Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
2 entries
Clear
2 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview The entries from April 30, 2026, detail inspections and field walks conducted by the FE team in various areas, focusing on the installation and alignment of racks and fiber splices. Key themes include the need for adjustments to the horizontal ladder runways and addressing issues related to fiber dressing and labeling. ## By Area / Equipment - **GSEF 1/2** - Completed field walk with the FE team. - Photos taken of the temporary 2 post rack for splices. - **CMDF 1/2** - Horizontal ladder runway adjustments required (5" away from walls). - Changes to be redlined post-installation. - **IDFNX5** - Temporary splices of two 192 fibers completed by Clear Core. - **GSIDFNX05** - Measurements taken to confirm rack placements before anchoring. - Racks landed according to prints. ## Issues / Open Items - **GSIDFNX05 MOFE Door** - Issue #6395 (April 30, 2026) - **GSIDFNX05 Labeling Conflict** - Issue #6393 (April 30, 2026) - Fiber clippings left on the floor by Clear Core (April 30, 2026). - Fiber dressing in the 432 can and 1u unican fiber enclosure not up to standard; Clear Core called back for correction (April 30, 2026). ## Progress / Completed - Temporary splices of two 192 fibers completed in IDFNX5 (April 30, 2026). - Racks in CMDF2 placed according to prints (April 30, 2026). ## People Mentioned - Timeon P. - SFE Paul - Super Chance - Richard
Thursday, April 30, 2026
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.