
On April 30, 2026, the QA team conducted walk-throughs in CMDF1, CMDF2, and IDFNX5, identifying several issues related to concrete and equipment placement. The team also verified specifications and measurements for VCMs and splicing requirements.
## By Area / Equipment
- **CMDF1**
- Walk-through conducted with QA team.
- Issue #6394: Concrete hole on East Wall (66 1/2 inches from South wall); dimensions 2 1/2 inches long and 1 inch wide, where the first VCM will be located.
- **CMDF2**
- Walk-through conducted with QA team.
- Issue #6391: South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit.
- **IDFNX5**
- Walk-through conducted with QA team.
- Verified splicing; findings reported to Superintendent Chance for follow-up with Clearcore.
## Issues / Open Items
- Issue #6394: Concrete hole in CMDF1 (4/30/2026).
- Issue #6391: Blocked ladder rack locations in CMDF2 (4/30/2026).
- Additional 3 issues identified by other team members during walk-through (4/30/2026).
## Progress / Completed
- Verified specifications and measurements for VCMs in CMDF2; all met requirements (4/30/2026).
- Verified splicing in IDFNX5 and reported findings for necessary changes (4/30/2026).
## People Mentioned
- Caleb Bourghs
- Chance (Superintendent)
- Clearcore (vendor)
Thursday, April 30, 2026
Caleb Bourghs
RPL10, CMDF1, CMDF2, GSIDFNX5
· logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination.
CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team.
Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located.
Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit.
Other team members placed 3 other issues today we found in the field during our walk-through.
Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards.
Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.