## Overview This log covers activities from April 30, 2026, focusing on site inspections and issue identification related to the CMDF1, CMDF2, and IDFNX5 areas. The main themes include coordination with the QA team and addressing issues related to concrete and conduit placement. ## By Area / Equipment - **CMDF1** - Conducted walk-through with QA team. - Identified Issue #6394: Concrete hole on East Wall (66 1/2 inches from South wall, 2 1/2 inches long, 1 inch wide) for VCM placement. - **CMDF2** - Conducted walk-through with QA team. - Identified Issue #6391: Vertical ladder rack locations blocked by EPMS/BAS conduit. - **IDFNX5** - Verified splicing on-site; reported findings to Superintendent for necessary changes. ## Issues / Open Items - Issue #6394: Concrete hole in CMDF1 (4/30/2026). - Issue #6391: Blocked vertical ladder rack locations in CMDF2 due to EPMS/BAS conduit (4/30/2026). - Additional 3 issues identified by team during walk-through (4/30/2026). ## Progress / Completed - Verified specs and measurements for CMDF2 VCMs; all met requirements (4/30/2026). - Verified splicing in IDFNX5 and reported to Superintendent (4/30/2026). ## People Mentioned - Caleb Bourghs - Chance (Superintendent) - QA Team Members
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.