Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
2 entries
Clear
2 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview The entries from April 28 and April 30, 2026, detail the pre-installation activities and field walkthroughs for CMDF 1/2, highlighting measurements taken, issues identified, and necessary adjustments for installation. ## By Area / Equipment - **CMDF 1/2** - Pre-installation walkthrough completed on April 28. - Issue #5174 documented regarding room measurements. - Horizontal ladder runway needs to be moved 5" from walls for fiber routing (April 30). - **GSEF 1/2** - Field walk completed with FE team; temporary splices documented. - Photos taken of the temporary 2 post rack for splices. - **IDFNX5** - Completion of temporary splices of two 192 fibers by Clear Core. ## Issues / Open Items - Issue #5174 documented regarding room measurements (April 28). - Horizontal ladder runway adjustments required for CMDF 1/2 (April 30). - Potential change order under review by FE team for CMDF adjustments (April 30). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed (April 28). - Field walk with FE team through GSEF 1/2, CMDF 1/2, and IDFNX5 completed (April 30). - Temporary splices in IDFNX5 completed by Clear Core (April 30). ## People Mentioned - Timeon P. - SFE Paul - Clear Core
Thursday, April 30, 2026
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).