Daily Log

A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.
4 entries
Clear
4 entries match current filters.
AI Summary (read-only — original entries not modified)
## Overview This briefing covers the daily logs from April 28 to April 30, 2026, focusing on the CMDF areas and associated equipment. Key themes include pre-installation assessments, field walkthroughs, and identification of issues requiring follow-up. ## By Area / Equipment - **RPL10.CMDF 1/2** - Pre-installation walkthrough completed; measurements taken (Issue #5174 noted). - Horizontal ladder runway needs to be moved 5" from walls for fiber routing (April 30). - **GSIDFNX05** - Measurements taken to ensure rack placements were correct before anchoring. - Issues documented: - Issue #6395: MOFE Door issue. - Issue #6393: Labeling conflict. - Fiber clippings left on the floor; dressing not up to standard, requiring correction by Clear Core (April 30). - **IDFNX5** - Temporary splices of two 192 fibers completed by Clear Core (April 30). - Splicing verified; findings reported for necessary corrections. ## Issues / Open Items - Issue #5174: Documented issue from CMDF 1/2 pre-installation walkthrough (April 28). - Issue #6395: MOFE Door issue in GSIDFNX05 (April 30). - Issue #6393: Labeling conflict in GSIDFNX05 (April 30). - Issue #6394: Concrete hole on East Wall in CMDF1 (April 30). - Issue #6391: Blocked vertical ladder rack locations in CMDF2 (April 30). - Fiber dressing issues in GSIDFNX05 needing correction by Clear Core (April 30). ## Progress / Completed - Pre-installation walkthrough of CMDF 1/2 completed (April 28). - Field walk through GSEF 1/2, CMDF 1/2, and IDFNX5 completed with photos taken (April 30). - Measurements for CMDF2 VCMs verified and met requirements (April 30). ## People Mentioned - Timeon P. - Super Chance - Caleb Bourghs - Richard - Clear Core
Thursday, April 30, 2026
Caleb Bourghs RPL10, CMDF1, CMDF2, GSIDFNX5 · logged 04/30/2026 04:54 PM CT
Started with daily specs, site updates, and team coordination. CMDF1, CMDF2, IDFNX5 Walk Throughs with QA Team. Created 2 Issues- Issue #6394: Concrete has a hole on the East Wall 66 1/2 inches from the South wall in CMDF1. Hole is 2 1/2 inches in length and 1 inch wide. Hole is where the first VCM will be located. Issue #6391: CMDF2 South & West wall vertical ladder rack locations blocked by EPMS/BAS conduit. Other team members placed 3 other issues today we found in the field during our walk-through. Verified specs and measurements for our CMDF2 VCMs on-site. All measurements met requirements and standards. Verified splicing in our IDFNX5. Reported findings to our Super Intendant Chance to contact Clearcore to make needed changes to meet all Splicing specs/Housekeeping.
Timeon P. GSIDFNX05 · logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints. Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below: Issue #6395 GSIDFNX05 MOFE Door Issue #6393 GSIDFNX05 Labeling Conflict Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.
Timeon P. RPL10 GSEF 1/2, CMDF 1/2, IDFNX5 · logged 04/30/2026 01:37 PM CT
Completed a field walk with the FE team through the GSEF's 1/2, CMDF 1/2, and IDFNX5. Photos of the temporary 2 post rack in GSEF 1 for the temporary splices were taken. Temp splices of two 192 fibers in IDFNX5 were completed by Clear Core. SFE Paul informed us that the horizontal ladder runway in both CMDF's will have to move away from their respective walls by approx. 5" to allow for adequate space for the fiber to be routed within the bend radius. The changes will be redlined after installation per Hargis. This will also allow for the horizontal crossovers to be installed with out the overhead support. As the CMDF's have been buildout to spec, the FE's are reviewing to see if this will be a change order.
Tuesday, April 28, 2026
Timeon P. RPL10.CMDF 1/2 · logged 04/30/2026 07:03 AM CT
Completed a pre-installation walkthrough of CMDF 1/2. Took measurements of the room and found one issue, that was documented (Issue #5174).