Daily Log
A running stream of daily inspection notes — what was inspected, where, and the progress. Type, dictate, or scan handwritten notes.2 entries
## Overview
The entries from April 30 to May 1, 2026, detail inspections and quality checks related to rack placements and material verification. Key themes include addressing issues logged in the ACC system and ensuring compliance with specifications.
## By Area / Equipment
- **GSIDFNX05**
- Racks were placed according to prints and measurements were taken to confirm correct locations.
- Issues reported by Super Chance:
- Issue #6395: MOFE Door
- Issue #6393: Labeling Conflict
- Splice cassette alignment reviewed with Chance for compliance with FE labels.
- Observed fiber clippings left by Clear Core; fiber dressing in the 432 can and 1u unican fiber enclosure was substandard, prompting a call for correction.
- **WAREHOUSE, NCB**
- Verified all materials, including 554 two-post racks, through OOR, receivables, and ACC website.
- Created templates for L1 connectivity material.
## Issues / Open Items
- Issue #6395: MOFE Door (2026-04-30)
- Issue #6393: Labeling Conflict (2026-04-30)
- Fiber dressing issues in the 432 can and 1u unican fiber enclosure needing correction (2026-04-30).
## Progress / Completed
- Racks at GSIDFNX05 were confirmed to be placed correctly and measurements taken (2026-04-30).
- All 554 two-post racks in the Warehouse were verified to be up to specifications (2026-05-01).
- Templates for L1 connectivity material were created (2026-05-01).
## People Mentioned
- Timeon P.
- Super Chance
- Richard
- Caleb Bourghs
Friday, May 01, 2026
Caleb Bourghs
WAREHOUSE, NCB
· logged 05/01/2026 03:20 PM CT
Went through all material at Warehouse. Verify all material through OOR, receivables, and ACC website. Verified all 554 tWo post racks were fully up to specs and in good condition. Created all templates for our L1 connectivity materiaL
Thursday, April 30, 2026
Timeon P.
GSIDFNX05
· logged 04/30/2026 04:49 PM CT
Walked CMDF2 and took measurements to ensure that the racks placed were at the correct locations before being anchored. Racks were landed according to prints.
Super Chance informed us about issues he noticed in the field, took pictures and created formal issues in ACC, listed below:
Issue #6395 GSIDFNX05 MOFE Door
Issue #6393 GSIDFNX05 Labeling Conflict
Richard reviewed splice cassette alignment with chance to ensure that they were aligned with the FE labels
Walked the GSIDFNX05 and noticed that Clear Core left fiber clippings on the floor and that the fiber dressing in both the 432 can and the 1u unican fiber enclosure was not up to standard, they were called back to correct the dressing.