Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
4 entries
Clear
4 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the period from April 30 to May 5, 2026, highlighting ongoing inspections and issues related to equipment placement and material verification across various areas, particularly focusing on the OOR process. ## By Area / Equipment - **GSIDFNX05** - Racks placed according to prints; measurements taken to ensure correct locations (4/30). - Issues reported: - Issue #6395: MOFE Door - Issue #6393: Labeling Conflict - Fiber clippings left on the floor; fiber dressing in 432 can and 1u unican enclosure not up to standard (4/30). - **CMDF1** - Hole in East Wall noted for VCM location; Issue #6394 created (4/30). - **CMDF2** - Vertical ladder rack locations blocked by EPMS/BAS conduit; Issue #6391 created (4/30). - **Warehouse** - Verified all material through OOR; 554 two-post racks confirmed to be up to specs (5/1). - **NCB** - Material verification completed through OOR (5/1). - **RPL** - New material verified at Warehouse; L1s completed and verified through OOR (5/5). ## Issues / Open Items - Issue #6395: MOFE Door (4/30). - Issue #6393: Labeling Conflict (4/30). - Issue #6394: Hole in East Wall (4/30). - Issue #6391: Blocked vertical ladder rack locations (4/30). - Fiber dressing issues in GSIDFNX05 (4/30). - Follow-up needed with Clearcore regarding splicing specs and housekeeping (4/30). ## Progress / Completed - Racks in GSIDFNX05 anchored and measurements confirmed (4/30). - Verified specs and measurements for CMDF2 VCMs (4/30). - All material at Warehouse verified through OOR (5/1). - L1s completed and verified (5/5). ## People Mentioned - Timeon P. - Caleb Bourghs - Super Chance - Richard
Tuesday, May 05, 2026
Caleb Bourghs RPL · logged 05/06/2026 07:07 AM CT
Verified new material at Warehouse. Completed L1s and verified through OOR. Verified material at Mortenson Tent, arranged our crew to pick it up to bring to Tent 1.
Friday, May 01, 2026
Caleb Bourghs WAREHOUSE, NCB · logged 05/01/2026 03:20 PM CT
Went through all material at Warehouse. Verify all material through OOR, receivables, and ACC website. Verified all 554 tWo post racks were fully up to specs and in good condition. Created all templates for our L1 connectivity materiaL
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.