Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.1 entry
## Overview
This log entry from April 30, 2026, details a field walk conducted by the FE team through the GSEF 1/2, CMDF 1/2, and IDFNX5 areas. Key themes include the completion of temporary splices, necessary adjustments to the horizontal ladder runway, and potential change order considerations.
## By Area / Equipment
- **GSEF 1/2**
- Field walk completed with the FE team.
- Photos taken of the temporary 2 post rack for temporary splices.
- **CMDF 1/2**
- Horizontal ladder runway needs to be moved approximately 5" from walls for proper fiber routing.
- Buildout completed to specifications; FE team reviewing for potential change order.
- **IDFNX5**
- Temporary splices of two 192 fibers completed by Clear Core.
## Issues / Open Items
- Need to redline changes for the horizontal ladder runway adjustments after installation (2026-04-30).
- Review by FE team to determine if a change order is necessary due to the runway adjustments (2026-04-30).
## Progress / Completed
- Completion of temporary splices in IDFNX5 by Clear Core (2026-04-30).
- Field walk with the FE team through GSEF 1/2, CMDF 1/2, and IDFNX5 completed (2026-04-30).
## People Mentioned
- Timeon P.
- SFE Paul
- Clear Core (vendor)
Thursday, April 30, 2026
Timeon P.
RPL10 GSEF 1/2, CMDF 1/2, IDFNX5
· logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5.
Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core.
SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.